r
'
,.
por
.
OFFICIAL COPY
o
UNITED STATES
gg
'. !
NUCLEAR REGULATORY COMMISSION
'
o
-
t r
REGION 11
k
'!
101 MARIETTA ST., N.W.. SUITE 3100
8
ATLANTA, GEORGIA 30303
JUN 3 01981
' Carolina Power and Light Company
ATTN: Mr. J. A. Jones, Senior Executive
Vice President and Chief
Operating Officer
411 Fayetteville Street
Raleigh, NC 27602
Gentlemen:
Subject: Report Nos. . 50-324/81-12 and 50-325/81-12
This refers to the routine safety inspection conducted by Mr. D. F. Johnson of
this office on May 15 - June 15, 1981, of activities authorized by NRC Operating
License Nos. DPR-71 and DPR-62 for the Brunswick facility and to the discussion
of our findings held with Mr. C. R. Dietz, Plant Manager, at the conclusion of
the inspection.
Areas examined during the inspection and our findings are discussed in the
enclosed inspection report.
Within these areas, the inspection consisted of
selective examinations of procedures and representative records, interviews with
personnel, and observations by the inspector.
Within the scope of this inspection, no violations or deviations were disclosed.
We have examined actions you have taken with regard to previously reported
- unresolved items.
The ' status of these items is discussed in the enclosed
inspection report.
Two new unresolved items resulted from this inspection and are discussed in the
enclosed report. These items will be examined during subsequent inspections.
In_accordance with 10 CFR 2.790 of the Commission's regulations, a copy of this
letter and the enclosed report will be placed in the NRC's Public Document Room.
If the report contains any information that you believe to be exempt from
disclosure under 10 CFR 9.5(a)(4), it is necessary that you:
(a) notify this
. office by . telephone within ten days from the date of this letter of your
intention' to file a request for withholding; and (b) submit within twenty-five
days from the date of - this letter a written application to this office to
. withhold such information. If your receipt of this letter has been delayed such
that less than seven days are available for your review, please notify this
office promptly so that a new due date may be established. Consistent with
section 2.79:(b)(1), such application must be accompanied by an affidavit
executed by the owner of the infermation which identifies the document or part
thereof sought to be withheld, and a full statement of the reasons on the basis
n
of which it is claimed that the information should be withheld from public
disclosure.
This section further
,gi s ,the statement to address with
specificity the considerations lis aci trl
FRr 6 790(b)(4) . The information
N'/ x,
c} W
p-
_
TW
7
J
f
a
!!
5
-
I 4 JUL 2 31981*- e
" EUY"
/ f
go7240506'810630
"
A
CK 05000324
}
,,
G
,
'.
'l
c.,
l i ,. .
'
7
..
'
.
.
.
,
JUN 3 01981
.
.
..
. Carolina Power and Light Company
2
sought to be withheld shall be incorporated as far as possible into a separate
part of the' affidavit.
If we do not hear from you in this regard within the
specified periods noted above, the report will be placed in the Public Document
Room.
Should you have any' questions concerning this letter, we will be glad to discuss
them with you.
Sincerely,
.
SC.
R. C.
ewis, Acting Director
Division of Resident and
Reactor Project Inspection
Enclosure:
Inspection Report Nos. 50-324/81-12
and 50-325/81-12
cc w/ encl:
C. R. Dietz, Plant Manager.
-
-
-
-
-
- -
-
-