Advises That Submittal of Tech Spec Revs,Per 830620 Commitment,Will Be Delayed Until 830930 Due to Delays in Completing Startup Testing
ML20024F176
Person / Time
Site: Brunswick  
Issue date: 09/02/1983
From: Howe P
CAROLINA POWER & LIGHT CO.
To: Vassallo D
Office of Nuclear Reactor Regulation
References
LAP-83-409, NUDOCS 8309090002
Download: ML20024F176 (1)


Text

.

CD&L SERIAL: LAP-83-409 Carolina Power & Light Cornpany SEP 021983 Director of Nuclear Reactor Regulation Attention:

Mr. D. B. Vassallo, Chief Operating Reactors Branch No. 2 j

Division of Licensing United States Nuclear Regulatory Commission Washington, DC 20555 BRUNSWICK STEAM ELECTRIC PLANT, UNIT NOS. 1 AND 2 DOCKET NOS. 50-325 AND 50-324 LICENSE NOS. DPR-71 AND DPR-62 NRC REQUESTED TECHNICAL SPECIFICATION REVISIONS REVISED SCHEDULE FOR SUBMITTAL

Dear Mr. Vassallo:

By letter dated June 20, 1983 (Serial: LAP-83-233), Carolina Power & Light Company (CP&L) agreed to submit proposed Technical Specification (TS) revisions relating to the main turbine bypass system and the feedwater/ main turbine trip system actuation instrumentation within 30 days of Brunswick-1 start-up. Due to unanticipated delays in completing the Brunswick-1 start-up testing and the resulting additional workload placed on plant engineering and operations personnel, CP&L has been unable to complete preparation and review of the subject TS revisions. Therefore, CP&L has rescheduled the submittal of the necessary TS revisions to September 30, 1983. We will continue to inform the NRR Project Manager of the status of the TS revisions.

If you have any questions concerning this schedule, please contact our staff.

Yours very trul,

8309090002 830902

~s PDR ADOCK 05000324

-1 p

PDR j

P. W. Howe Vice President Brunswick Nuclear Project WRM/cce (7804WRM) cc:

Mr. D. O. Myers (NRC-BSEP)

Mr. J. P. O'Reilly (NRC-RII) l Mr. S. D. MacKay (NRC) y 411 Fayetteville Street e P. O. Box 1551