Notice of Violation from Insp on 810505-07
ML20005B086
Person / Time
Site: Beaver Valley
Issue date: 06/15/1981
From: Brunner E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML20005B085 List:
References
50-412-81-02, 50-412-81-2, NUDOCS 8107060297
Download: ML20005B086 (1)


Text

.

APPENDIX A NOTICE OF VIOLATION Duquesne Light Company Docket No.: 50-412 Beaver Valley, Unit 2 License No.: CPPR-105 As a result of the inspection conducted on May 5, 1981 thrcugh May 7, 1981, and in accordance with the Interim Enforcement Policy, 45 M 66754 (October 7, 1980), the following violation was identified:

10 CFR 50, Appendix B, Criterion XIII, states in part, " Measures shall be established to control the handling, storage...to prevent damage or deterioration."

The Beaver Valley Power Station, Unit 2, PSAR Section 17, paragraph 17.2.1.13A, also states, "The DLC QAP estab;ishes measures to control the handling, storage, shipping, cleaning and preservation of material and equipment in accordance with work and inspection instructions to prevent damage or deterioration."

The Duquesne Light Procedure D.L.C. FCA-11, paragraph 8.6.3, states in part, " Material must be maintained as nearly as practical in its.

required storage level during transit" and S.I.C.P 13.2, Revision 2, Level D states, " Reasonably removed from actual construction area and traffic..."

Contrary to the above, on May 5, 1981, ASME Safety Related piping was temporarily stored in the cable vault area and on the ground outside the containment building without adequate protection from damage.

This-isaSeverityLevel19 Violation (SupplementI.E.).

Pursuant to the provisions of 10 CFR 2.201, Duquesne Light Company is hereby required to submit to this office within twenty-five days of the date of this Notice, a written statement or explanation in reply including the corrective steps which have been taken and results achieved; corrective steps which will be taken to avoid further violations; and the date when full compliance will be achieved.

Under the autharity of Section 182 of the Atomic Energy Act of 1954, as amended, this response shall be submitted under oath or affirmation.

M--^

JUN 151981 Dated Eld J. Brunner, Acting Director Division of Resident and Project Inspection 8107063a97 810615!