Responds to NRC Re Violations Noted in IE Insp Repts 50-348/83-17 & 50-364/83-15.Corrective Actions: Personnel Instructed to Cover Open Instrument Air Lines If Left Unattended & Procedure FNP-0-AP-44.0 to Be Revised
ML20024E751
Person / Time
Site: Farley  Southern Nuclear icon.png
Issue date: 08/03/1983
From: Clayton F
ALABAMA POWER CO.
To: Verrelli D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
Shared Package
ML20024E748 List:
References
NUDOCS 8309070018
Download: ML20024E751 (2)


Text

,, 4 Mamng Address Alabama Power Company a

600 North 18th Street Post Office Box 2641 Crmingham, Alabama 35291 0$N8C,8g)gg 'j

. Telephone 205 783-6081 gg F. L Clayton, Jr.

Senior Vice President AlabamaPbwer Flintridge Building B3 MG 'd A8 August 3, 1983 Docket No. 50-348 Docket No. 50-364 Mr. D. M. Verrelli U. S. Regulatory Commission Region II 101 Marietta Street, N.W.

Suite 3100 Atlanta, GA 30303

SUBJECT:

J. M. Farley Nuclear Plant NRC Inspection Of 5/16 - 6/10, 1983 RE:

Report Numbers 50-348/83-17 50-364/83-15

Dear Mr. Verrelli:

This letter refers to the violation cited in the subject inspection reports which states:

"As a result of the inspection conducted on May 16 - June 10,1983, and in accordance with the NRC Enforcement Policy, 47 FR 9987 (March 9, 1982), the following violation was identified.

Technical Specification 6.8 requires in part, that ' written procedures shall be established, implemented and maintained.'

Contrary to the above on May 19, 1983, while repair work was in progress on Unit 2 turbine driven auxiliary feedwater pump steam stop valve (HV-3226), control air (instrument ai r) lines which had been disconnected from the valve and controller were not protected as requi red by FNP-0-AP-44.0, ' Cleanliness of Fluid Systems and Associated Components. '"

Admission or Denial The above violation occurred as described in the subject report.

hp O

G

g, Mr. D. M. Verrelli '

F.: L. Clayton, J r.

August 3,:1983 Page 2 -

' Reason for Violation

' This violation was due to a combination of personnel error and procedural inadequacy.-

The I

& C personnel failed to ' cap the disconnected air line because FNP-0-AP-44 (Cleanliness of Fluid Systems and Associated Components) did not explicitly list instrument air as a system requiring Class-B cleanliness.

Corrective Action Taken and Results Achieved I & C personnel have been instructed to cover open instrument air

' lines if they are to be left unattended and to continue the practice of blowing down the lines prior to reconnection.

In addition, FNP-0-AP-44 will be revised to add instrument air to the list of systems requiring Class B cleanliness.

Corrective Steps Taken to Avoid Further Violations See above.

All corrective action is scheduled to be completed by August 5, 1983.

Date of Full Compliance May 19, 1983.

Af fi rmation I affirm that this response is true and complete to the best of my knowledge, information and belief.

The information contained in this letter is not considered to be of a proprietary nature.

Yours very truly, f

W )r F. L. Clayton, r.