ML20023C509

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-508/83-03 on 830314-17.Noncompliance Noted: Failure to Qualify Weld Procedure in Accordance W/Aws D.1.1 Requirements
ML20023C509
Person / Time
Site: Satsop
Issue date: 04/07/1983
From: Burdoin J, Dodds R, Haist D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML20023C502 List:
References
50-508-83-03, 50-508-83-3, NUDOCS 8305170390
Download: ML20023C509 (8)


See also: IR 05000508/1983003

Text

.

U. S. NUCLEAR REGULATORY COMMISSION

REGION V

Report No.

50-508/83-03

Docket No.

50-508

Licensee:

Washington Public Power Supply System

P. O. Box 1223

Elma, Washington 98541

Facility Name: Washington Nuclear Project No. 3 (WNP-3)

Inspection at: WNP-3 Site (SATS0P)

Inspection conducted:

March 14-17, 1983

Inspectors:

A-

v/

f/7/63

II. P. HVist, Reactor Inspector

Dite' Signed

9-

H ,$>

47N3

3. F. ]!urdoinf Reactor Inspector

Dat'e Signed

Approved By:

[./ / b

'/!7N3

R. T. )fodds,' Chief, Reactor Projects

Dfits Signed

Sectida No. 1, Reactor Projects Branch No. 1

Summary:

Inspection during the period of March 14-17, 1983 (Report

No. 50-508/83-03)

Areas Inspected: Routine, unannounced inspection by regional-based

inspectors of construction activities including: reactor vessel internals

installation and welding; electrical component and cable installation;

and licensee action on previously unresolved and follow-up items.

The inspection involved 60 inspection-hours onsite by two NRC inspectors

and 20 inspection-hours in-office by on NRC inspector.

Results: One deviation was identified (failure to qualify a weld

procedure in accordance with AWS D.1.1 requirements

paragraph 4).

8305170390 830408

PDR ADOCK 05000508

G

PDR

_

_

_

.

.

DETAILS

1.

Persons Contacted

The inspectors interviewed various engineering, management,-inspection,

and construction personnel of the organizations listed below. Key

personnel, including those who attended the exit interview, are

identified below.

a.

Washington Public Power Supply System (WPPSS)

  • 0.

E. Trapp, Project Quality Assurance Manager

  • J. A. Puzauskas, Quality Assurance Supervisor
  • M.

F. Keller, Project Engineer

  • J. E. Werle, Project Engineering Manager
  • D. S. Feldman, Plant Quality Assurance Manager
  • D. R. Coody, Quality Assurance Engineer
  • C.

Butros, Field Engineer

C.

Tewksbury, Quality Assurance Supervisor

b.

Ebasco Services, Inc. (Ebasco)

  • A. M. Cutrona, Quality Assurance Manager
  • W. K. Drinkard, Quality Assurance Engineer
  • L.

A. Bast, Quality Assurance Engineering Supervisor

  • J.

Ruimerman, Project Engineer

  • J.

P. Sluka, Manager of Engineering

  • K.J.

Giadrosich, Quality Assurance Engineer

J. D. May, Quality Assurance Engineer

  • P. J. Massman, Quality Assurance Engineer

G. L. Harrison, Quality Assurance Records

M. J. Rackley, Project Startup Manager

H. D. Laford, Unit 3 Manager

R. E. Abel, Quality Assurance Engineer

M. R. Mooney, Lead Electrical Surveillance Inspector

V. J. Lovelace, Audit Supervisor

c.

Combustion Engineering (CE)

R. E. Claar, Quality Assurance Representative, CE Avery

L.

Lehman, Quality Assurance Site Representative

R.

Taisey, Field Engineering

R.

Hicks, Quality Assurance Inspector

E.

Shenk, Installation Manager

d.

Fischbach/ Moore (F/M)

B. G. Ashby, Project Quality Control Manager

L. A. Woolridge, Electrical Construction Superintendent

R. D. Brown, Quality Control Supervisor

E. G. Courtney, Quality Control Documents Supervisor

L. A. Beach, Cable Pulling Superintendent

_ _ _ - -

,

,

,

__

, _ ,

_ _ _ _

2

-

R. G. Frank, Cable Pulling Engineer

L. L. Bickar, Cable Yard Controller

J. R. Vrooman, Cable Yard Quality Control Inspector

N. H. Powell, Electrical Terminations Superintendent

e.

Peter Kiewit Sons Co. (PKS)

'

.

F. Wisner, Project Quality Assurance Manager

E. Tosh, Quality Assurance Administration Manager

'

S. W. Scott, Quality Control Manager

P. A. Smith, Assistant Quality Control Manager-

M. E. Loennig, Equipment Erection Engineer

  • Denotes attendance at exit interview on March 17, 1983- .

2.

Construction Status

The licensee reported that Unit 3 construction was 72 percent complete on-

March 1, 1983. The WPPSS Executive Board directed immediate

implementation of a four-day work week for all supply system and

contractor personnel at Unit 3 on February 25, 1983. This action was

taken in order to extend construction funds until summer of 1983.

It is

expected that an appeal on Initiative 394 as well as litigation

associsted with the termination of Supply System projects WNP-4/5 will be

sufficiently resolved by July 1983 to permit the Licensee to sell bonds

and resume full construction at WNP-3.

Currently, Supply System

perscnnel and crafts are working four days a week. Ebasco and contractor

salaried personnel are continuing to work five days a week.

3.

Site Tour

The inspectors conducted a tour of Unit 3 on March 14, 1983, to observe

completed work, work in progress, and storage and maintenance of

safety-related equipment.

,

No items of noncompliance or deviations were identified.

4.

Licensee Action on Previously Unresolved and Follow-up Items

a.

(Closed) Unresolved Item (50-508/83-02/02)-Ebasco Deviation From

AWS Joint Qualification Provisions

The inspector had previously examined a project change proposal

which modified the mounting details of the upper main steam

restraint assemblies. The project change proposal involved the use

l

of a non prequalified AWS D.1.1 joint without the weld procedure

l

qualification tests required by Section 5.2 of AWS D.1.1.

The

l

Engineer relieved the construction contractor of the AWS joint

l

qualification requirements based on a judgment that the

l

code-required macroscopic examination would not produce any relevant

!

information.

l

The WNP-3 Final Safety Analysis Report, Section 3.8.3.2.1.(c)

specifies that the design, fabrication, erection and inspection and

1

l

,

- . , . , - - ,-

- - - - , ,

.-

-

-

w

- - ,

- - - .

-...-a

-. - _ _ _ __ - - ______- __ _ __________ . _ _ _ _ _ _ _ _ _ _ - _ _ _ _ - _ , _ - _

_ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

'

,.

3

.

.

testing of the steel internal structures of the pipe rupture

restraints complies with the AWS Structural Welding Code DI.1-79.

Paragraph 2.6.2 of this code specifies that joints may depart from

the details of prequalified joints only if the contractor submits to

the Engineer his proposed joints and joint welding procedures and at

his own expense demonstrates their adequacy in accordance with the

requirementr: of Section 5.2.

Section 5.2 states that, except for

prequalifico joints, " welding procedures which are to be employed in

executing contract work under this code shall be qualified prior of

use, to the satisfaction of the Engineer, by tests as prescribed in

Part B of this section." Contrary to the above commitments, a weld

joint which does not meet the AWS Dl.1 prequalified joint

requirements was authorized for use on the upper main steam pipe

rupture restraints without prior qualification in accordance .with

,

Section 5.2 by Project Change Proposal No. 35Q-14386. A Safety

'

i

Analysis Report deviation notice has not been initiated to describe

this deviation from the AWS Structural Welding Code. This is an

apparent deviation.

(50-508/83-03/01)

t

b.

(Closed) Unresolved Item (50-508/82-26/01) - Cleanliness Controls

for Core Internals Work

The inspector had previously questioned whether the controls

established for access and cleanliness were consistent and workable,

and whether these controls were being satisfactorily implemented.

The installation contractor, Combustion Engineering has recently

revised the applicable procedure, No. AS-P-019, " Housekeeping and

Cleanliness Procedure," to designate the entire reactor cavity area

Zone III and now applies personnel and material accountability

controls at the entrance to the cavity. The Zone level and

applicable restrictions are conspicuously posted and enforced.

Machined surfaces, such as the reactor vessel flange are protected

and the reactor cavity area cleanliness has improved. This item is

considered closed.

c.

(Closed) Follow-up Item (50-508/83-01/01) - Quality of CE Ring

Forgings for Core Internals Components

The inspector had previously expressed concern over apparent forging

laps which appeared in the lower ring forging of the core support-

barrel during performance of the flexure weld. Specifically, the

inspector questioned whether the apparent laps were an isolated

,

instance which could not affect the other three forged rings in the

'

reactor internals.

Combustion Engineering responded to these and other concerns by

>

researching the origin of the ring forging and by performing

nondestructive volumetric examinations of the core support barrel

ring forging. CE also performed an evaluation of the identified.

indications for 10 CFR 50.55(e) reportability.

The forging used for the WNP-3 flexure membrane was supplied by

Standard Steel.

Standard Steel supplied 9 flexure membrane forgings

__ , _ _ _ _ _ _ _ _ _ - - _ . _ _ _ _ _ . - _ - . _ _ . _ - . _ _ _ _ _ _ _ _ _ _ ~

. _ - . - -

--

.__

4

.

.

for System 80 reactor vessel internals. Each of these forgings were

of a different heat. All of.the other forgings used in the WNP-3

reactor vessel internals were supplied by Terut-Siderius. An

analytical study was conducted to review the significance of

observed indications and potential structural anomalies, if found.

CE also reviewed the manufacturing and engineering requirements to

verify the adequacy of the WNP-3 core support barrel-lower forging

design and fabrication. The results of this review indicate that:

(1) the forging design and fabrication requirements are conservative

with respect to the indications observed, as well as other'

postulated scenarios such as the potential for indication

propagation, and; (2) that the item is'not reportable under 10 CFR

50.55(e).

s-

,

Ultrasonic examinations were performed on the WNP-3 forging using a

,'

calibration block made from a Standard Steel-supplied forging for a

TVA plant. The calibration block was a full scale sample which

exactly simulated the WNP-3 forging. A series of calibration holes

were machined into the calibration block and on January 21, 1983,

the flexure membrane was subjected to a 3-directional shear wave

-examination: axially, both upward and downward, and

circumferential1y, one direction clockwise. The flexure membrane

was also subjected to a 2-directional straight beam-axially upward

-

and radially outward. The total forged mass was also subjected to a

2-directional straight-beam radially inward and axially upward.

This examination was performed at 1/2 the originally required design

maximum indication size and at double sensitivity. The examination

disclosed no reportable. indications.

The inspector examined the ultrasonic examination procedure and

calibration block used to perform the examinations. The technique

appeared to result in a adequate examination of the WNP-3 ring

forging and flexure membrane. The investigations by CE appear to

adequately demonstrate that these indications are an isolated

incident on the WNP-3 core internals. The information provided by

CE will be transmitted to the NRC Region IV, Vendor Inspection

Branch for information. This item is considered closed.

5.

Electrical Component and Cable Installation Fischbach-Moore

a.

Observation of Work

The inspector examined receiving inspection, identification,

storage, handling, installation, and quality control inspection

activities for the following electrical components to determine

completeness and conformance with the contractor's applicable

installation and quality control inspection procedures:

!

Battery Racks (Train A)

125V DC Switchgear (Train B)

l

Auxiliary Feedwater Pump Motor B

HPSI Pump Motor A

Containment Spray Valves (2CS-V-S079-SAR and 2CS-V-S080-SBR)

!

. - - - .

.

.

- ._.

.

..

. - .

. .-

~ - _._-_

.

_ _ - .

..

.

._

-_

_--

-

>..

,

S

.

,

'

.

,

-

l

,

,

>The; installation of cables started in December 1982, with less than

,

.10 percent of the cables pulled to-date. The inspection of

-

-

. installed cable included receiving, storage,. identification and

,

,' . control ~, installation, termination, and quality control inspection

>

activities for completeness and conformance with applicable

~

i

. installation and' quality control inspection procedures.

~

_No items'of noncompliance or deviations were identified.

,

.,

,

b.

Review of Quality; Records

!

The quality records for installation of 120 Volt instrument and

control cables were examined for completeness and conformance with

applicable installation and quality procedures. The specific

.

activities, examined were receipt inspection, storage, handling,

installation, termination, and identification from receipt through

'

installation and termination.

No items of noncompliance or deviations were identified.

,

'

6.

Reactor Vessel Internals-Combustion Engineering

a.

Review of Quality Assurance Implementing Procedures

The inspector reviewed the following quality assurance implem'nting

e

procedures for conformance with the contractor's quality assurance

field manual, the FSAR, the ASME B&PV Code Section III, and industry

standards:

Procedure No.

Title

IG-8973-RCE-400

Reactor Vessel Internals Instruction

,

Manual

SPS-652500

Site Process Sheet - Install and Weld

j

Flow Baffle

1

AS-P-019

Housekeeping and Cleanliness Procedure

AS-P-012

Filler Metal Control Procedure

SPS-650100

Removal of Tie Rods

1

SPS-650600

Site Process Sheet-Remachine Tie Rod

1

Holes

'

DWP-VI-35-43.43-1

Detailed Welding Procedure

i

l

DWP-RP-35-4

Detailed Welding Procedure

i

GTA-43.43-2G-1

Procedure Qualification Record

--

!

'SMA-43.43-1G-2(s)

Procedure Qualification Record

,

i

m

,..,.._.w

,- , . .

.u_,

-

6

.

.

<The inspector noted, during observation of work and examination of

weld filler metal controls, that the contractor is using portable

filler metal ovens to maintain hydrogen control in covered

ele'ctrodes but does not periodically check the adequacy of the

protable oven temperature control nor calibrate the thermometers

attached to the portable ovens. Following identification of this

item,'the portable filler metal oven in use was checked with a

calibrated thermocouple and found to be adequately controlling

. filler metal temperature above 250 degrees, farenheit. The

contractor has initiated a revision to procedure No. AS-P-012 to

require weekly temperature checks.

No items of noncompliance or deviations were identified.

b.

Observation of Work and Work Activities

The inspector examined work activities which included installation

of the flow baffle, remachining of tie rod holes in the upper guide

structure, and marking the core shroud for minor grinding to meet

core envelope requirements. Attributes examined in connection with

flow baffle activities included: verification of site process sheet

preparation and sign-off; completion of preliminary measurements

prior to initiation of welding; qualification of weld procedure

specifications and welders; verification of base materials for

welding; weld filler metal control; verification of proper back

gouging and satisfactory liquid penetrant examination of root

passes; welding and interpass cleaning technique; interpass

temperature control; and control on grinding operations. Attributes

examined in connection with remachining on the upper guide structure

included verification of site process sheet preparation and signoff

and machining of one tie rod hole in preparation for threading.

The inspector identified a linear indication in excess of one inch

long on a portion of a flow baffle flange. The contractor examined

the documentation which accompanied the flow baffle from the factory

but was unable to determine if the indication was previously

identified. The contractor has initiated a deviation notice and is

continuing to investigate the circumstances behind the linear

indication. This item will be examined in the future. Follow-up

Item (50-508/83-03/02).

The inspector questioned the need for and prior authorization for

grinding operations which encroached into the flow baffle base

material adjacent to the attachment welds. Although the applicable

site process sheet did not authorize the grinding during the root

pass back gouging, it appears that engineering and quality assurance

personnel discussed the necessity for cutting into base metal due to

the limited access and unavailability of grinding tools which could

be used to back gouge the weld without disturbing the adjacent base

material.

It appears the contractor quality assurance personnel are

now aware of the need to authorize such operations, in writing,

prior to commencement. The base metal areas requiring repair have

been identified on a deviation notice and a repair welding procedure

exists.

,

_,

_

-

_

.

,

.

_... -

-_ _ .

.

.

7

,

'

No items of noncompliance or deviations were identified.

c.

Review of Quality Records

,

The inspector reviewed the following quality records for_ conformance

with the contractor's field quality assurance manual and

implementing procedures, the ASME B&PV Code Section III, and

industry standards:

  • Site Process Sheet No. 652500 (partially completed) for

installation of flow baffle

  • Site Process Sheet No. 650600 (partially completed) for

remachining tie rod holes

Nondestructive examination reports for flow baffle root pass

welds

Welder qualification records for welder Nos. BM-03 and BM-06

ENiCrFe 3-1/8 inch weld filler metal (inconel) material

'*

certifications

No items of noncompliance of deviations were identified

d.

Surveillance: Activities

The inspector examined reports of twelve surveillances of reactor

internals activities by Ebasco during the December through January

time period. Activities examined by Ebasco included welder

qualification, flexure welding, use of site traveller,_ weld

inspection, tool and gage calibration, optical training, weld

repairs'on core barrel forging, liquid penetrant examination, and

receiving inspection.

Generally, the surveillance reports examined and the findings

identified indicate a substantial improvement in the quality of the

Ebasco survei.llance program. The surveillance reports clearly

delineate the activity examined, the requirements to be adhered to

during the activity-and the acceptance standards, and the findings

of the surveillance. The reports demonstrate adequate preparation

by the surveillance inspector prior to the surveillance. The

j

scheduling of surveillance activities appears to have substantially

improved. The six month and four week construction schedules are

'

considered when scheduling surveillance activities as are the

findings of the quality assurance audit group, the quality assurance

engineering group, and the NRC.

I

7.

Management Meeting

,

The inspectors met with the licensee and management personnel denoted in

paragraph 1 at the conclusion of the inspection on March 17, 1983. The

inspectors discussed the scope and findings of the inspection. The

findings were acknowledged by the licensee.

(

,

T

.,--#

%

<.,m-

y

--.

._.,--m.

,m_.,v-.-.-

-,.,.,m,

, . , . ,

r

-,,-- -., . - -_ --,- . - - - ~

, . , , . , - , - , - - , , .