Discusses Resolution of 810330 Open Items Re NUREG-0654 & NUREG-0696.Areas Will Be Resolved by Either Meeting Requirements & Implementation Dates Listed or Finding Mutually Agreeable Solution on Requirements W/Nrc
ML20003G437
Person / Time
Site: Summer South Carolina Electric & Gas Company icon.png
Issue date: 04/22/1981
From: Nichols T
SOUTH CAROLINA ELECTRIC & GAS CO.
To: Harold Denton
Office of Nuclear Reactor Regulation
References
RTR-NUREG-0654, RTR-NUREG-0696, RTR-NUREG-654, RTR-NUREG-696 NUDOCS 8104290414
Download: ML20003G437 (1)


Text

SOUTH CAROLINA ELECTRIC a GAS COMPANY POST OFFICE BOR 784 ColuMs A, south CAROLINA 29218 t

4)

S T. C. NicMots, J n.

April 22, 1981 6

Vice Patsiorme a.o Gaoup Decurevt NucLean Oerpatens C

4 Ap q% fp 198 1 4

~~

Nb Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation N

y U. S. Nuclear Regulatory Commission

~>,

4 Washington, D. C.

20555

Subject:

Virgil C. Summer Nuclear Station Docket No. 50/395 Radiological Emergency Plan

Dear Mr. Denton:

On }brch 30, 1981, South Carolina Electric and Gas Company (SCE&G) submitted information to Mr. Tom Kevern of the NRC on the Virgil C. Summer Nuclear Station Radiological Emergency Plan. In the letter, three areas were identified as open items and under review by SCE&G. These areas are:

(1) Staffing requirements of NUREG-0654; (2) Technical Support Center / Emergency Operating Facility in meeting NUREG-0696; (3) Meteorological Tower requirements of Appendix 2, NUREG-0654.

Each of these areas have implementation dates at various times in 1982, which gives SCE6G some time to fully complete our review and coordinate actions to be implemented in meeting the required dates. SCE&G will resolve these areas by either (1) meeting the requirements and implementation dates of the above listed items in l

NUREG-0654 and NUREG-0696 or (2) come to a mutually agreeable solution on the l

requirements with the NRC staff.

Specific information on the Meteorological Tower requirements will be provided l

to the NRC staff by May 8, 1981.

If you have additional questions, please advise us.

Very truly yours, Y

/

i l

T. C. Nichols, Jr.

RBC:TCN:pj cc:

V. C. Summer R. B. Clary O. S. Bradham G. H. Fischer A. R. Koon ISEC T. C. Nichols, Jr.

A. A. Smith NPCF/Whitaker H. E. Yocom H. N. Cyrus File l

p C. A. Price J. B. Knotts, Jr.

PRS D. A. Nauman J. L. Skolds W. A. Williams, Jr.

B. A. Bursey 81042qO g