T/D
.
.
/
'o
UNITED STATES
g
t/
NUCLEAR RE*lULATORY COMMISSION
o
$
E
REGION lil
o
799 ROOSEVELT ROAD
GLEN ELLYN. ILLINOIS 60137
4,.....
76@*r7;k.
lAPR~8
Jggp
\\
~f ,f/]PREC
Y[ %
'
b
5
/
9
Docket Nc. 50-409
07
-
-
3 %
IS8 k j
Dairyland Power Cooperative
r,
%i
ATTN:
Mr. F. W. Linder
y
General Manager
4
g
2615 East Avenue - South
w
La Crosse, WI 54601
Gentlemen:
-
This refers to the routine inspection conducted by Messrs. W. L. Forney'
and M. W. Branch of this office on February 1-28, 1981, of activities
at La Crosse Boiling Water Reactor authorized by NRC Operating License
No. DPR-45 and to the discussion of our findings with Mr. R. Shimshak
at the conclusion of the inspection.
The enclosed copy of our inspection report identifies areas examined
during the inspection. Within these areas, the inspection consisted
of a selective examination of procedures and representative records,
observations, and interviews with personnel.
During this inspection, certain of your activities appeared to be in
noncompliance with NRC requirements, as described in the enclosed
Appendix A, and a written response is required.
In accordance with Section 2.790 of the NRC's " Rules of Practice," Part
2, Title 10, Code of Federal Regulations, a copy of this letter, the
enclos>res, and your response to this letter will be placed in the NRC's
Public Document Room, except as follows.
If the enclosures contain
information that you or your contractors believe to be proprietary, you
must apply in writing to this office, within twenty-fivt Nys of the date
of this letter, to withhold such information from public de losure.
The
application must include a full statement of the reasons for which the
information is considered proprietary, and should be prepared so that
proprietary information identified in the application is contained in an
enclosure to ;he application.
'8:10511 0 @
1
.
Dairyland Power Cooperative
-2-
It should be noted that this item of noncompliance represents the third
instance of personnel error since January 1981.
In addition to your
response to the specific item of noncompliance please provide us with
the actions you plan to take to reduce this high frequency of personnel
error.
We will gladly discuss any questions you have concerning this inspection.
Sincerely,
$CXby-w
R. F. Heishman,
cting Director
Division of Resident and
Project Inspection
Enclosures:
1.
Appendix A, Notice
of Violation
2.
IE Inspection Report
No. 50-409/81-02
-ce w/encls:
R. E. Shimshak, alant
Superintendent
Central Files
Reproduction Unit NRC 20b
AE0D
Resident Inspector, RIII
Local PDR
John J. Duffy, Chief
Boiler Inspector
Mr. Stanley York, Chairman
Public Service Commission
.