Refers to Informing NRC of Steps Taken to Correct Violations Noted in IE Insp Rept 50-334/80-05.Discusses Mgt Controls Over Corrective Actions
ML20004E682
Person / Time
Site: Beaver Valley
Issue date: 03/03/1981
From: Grier B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Dunn C
DUQUESNE LIGHT CO.
Shared Package
ML20004E683 List:
References
NUDOCS 8106150042
Download: ML20004E682 (2)


See also: IR 05000334/1980005

Text

.p.

.-

  • p Kit
  • -

UNITED STATES

Yb

'

~

E

NUCLEAR REGULATORY COMMISSION

-

n

$

f

REGION 1

631 PARK AVENUE

0,

%

,o',4 -

KING OF PRUSSIA, PENNSYLVANIA 19406 g'

7

,

Docket No. 50-334

g

ppjggj

e

Duquesne Light Company

98

f6 h M9

ATTN: Mr. C. N. Dunn

2

g% 0 3 79g

,

Vice President

!

-

Operations Division

4

"8

fB

%'ESEP% K

435 Sixth Avenua

\\

Pittsburgh, Pennsylvania 15219

$

,

Gentlemen:

J.O

Subject:

Inspection 50-334/80-05

This refers to your letter dated April 17, 1980, in response to our letter

'

dated March 25, 1980; our subsequent letters dated August 11, 1980 and

January 29, 1981; your letters dated January 12, 1981 and February 6,1981;

and, discussions of your February 6,1981 letter between Mr. D. A. Beckman

of this office and Mr. J. A. Werling and Mr. J. D. Sieber of your staff on

February ll and 17, 1981, respectively.

Regarding your management controls over corrective actions for noncompliances,

the above discussions with your staff confinn Duquesne Light Company acknow-

ledgement of:

i

The responsibility to promptly notify NRC in writing of substantive changes

--

in actions which have been documented as written commitments to NRC. Written

notification must be made prior to the committed completion date.

The responsibility to assure that adequate corrective and preventive actions

,

--

are prescribed and fully implemented for NRC inspection findings. These

'

actions must be taken on a time frame consistent with the safety significance

i

of the findings, irrespective of the status of correspondence with NRC.

Oral notification to NRC regarding changes to commitments does not change

!

--

the responsibilities for conducting activities in accordance with your NRC

license nor in providing a timely written notification of such changes.

3

Regarding your actions to prevent recurrence of the nencompliance identified in

Inspection 50-334/80-05, we understand that measures o..er than the establishment

of a log room have been taken to control safety related procedure issuance.

These actions will be reviewed during a subsequent inspection of ycur licensed

program. We further understand that your review of log room feasibility may

result in cancellation of its im

12,1981)plementation (scheduled for August 1,1981 by

your letter of January

You are requested to advise this office, in

.

writing, of your final disposition of this matter on or before April 30, 1981.

i

,

!

l

,

810 615 0 OG,

k

-

- - - , -

.

-

-

.

.

Duquesne Light Company

2

g

gg

If our understanding is incorrect, please contact this office within 10 days of

receipt of this letter.

Your cooperations with us is appreciated.

Sincerely,

'

w

-

.,

'

B

H. Grier

.

'

Director

CC'

F. Bissert, Technical A;sistant Nuclear

R. Washabaugh. QA Manager

'

J. Werling, Station Superintendent

G. Moore, General Superintendent, Power Stations Department

,

'

J. J. Carey, Director of Nuclear Operations

R. Martin, Nuclear Engineer

J. 'lieber, Superintendent of Licensing and Compliance, BVPS

-

,