Text
,
y
%%
-
MR 0 91930
Docket No. 50-336
Northeast Nuclear Energy Company
ATTN: Mr. . Edward J. Mroczka
Senior Vice President - Nuclear
Engineering and Operations
'
P.O. Box 270
Hartford, Connecticut
06141-0270
Gentlemen:
Subject: NRC Region I Inspection No. 50-336/89-24
This refers to the routine resident safety inspection condv ced by
Mr. P. Habighorst of this office on December 5,1989 - January 19, 1990, at
Millstone Nuclear Power Station, Unit 2, Waterford, Connecticut, of activities
authorized by NRC License No. DPR-65 and to the discussions of our findings
held by Mr. Habighorst with Messrs. S. Scace and J. Keenan of your staff at the
conclusion of the inspection.
Areas examined during this inspection are described in the NRC Region I
inspection report which is enclosed with this letter. Within these areas, the
inspection consisted of observation of activities, interviews with personnel,
measurements and document reviews.
Based on the results of this inspection, it appears that one of your activities
was not conducted in full compliance with NRC requirements, as set forth-in the
Notice of Violation enclosed herewith as Appendix.A.
The licensee-identified
violation involved operation of the facility in cold shutdown for a period of
29 hours3.356481e-4 days <br />0.00806 hours <br />4.794974e-5 weeks <br />1.10345e-5 months <br /> without an operable containment gaseous and particulate radiation
monitor. You reported this event in Licensee Event Report (LER)89-009.
This
violation has been categorized by severity. level in accordance with the
" General Statement of Policy and Procedure for NRC Enforcement Actions," 10 CFR Part 2, Appendix C (Enforcement Policy). You are required to respond to this
letter and in preparing your response, you should follow the instructions in
Appendix A.
In review of the apparent violation, NRC inspection identified two deficiencies
not recognized or reported in LER 89-009; specifically, the failure to identify
an-additional technical specification limiting condition for operation appli-
cable to the event; and secondly, an inaccurate time interval for the
out-of-service radiation monitors. Our independent review determined that a
plant vulnerability existed based on plant decay heat rate and reduced
inventory operation at the time of the event. Therefore, in your response to
this letter .you are requested to address LER accuracy and your assessment of
plant vulnerability during the event.
OFFICIAL RECORD COPY
IR MILL 2 89-24 - 0001.0.0
03/08/90
g
9003200425 90030p
,
ADOCK 05000336
0
l {
}
7
'
N
- %) ,
.
g
L
Northeast Nuclear Energy Company
2
i
L
With regards to matters discussed in section 8.3 of the enclosed inspection
report regarding LER 89-011, we are concerned about the apparent untimely
notification and reporting of the incorrect location of the air supply check
valve for a service water isolation valve.
The deficiency was identified on
September 6,1989, but the event was not reported until. January 5,1990. You
are requested to respond to this concern.
Please submit to this office, within
thirty days of the date of this letter, a written explanation in reply,
including; (1) your assessment of when the service water system deficiency
should have been reported and (2) the steps which have or will be taken to
assure timely notification and reporting of events or. conditions as required by
.
10CFR 50.72 and 10CFR 50.73. This response may be appended to your response to
[
a similar request for an event at Millstone Unit 3 as documented in inspection
l
report 50-423/89-23.
!
The response directed by this letter and the accompanying notice is not subject
to the clearance procedures of the Office of Management and Budget as required
by the Paperwork Reduction Act of 1980, PL-96-511.
Your cooperation with us in this matter is appreciated.
Sincerely,
ORIGINAL StGNED BY:
Edward C. Wenzinger, Chief
Projects Branch No. 4
Division of Reactor Projects
Enclosures:
1. Appendix A, Notice of Violation
2. NRC Region I Inspection Report No. 50-336/89-24
cc w/encis:
W. D. Romberg, Vice President, Nuclear Operations
S. E. Scace, Nuclear Station Director, Millstone Station
.J. S..Keenan, Nuclear Unit Director, Millstone Unit 2
D. O. Nordquist, Director of Quality Services
R. M. Kacich, Manager, Generation Facilities Licensing
Gerald Garfield, Esquire
Public Document Room (PDR)
Local Public Document Room (LPOR)
Nuclear Safety Information Center (NSIC)
NRC Senior Resident Inspector
State of Connecticut
4
0FFICIAL RECORD COPY
IR MILL 2 89-24 - 0001.1.0
11/29/80
._
___
_ _ _ _ _ - _ _ - _ _ - _ _ - _ _ _ _ _ - _ - . _ _ _ _ _ _ _ _ _ . - _ _ _ _ _ _ _ _ _ _ _ _ _ .
w,
.. _ .;n ,
.
-
. .
Northeast Nuclear Energy Company
3
bec w/encis:
Region I Docket Room (with concurrences)
Management Assistant, DRMA (w/o enclosures)
D. Haverkamp, DRP
J. Shediosky, SRI, Haddam Neck
P. Habighorst, RI, Millstone 2
G. Vissing, NRR/PD14
R. Paolino, DRS (See Section 6.1.1 and 8.2.1)
M. Conner, DRP (3ee Section 7.2)
R. Keimig DRSS (See Section 7.2)
,
RI:DR
RI
R
P
PH
orst/geb
WRaymond
DHa
'r
mp
Ekiger
03/3/90
03/7/90
03/I/90
03
/90
0FFICIAL RECORD COPY
IR ILL2 89-24 - 0004.0.0
03/ 8/90