Forwards IE Insp Repts 50-424/81-05 & 50-425/81-05 on 810420-22 & Notice of Violation
ML20004B263
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 05/13/1981
From: Robert Lewis
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: John Miller
GEORGIA POWER CO.
Shared Package
ML20004B264 List:
References
NUDOCS 8105270461
Download: ML20004B263 (2)


See also: IR 05000424/1981005

Text

.

.

'~

+ # p eur

.

'o

UNITED STATES

l'

NUCLEAR REGULATORY COMMISSION

~

n

3

E

REGl0N 11

0,4ggd h

101 MARIETTA ST., N.W.. SUITE 3100

/

o,g

p/

/

ATL.ANTA, GEORGIA 30303

MAY 131981

$ [g

    • "'

(Q~

$ * e$

'!

f

Georgia Power Company

ATTN: J. H. Miller, Jr.

. >g

,@ g o

-

,

6-

,a

"

6)); [4

Executive Vice President

270 Peachtree Street

6

Atlanta, GA 30303

Y 5 5p

Gentlemen:

Subject: Report Nos. 50-424/81-05 and 50-425/81-05

This refers to the routine inspection conducted by Mr. W. P. Kleinsorge of this

office on April 20-22, 1981, of activities authorized by NRC Conttruction Permit

Nos. CPPR-108 and CPPR-109 for the Vogtle facility. Our preliminary findings

were discussed with Mr. K. M. Gillespie at the conclusion of the inspection.

Areas examined during the inspection and our findings are discussed in the

enclosed inspection report. Within these areas, the inspection consisted of

selective examinations of procedures art 1 representative records, interviews with

personnel, and observations by the inspector.

During the inspection, it was found that certain activities under your license

appear to violate NRC requirements. These items and references to pertinent

'

requirements are listed in the Notice of Violation enclosed herewith as

Appendix A.

Elements to be included in your response are delineated in

Appendix A.

We have examined actions you have taken with regard to previously identified

enforcement matters. These are discussed in the enclosed inspection report.

In accordance with Section 2.790 of the NRC " Rules of Practice," Part 2, Title

10, Code of Federal Regulations, a copy of this letter and the enclosed

inspection report will be placed in the NRC Public Document Room. If this report

contains any ir. formation that you believe to be proprietary, it is necessary that

you make a written applicatics within 20 days to this office to withhold such

information from public disclosure. Any such application must include the basis

for claiming that the information is proprietary and the proprietary information

should be contained in a separate part of the document.

If we do not hear from

you in this regard within the specified period, the report will be placed in the

Public Document Room.

\\

h,0

4's\\

i

810 52 'F 0 M

k

.

-

MAY 131981

-

j

.

.

Georgia Power Company

2

Should you have any questioni concerning this letter, we will be glad to discuss

them with you.

Sincerely,

/

Y C. Lewi[,[Acti

Dir ctor

Divisien of Resident and

Reactor Project Inspection

Enclosures:

1.

Appendix A, Notice of Violation

2.

Inspection Report Nos. 50-424/81-05,

and 50-425/81-05

c:: w/ encl :

K. M. Gillespie, Construction

Project Manager-

E. D. Groover, QA Site Supervisor

D. E. Dutton, Project General Manager

.