ML20004B275

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-424/81-05 & 50-425/81-05 on 810420-22. Noncompliance Noted:Failure to Follow Welding Procedure Purge Requirements & to Follow Storage Procedure Requirements
ML20004B275
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 05/07/1981
From: Herdt A, Kleinsorge W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20004B264 List:
References
50-424-81-05, 50-424-81-5, 50-425-81-05, 50-425-81-5, NUDOCS 8105270477
Download: ML20004B275 (10)


See also: IR 05000424/1981005

Text

fs

'

  1. >* %c

o

UNITED STATES

8'

NUCLEAR REGULATORY COMMISSIOff

~

o

$

REGION !I

,

o

.7

101 MARIETTA ST., N.W., Su1TE 3100

D

ATLANTA. GEORGIA 30303

o

.....

Report Nos. 50-424/81-05 and 50-425/81-05

Licensee: Georgia Power. Company

270 Peachtree Street

Atlanta, GA 30303

Facility Name: Vogtle

Cocket Nos. 50-424 and 50-425

License Nos. CPPR-108 and CPPR-109

near Waynesboro, GA

Inspection a+ V

a

, ,

___

kN

Inspector.

-

'W. P. Tleinsor

Oat 1! S'igned

f/7/[/

Approved by:

.

.

A. R. Herdt, Section Chthf

'Date Signed

Engineering Inspection Branch

Engineering and Technical Inspection Division

-

SUMMARY

Inspected on Xpril 20-22, 1981

Areas Inspected

This routine, unannounced inspection involved 19 inspector-hours onsite in the

areas of licensee action on previous inspection findings (Units 1 and 2),

safety-related piping (Units 1 and 2),

steel structures and supports (Units 1

and 2) and status of IE Bulletins (Units 1 and 2).

Results

Of the three areas inspected, no violations or deviations were identified in two

areas; three violations were found in one area (Violation

" Failure to follow

welding procedure purge requirements" - paragraph 6.b.(1), Violation

" Failure

to follow storage procedure requirements"

paragraph - 6.a.(2) and, Violation -

" Inadequate measures to control handling of safety related materials or equip-

ment"

paragraph 6.a.(3)).

810527 0 N

,

.

- - - - - - - , . .

-

.

REPORT DETAILS

1.

Persons Contacted

Licensee Employees

  • K. M. Gillespie, Project Manager

'E. D. Groover, QA Site Supervisor

  • R. W. McManus, Manager QC

i

  • M. H. Googe, Manager of Field Operations

"R. R. Allen, Assistant Construction Product Manager

  • C. W. Hayes, PQAM
  • G. R. McCarley, APPS - Mechanical
  • B. F. Barnett, Sr. QA Field Representative

Other licensee employees contacted included construction craftsmen, techni-

cians, and office personnel.

Other Organizations

  • J. P. Runyan, QA Manager, Pullman Power Products (PPP)
  • J. E. Mah1meister, Resident Engineer, Bechtel Power Corp. (BPC)
  • W. A. House, Resident Engineer "N" Stamp, BPC

.

" Attended exit interview

2.

Exit Interview

The inspection scope and findings were summarized on April 22,1981 with

those persons indicated in paragraph 1 above. The inspector described the

areas inspected and discussed in detail the inspection findings listed

below. No dissenting comments were received from the licensee.

(0 pen) Violation 424/81-05-01: " Failure to Follow Welding Procedure Purge

Requirements" - paragraph No. 6.b.(1) .

(0 pen) Violation 424, 425/81-05-02:

" Failure to Follow Storage Procedure

Requirements"

paragraph No. 6.a.(2).

(0 pen) Violation 424, 425/81-05-03:

" Inadequate Measures to Control

Handling of Safety Related Materials or Equipment"

paragraph No. 6.a.( 3).

(0 pen) Inspector Followup Item 424, 425/81-05-04: " Clear Distance Between

Parallel Reinforcing Bar Splices"

paragraph 5.b.

-

.

- -

__

-

_

2

3.

Licensee Mtion on Previous Inspection Findings (Units 1 and 2)

a.

(Closed) Violation 424, 425/81-02-02: " Welder Qualification Controls"

Georgia Power Company letters of response dated March 11 and 20, 1981,

have been reviewed and determined to be acceptable by Region II. The

inspector held discussions with the project manager and examined the

corrective actions as stat M in the letter of response. The inspector

concluded that Georgia Power Company had determined the full extent of

the subject noncompliance, performed the necessary survey and follow-up

actions to correct the present conditions and developed the necessary

corrective actions to preclude recurrence to similar circumstances.

The corrective actions identified in the letters of response have been

implemented.

b.

(Closed) Violation 424, 425/81-02-03: " Weld Rod Control"

Georgia Power Company letters of response dated March 11 and 20,1981

!

have been reviewed and determined to be acceptable by Region II. The

inspector held discussions with %e project canager and examined the

corrective actions as stated in t% letters of response. Tne inspector

concluded that Georgia Power Company had determined the full extent of

the subject nonc.mpliance, performed the necessary survey and follow-up

actions to correct the present conditions and developed the necessary

-

corrective actions to preclude recurrence of similar circumstances.

The corrective actions identified in the letters of response have been

implemented,

c.

(Closed) Violation 424, 425/81-04-02: " Failure to Follow Procedure for

Controlling Nonconforming Items"

Georgia Power Company letter of respense dated April 1,1981 has been

reviewed and determined to be acceptable by Region II. The inspector

hela discussions with the project manager and examined the corrective

actions as stated in the letter of response. The inspector concluded

that Georgia Power Company had determined the full extent of the

subject noncompliance, performed the necessary survey and follow-up

actions to correct the present conditions and developed the necessary

correa,tive actions to preclude recurrence of similar circumstances.

The corrective actions identified in the letter of response have been

implemented.

4.

Unresolved Items

Unresolved items were no' identified during this inspection.

l

..--g

-

- - - -

y

3

5.

.ndependent Inspection Effort (Units 1 and 2)

a.

Construction Progress

The inspector conducted a general inspection of the Units 1 and 2

containment construction sites, auxiliary building, PPP pipe fabri-

cation shop, and the piping assembly lay down jard to observe construc-

tion progress and construction activities such as welding, nondestruc-

tive examination, material handling and control, housekeeping and

storage.

b.

Reinforcing Stael Placement

During the general inspection above, the inspector accompanied by a

representative of the licensee noted nine examples of the clear

distance between parallel lap splices in a layer to be less than one

inch. American Concrete Institute Standard 318-1971 " Building Code

Requirements for Reinforced Concrete", Section 7.4.5 requires that the

clear distance between parallel lap splices or parallel lap splice and

adjacent bars be no less than one inch. The inspector determined that

the condition described above was still in the erection stage and had

not yet received a QC acceptance inspection. Vogtle Plant Specifica-

tion X2AP01, Division C3, Section No. C3.4 " Placing Reinforcing Steel",

Revision 6 only addresses the clear distance between bars and not

-

splices. The licensee indicated that they would look further into the

matter.

The inspector stated that the above would be an inspector

followup item identified as 424, 425/81-05-04: " Clear Distance Between

Parallel Reinforcing Bar Splices".

Within the area examined no violations or deviations were identified.

6.

Safety-Related Piping (Units i and 2)

The inspector observed non welding and welding work activities for safety-

related piping as described below to determire whether applicable code and

procedure requirements were being met. The applicable code for safety-

related piping is the ASME B and PV Code,Section III, Subsection NC and NO

1977 Edition with addends through Winter 1977.

a.

Observatior, of Non-Welding Activities

Observation of specific work activities were conducted to determine

conformance, where applicabla, with the following; inspection and/or

work procedures, record keeping, installation specifications or plans,

specified materials, specified NDE, calibration and use of proper test

equipment and qualified inspection and NDE personnel.

.

. . _ . _ . .

_.

.

.

4

System or

Activity

Comoonent

Unit

Procedure

Storage

Various

1&2

Specificailon No. X4AZ01

Division P1, Revision 4

Handling

Various

1&2

See Paragraph 6.a.(3)

(1) With regard to the storage inspection above the inspector noted

the licensee's program for the storage of carbor steel piping

assemblies deviates from their PSAR commitment to Regulattry Guide

1.38 for material storage.

Regulatory Guide 1.38 endorses ANSI

N45.2.2-1972Property "ANSI code" (as page type) with input value "ANSI</br></br>N45.2.2-1972" contains invalid characters or is incomplete and therefore can cause unexpected results during a query or annotation process.. ANSI N45.2.2 requires that items in storage shall

have all covers, caps or other cicsures intact. GPC Specification

X4AZ01 Division P 1, Revision 4 requires that the pipe caps on

carbon steel piping assemblies be removed before storage.

This

deviation is documented in Vogtle Licensing Document Deviation,

PSAR Deviation No. P16 dated April 21, 1980, and submitted to

Southern Company Services, Inc. by Bechtel Power Corp. letter

dated April 22, 1980 for incorporation into the FSAR, when issued.

(2) With regard to the storage inspection above, the inspector accom-

panied by a representative of the licensee, made an inspection of

pipe spool laydown areas, to determine whether pipe storage was

-

accomplished in accordance with applicable procedures.

On

April 21,1981, the inspector noted the fol. lowing:

,

(a) Numerous carbon steel piping assemblies containing standing

water.

(b) Numerous carbon steel piping assemblies without caps or rain

hoods on upward protruding open vertical branches.

(c) Several carbon steel flange.d piping assemblies without

protective covers on the flange surfaces.

(d) Several stainless steel piping assemblies missing protective

end caps.

l

(e) Several stainless steel piping assemblies off dunnage in

contact with mud.

Specification No. X4AZ01, Division P1, Revision 4, " action P.1.6

provides the general requirements for storage safety-related and

!

balsnee of plant piping assemblies and components. The licensee

l

stores all piping assemblics as if they were intended for safety-

I

related applications.

l

l

!

!

--

--

-.

-.

- -

-.

f

.

5

Section Pl.6.2 reautres carbon steel piping assemblies to be

stored so they are free draining with upward protruding vertical

branches provided with covers or rain hoods.

Section Pl.6.2

further requires that flange ends be provided with bolted wooden

'

protective disks.

Section Pl.6.3 requires that stainless steel

piping assemblies be capped and stored on dunnage to ' prevent

contact with ground water. Therefore procedures were not followed

for the storage of piping assemblies. Failure to follow proce-

dures for activities affecting quality is in violation of 10 CFR 50, Appendix B, Criterion V.

The above violation will be identi-

fied as 424, 425/81-05-02: " Failure to Follow Storage Procedure

Requirements".

(3) With regard to material handling, the inspector noted, an

April 21, 1981, that the licensee did not have a documented

program established for the inspection of rigging slings or

chokers used for handlirg safety-related materials or equipment.

ANSI N45.2.2-1972, " Packaging Shipping, Receiving and Handling of

Items for Nuclear Power Plants (During the Construction Phase)"

has been iduntified as the applicable standard for material and

equipment handling.

ANSI N45.2.2, pmJraph 7.4 requires an

'

inspection program be established for rigging and a system be

established that will indicate acceptability of all rigging after

each inspecti:n.

Therefore the licensee has not established

-

adequate measures to control the handling of materials and equip-

ment.

Failure to establish adequate measures to control the

handling of materials and equipment by work and inspection proce-

dures to prevent damage is in violation of 10 CFR 50, Appendix B,

Criterion XIII. The above violation will be identified as 424,

425/81-05-03: " Inadequate Measures to Control Handling of Safety

Related Materials or Equipment".

b.

Observation of Welding Activities

The inspector observed in process welding activities of safety-related

piping field welds as described below to determine whether applicable

code and procedure requirements were being met.

.

(1) Welding

The below listed welds were examined in process to determine work

conducted in accortree with traveler; welder identification and

location; welding procedure assignment; welding technique and

sequence; materials identity; weld geometry; fit-up; temporary

attachments; gas purcing; preheat; electrical characteristics;

shielding gas; welding equipment concition; tnterpass temperature;

interpass cleaning; orocess control systems; identity of welders;

qualification of inspection personnel; and weld history ?ecords.

,

, ,

---

,

, .

--

,

-

6

Weld No.

ISO Number

Unit

Size

System

E

1K3-1208-099-02

1

3"sch 160

Chemical and

Volume Control

038-W-05 IK3-1206-004-01, R1

1

10" v.0. 365" Containment

Spray

038-W-02 1K3-1206-004-01

1

14"x0.438" Contaicment

Spray

003-W-01 2K3-1205-003-01

2

14"x0.438" Residual Heat

Removal

With regard to the above inspection, the inspector accompanied by

a representative of the licensee, on April 21, 1981, noted that

.

the flow meter ball for the back purge on containment spray system

'

weld joint 038-W-02, during root welding was pegged at the top of

the sito glass indicating a flow rate far in excess of 70 CFH.

-

Pullman Power Products General Welding Information Requirements,

dated January 31, 1981, specifies that back purge shall be approx-

imately 20 CFH. Theref ere the welder of record for joint 038-W-02

did not follow the welding procedure. Failure to follow procedure

for activities affecting quality is in violation of 10 CFR 50,

-

Appendix B, Criterion V.

The above violation will be identified

as 424/81-05-01:

" Failure to Follow Welding Procedure Purge

Requirements".

(2) Welder Qualification

-

The inspector reviewed the PPP and CB&I programs for qualification

of welders and welding operators for compliance with QA procedures

and ASME Code requirements.

The applicable Code for welding

qualification is ASME B&PV Code Section IX as invoked by GPC

Specifications X2AG06 Rev. 4 and X4AZ01, Section P.1, Revision 8.

l

The following welder qualification status records and " Records of

Performance Qual'.fication Test" were reviewed relative to the weld

joints listed in paragraphs 6.b and 7.a.

j

Welder Symbol

Unit

Organization

Aeolication

CD

1

PPP

Safety-Relat.ad Piping

,

R1

1

PPP

Safety-Related Piping

AS

1

PPP

Safety-Related Piping

l

l

l

. --

-

-

-

..

_.

__ _

_

.

.

_-

,

_

_

i

~

4

7

i

Welder Symbol

Unit

Orcanization

Aoplication

B7

2

PPP

Safety-Related Piping

RJH

1

CB&I

Steel Structures &

Supports

CJM

1

CB&I

Steel Structures &

Supports

DCT

1

CB&I

Steel Structures &

Supports

'

JTL

1

CB&I

Steel Structures &

Supports

RCC

2

CB&I

Steel Structures &

-

Supports

LDW

E

CB&I

Steel Structures &

Supports

(3) Welding Filler Material Control

The inspector reviewed the CB&I and PPP programs for control of

welding materials to determine whether materials are being pur-

hased, accepted, stored, and handled in accordance with QA

procedures

and applictble code requirements.

The following

specific areas were examined:

.

Purchasing procedure receiving, storing, distributing and

.

handling procedures, material identification.

Welding material purchasing and receiving records for the

.

following material s were reviewed for conformance with

applicable procedures and code requirements:

Heat Lot or

Process *

Type

' Size

Batch No.

Aoplication

SMAW

E-308-16 3/32",

2598267

Safety-Related Piping

GTAW

ER-308L

3/32"

741872

Safety-Related Piping

GTAW

ER-308L

1/8"-

760284

Safety-Related Piping

GTAW

ER-308L

1/16"

713589

Safety-Related Piping

GTAW

ER-308L

1/16"

26245

Safety-Related Piping

GTAW

ER-308L

3/32"

05394

Safety-Related Piping

GTAW

ER-308L

1/8"

05394

Safety-Related Piping

SMAW

7018

1/8"

RRR-074

Steel Structures &

Supports

.

,

.

.

.

.

_-

-

.

8

Heat Lot or

Process"

Type

Sizt

Batch No.

Apolication

SMAW

7018

5/32"

RRR-090

Steel Structures &

Suppcrts

SMAW

7018

3/16"

RRR-079

Steel Structures &

Supports

"SMAW - Shielded Metal Arc Welding

GTAW - Gas Tungsten Arc Welding

Within the areas examined, no violations or deviations were identified

except as described in paragraph Nos. 6.a.(2), 6.a.(3) and 6.b.(1).

7.

Steel Structures and Supports (Units 1 and 2)

The inspector observed welding work activities for steel structures and

supports as described below to determine whether applicable code and proce-

dure requirements were being met.

The applicable code for containment

fabrication is the ASME B&PV Code,Section III 1974 edition with addenda

through summer 75, and Section VIII 1974 edition with addenda through Summer

75.

The inspector observed in process welding activities of containment

structural field welds as described below to determine whethar 7.pplicable

code and procedure requirements were being met.

-

a.

Weldirg

The following welds were examined in process to determine work

-

conducted in accordance with traveler; welding procedures available:

welding technique and sequence; weld geometry; fit-up electrica'

characteri: tics; equipment condition:

l

Structure

Unit

Location or Identification

Containment

1

4th to 5th Ring Increment 5

Containment

1

4th to 5th Ring Increment 2

(

Containment

1

4th to 5th Ring Increment 4

Containment Stiffener

1

5th Ring

Containment Leak Chase

2

Seam B-3

Containment Leak Che;c

2

Seam B-21

,

l

b.

Welder Qualification

'

(

Welder Qualification is discussed in paragraph 6.b.(2).

i

l

c.

Welding Filler Material Control

1

l

Welding filler material control is discussed in paragraph 6.b.(3).

Within the areas examined, no violations or deviations were identified.

I

!

l

.

.

-.

-

,.

.-

9

8.

Status of IE Bulletins (IEB's) (Units 1 and 2)

(Closed) IEB 424/425/80-BU-21:

Valve Yokes Supplied by Malcolm Foundry

Company, Inc.

The licensee's response letter for this bulletin, dated

December 30, 1980, has been received and reviewed by Region II. The letter

response indicates that the licensee's active valves do not contain parts

cast by Malcolm Foundry.

This issue is considered closed based on the

letter response.

-

1

!

.

t

!

! -.

-.

-

. - . . -

.

. .

- - .

-

. .

..

- - _ - -

. - _ - _ . . . _

- . - - . .