ML20009D964
| ML20009D964 | |
| Person / Time | |
|---|---|
| Site: | North Anna |
| Issue date: | 05/28/1981 |
| From: | Robert Lewis NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| To: | Ferguson J VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.) |
| Shared Package | |
| ML20009D952 | List: |
| References | |
| NUDOCS 8107240537 | |
| Download: ML20009D964 (2) | |
See also: IR 05000338/1981013
Text
a
.p aw
OFFICIAL COPY
.
hy
o
UNITED STATES
g
8}
NUCLEAR REGULATORY COMMISSION
,
g
r
REGION 11
- '
- #
o
101 MARIETTA ST., N.W., sulTE 310o
ATLANTA, GEORGIA 30303
.....
W 2 81981
Virginia Electric and Power Company
ATTN:
J. H. Ferguson
Executive Vice President-Power
P. O. Box 26666
Richmond, VA 23261
Gentlemen:
Subject: Report Nos. 50-338/81-13 and 50-339/81-10
This refers to the routine inspection conducted by Mr. E. H. Webster of this
office on April 6 - May 5,1981, of activities authorized by NRC License Nos.
NPF-4 and NPF-7 for the North Anna facility.
Our preliminary findings were
discussed with Mr. E. W. Harrell, Assistant Station Manager, at the conclusion of
the inspection.
Areas examined dt. ring the inspection' and our findings are discussed in the
enclosed inspection report.
Within these areas, the inspection consisted of
selective examinations of procedures and representative records, interviews with
per sonnel, and observations by the inspector.
During the inspection, it was found that certain activities under your license
appear to violate NRC requirements.
This item and references to pertinent
requirements are listed in the Notice of Violation enclosed oerewith as
Appendix A.
Elements to be included in your response are delineated in
Appendix A.
,,
In accordance with 10 CFR 2.790 of the Commission's regulations, a copy of this
letter and the enclosed report will be placed in the NRC's Public Document Room.
If the report' contains any information that you believe to be exempt from
disclosure under 10 CFR 9.5(a)(4), it is necessary that you:
(a) notify this
office by telephone within ten days from the date of this letter of your
intention to file a request for withholding; and (b) submit within twenty-five
days from the date of this letter a written application to this office to
withhold such information.
If your receipt of this letter has been delayed such
that less than seven days are available for your review, please notify this
office promptly so that a new due date may be established.
Consistent with
section 2.790(b)(1), such application must be accompanied by an affidavit
executed by the owner of the information which identifies the document or part
thereof sought to be withheld, and a full statement of the reasons on the basis
of which it is claimed that the information should be withheld from public
disclosure.
This section f u r'.h e r requires the statement to address with
i
specificity the considerations listed in 10 CFR 2.790(b)(4).
The information
sought to be withheld shall be incorporated as far as possible into a separate
part of the affidavit. If we dc not hear from you in this regard within the
-
'C
[
.
-
.
,
,'
~'
.
Virginia Electric and Power
2
Company
specified periods noted above, the report will be placed in the Public Document
Room.
Should you have any questions concerning this letter, we will be glad to discuss
them w.ith you.
Sincerely,
.
5.[.
R. C. L_ sis, Acting Director
Division of Resident and
Reactor Project Inspection
Enclosures:
1.
Appendix A, Notice of Violation
2.
Inspection Report Nos. 50-338/81-13
50-339/81-10
cc w/ encl:
W. R. Cartwright, Station Manager
P. G. Perry, Senior Resident Engineer
,