s-e 000.JEJED LAW OFFICES OF DEBEVOISE & LIBERMAN 8200 S EVE NTEENTH STREET,N.W
'83 JU.113 P3 :56
~ ~'~aro~ o e = = =*
TELEPHONE (202) S57-9800 June 10, 1983 Morton Margulies, Esq.
Mr. Frederick J.
Shon Chairman, Atomic Safety Atomic Safety and Licensing and Licensing Board Board U.
S.
Nuclear Regulatory U. S.
Nuclear Regulatory Commission Commission Washington, D.
C.
20555 Washington, D. C.
20555 Dr. James H.
Carpenter Atomic Safety and Licensing Board U.
S. Nuclear Regulatory Commission Washington, D.
C.
20555 Re:
Washington Pub?.ic Power Supply System (WPPSS Nuclear Project No. 3)
Docket No. 50-508 Gentlemen:
Attached for your information is a copy of a letter from the Washington Public Power Supply System, the Applicant in the captioned proceeding, to the NRC Staff advising it of a thirty-day slow down in the construction of WNP-3 and possible additional construction delays.
We provide this letter to the Board mindful of our responsibilities to apprise the Board of developments bearingonmatterswithinitsjurisdlcton.
Sincerely l
- Nichol, S.
Reynolds Counsel for Applicant L
Attachment cc:
Service List 8306150354 830610
}fh,()
PDR ADOCK 05000508 o
PDR l
Washington Public Power Supply System 3000 George Washington Way P.O. Box 968 Richland, Washington 99352-0968 (509)372-5000 June 3, 1983 G03-83-451 Harold R. Denton, Director Office of Nuclear Reactor Regulation US Nuclear Regulatory Commission Washington, DC 20555
Dear Mr. Denton:
On May 27, 1983, the Washington Public Power Supply System implementec a slowdown of constructior, on Project No. 3 for a period of 30 days. The reason for this action is that construction funds are nearly exhausted and the Supply System has been unable to secure financing from the municipal bond market necessary to continue construction. During the 30 day slowdown period, the Supply System will attempt to obtain alternate sources of financing.
If successful, construction will be restarted with no change in the project completion schedule; if not, further construction delays will be necessary.
In the eventuality that near term financing is unavailable, detailed plans are being developed for a possible 3 year extension of the WNP-3 scheduled completion date.
Activities essential to preservation of the physical plant and maintaining the Construction Permit will be continued throughtout all periods of construction delay. The Supply System and Bonneville Power Administration remain firmly committed to protection of the regions investment in this plant and to the completion of the WNP-3 facility on a schedule consistent with regional power needs.
Very truly yours, A
G. D. Bouchey, Manager Nuclear Safety and Regulatory Programs l