ML20011A990
| ML20011A990 | |
| Person / Time | |
|---|---|
| Site: | Bellefonte |
| Issue date: | 10/26/1981 |
| From: | Mills L TENNESSEE VALLEY AUTHORITY |
| To: | James O'Reilly NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| References | |
| 10CFR-050.55E, 10CFR-50.55E, NCR-1173, NUDOCS 8111030494 | |
| Download: ML20011A990 (1) | |
Text
_
TENNESSEE VALLEY ALU$fGOMGION ::
CH ATTANOOGA, TENNESSE 6
400ChestnutStreetTo[erII8 0C T 28 A 9 : 1g October 26, 1981
.Mr. James P. O'Reilly, Director Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission Region II - Suite 3100 101 Marietta Street Atlanta, Georgia 30303
Dear Mr. O'Reilly:
BELLEFONTE NUCLEAR PLANT UNIT 2 - WELDING OF STRUCTURAL STEEL ANNULUS FLOOR -
FRAMING - NCR 1173 - SEVENTH INTERIM REPORT The subject nonconformance was initially reported to NRC-0IE Inspector R. W. Wright on April 15, 1980, in accordance with:10 CFR 50.55(e). This was followed by our interim reports dated May 15, July 30, and November 7, 1980, and February 20, June 23, and July 28, 1981. Approximately 456 welds have been reinspected from the 566 weld samples selected per MIL-Standard 105D. TVA is continuing the reinspection of the remaining. welds. We expect to submit our next written report by February 10, 1982.
If you have any questions concerning this matter, please get in touch with R. H. Shell at FTS 857-2581.
Very truly yours, TENNESSEE VALLEY AUTHORITY
-h i
L. M. Mills,-
nager Nuclear Regulation and Safety cc:
Mr. Victor Stello, Jr., Director Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission Washington, DC 20555 p7 ll0 ojjjj6 0
Phk An Equal Opportunity Ernployer