Text
'
'
./
/
..
.
g;
,
,
,
.
JUL 1 4 1982
Georgia Power Company
ATTN:
Mr. R. J. Kelly
Executive Vice President
P. O. Box 4545
Atlanta, GA 30302
Gentlemen:
-424/82 N
Subject:
Report Nos.
16 and 50-425/82-16
This refers to the routine safety inspection conducted by Mr. N. Merriweather of
this office on June 22-25, 1982, of activities authorized by NRC Construction
Permit Nos. CPPR-108 and CPPR-109 for the Vogtle facility.
Our preliminary
findings were discussed with Mr. H. Googe, Assistant Construction Project
Manager, at the conclusion of the inspection.
Areas examined during the inspection and our findings are discussed in the
enclosed inspection report.
Within these areas, the inspection consisted of
selective examinations of procedures and representative records, interviews with
personnel, and observations by the inspector.
During the inspection, it was found that certain activities under your license
appear to -violate NRC requirements.
This item and references to pertinent
requirements are listed in the Notice of Violation enclosed herewith as Appen-
dix A.
Elements to be included in your response are delineated in Appendix A.
In accordance with 10 CFR 2 790(a), a copy of this letter and the enclosures will
be placed in the NRC's Public Document Room unless you notify this office, by
telephone, within ten days of the date of this letter and submit written appli-
i
cation to withhold information contained therein within thirty days of the date
'
of this letter.
Such application must be consistent with the requirements of
2.790(b)(1).
The responses directed by this letter and the enclosures are not subject to the
clearance procedures of the Office of Management and Budget as required by the
Paperwork Reduction Act of 1980, pL 96-511.-
Should you have any questions concerning this letter, we will be glad to discuss
them with you.
Sincerely,
H. C. Dance, Chief
Reactor Projects Branch 2
Division of Project and
Resident Programs
Enclosures:
See Page 2
8209160602 820817
PDR ADOCK 05000424
G
- . . .
. -
. .
. . -
&-
-
4
,
.
-
JUL 14 1982
Georgia Power Company
2
Enclosures:
1.
Appendix A. Notice of Violation
2.
Inspection Report Nos. 50-424/82-16
and 50-425/82-16
cc w/ encl:
H. H. Gregory. III, Construction
Project Manager
E. D. Groover, QA Site Supervisor
D. O. Foster, Project General Manager
M. Manry, Plant Manager
bcc w/ encl:
NRC Resident Inspector
Document Management Branch
State of Georgia
//
)?>
n
,
R
./
RII
RII
RII
-
jg
p
f
Herdt
JRogge
HCD ce
NMer.fweather:ht
TECon on
7/ /82
7/ /82
7/f3/8.2
7/,q/82
7/g/82
.