Forwards IE Insp Repts 50-321/81-05 & 50-366/81-05 on 810316-20 & Notice of Violation.Notice of Violation Withheld (Ref 10CFR2.790)
ML20004E044
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 04/15/1981
From: Robert Lewis
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: John Miller
GEORGIA POWER CO.
Shared Package
ML19064B213 List:
References
NUDOCS 8106110040
Download: ML20004E044 (2)


See also: IR 05000321/1981005

Text

taarsumnamutunwtu

g

CONTAINS 2.0INFORMATION

o,

UNITED STATES

o,,

8

NUCLEAR REGULATORY COMMISSION,

o

REGION 11

3

r

[f

101 MARIETTA ST

N.W.. SulTE 3100

q,

ATLANTA, GEORGIA 3o3o3

.....

O

APR 151981

Georgia Power Company

ATTN:

J. H. Miller, Jr.

Executive Vice President

270 Peachtree Street

Atlanta, GA 30303

Gentlemen:

Subject: Report Nos. 50-321/81-05 and 50-366/81-05

This refers to the routine safeguards inspection conducted by A. Tillman of this

office on March 16-20, 1981, of activities authorized by NRC Operating License

No. DPR-57 and NRC License No. NPF-5 at Hate., Nuclear Plant facility and to the

discussions of our findings held with C. T. Moore at the conclusion of the

inspection.

Areas examined during this inspection included your physical security program as

implemented under the provisions of Title 10, Code of Federal Regulations, Part

73, " Physical Protection of Plants and Materials", and the specific requirements

of your approved Security Plan. Within these areas, the inspection consisted of

selective examinations of procedures and representative records, interviews with

personnel, performance tests, and observations by the inspectors.

During the inspectica, it was found that certain activities under your license

appear to violate NRC requirements.

This item and references to pertinent

requirements are listed in the Notice of Violation enclosed herewith as Appen-

dix A.

Elements to be included in your response are delineated in Appendix A.

Details of activities involving safeguards and security measures are exempt from

disclosure in accordance with 10 CFR 2.790(d). Therefore, your respunse should

be incorporated in a separate paper and referenced in your reply.

We have examined actions you have taken with regard to previously reported

unresolved matters.

The status of these items is discussed in the enclosed

report.

In accordance with Section 2.790(d) of the NRC's " Rules of Practice", Part 2,

Title 10, Code of Federal Regulations, activities involving safeguards and

security measures are exempt from public disclosure; therefore, the enclosures to

this lettor with the exception of the report cover page, which is an inspection

summary, will not be placed in the Public Document Room.

.

.

810 6110 OMO

MATERIAL TRANSMITTED HEE #lTH

CONTAINS 2.7N INFORMATi3N

o'

MATERIALTRANSMITTED HEREWTTX

<-

.

CONTAINS 2.790INFORMATION

,

Georgia Power Company

2

APR 151881

Should you have any questions concerning this letter, we will be glad to discuss

them with you.

Sinc rcl ,

Division h Resident and

.T . La

ng

rector

l

Reactor Project Inspection

Enclosures:

1.

Appendix A, Notice of Violation

(Exempt from Disclosure)

2.

Inspection Report Nos. 50-321/81-05

and 50-366/81-05

(Exempt from Disclosure)

3.

Inspection Summary

(Not Exempt)

cc w/ enc 1:

M. Manry, Plant Manager

-

C. E. Belflower, Site QA Supervisor

W. T. Widner, Vice President and

G2neral Manager Nuclear Generation