Requests Results of Investigation Re Adequacy of Physical & Electrical Separation to Determine Channel Dependence of Reactor Protection Sys Sensing channels.Two-out-of-three Logic Configuation Is Acceptable Per Noted Conditions
ML20003G040
Person / Time
Site: Millstone, Calvert Cliffs, Palisades, Saint Lucie, Maine Yankee, Fort Calhoun  Entergy icon.png
Issue date: 04/16/1981
From: Clark R
Office of Nuclear Reactor Regulation
To: William Jones
OMAHA PUBLIC POWER DISTRICT
Shared Package
ML18046B409 List:
References
NUDOCS 8104280116
Download: ML20003G040 (3)


Text

-

'o, UNITED STATES NUCLEAR REGULATORY COMMISSION

!-.,'y,, c, g' },

WASHING TON. D. C. 20555

/j

,. 4;p.3 ;

j o, nm i a

\\,,[/

April 16, 1931 Docket No. 50-285 is.

S

\\

b fir. W. C. Jones 4p A.

g8,7 y '9

~ %, k%

Division Manager, Production

/887 E,

Operations A

Omaha Public Power District

'e h%

i 1623 Harney Street g

Omaha, Nebraska 68102 iG

Dear Mr. Jones:

In a continuing review of open licensing actions on power reactors, the staff has resumed the evaluation of the Reactor Protection System (RPS) inoperable channel condition for the Fort Calhoun Station. This item was initiated by our letter to you dated December 7,1977 which requested your review of the Technical Specification (TS) requirements for operation with an inoperable RPS channel and asked that you either apply for a TS change to require placing an inoperable channel in the tripped condition within one hour or request a NRC review of your existing system.

By letter dated January 31, 1978, you submitted the bases for continued operation of the Fort Calhoun Station with an inoperable RPS channel in the bypassed condition for an unlimited time period.

In this condition, the RPS logic is changed from a 2+out-of-4 to a 2-out-of-3 logic. On August 2,1978, a meeting was held to clarify our position on this subject and to gain an understanding of the licensee's position. Enclosure 1 is the minutes of the August 2,1978 meeting.

This review has been expanded to include the Engineered Safety Features Actuation System (ESFAS) since a preliminary review indicates a similar problem exist with the TS for ESFAS operability requirements.

Long tenn operation of a four channel RPS and ESFAS in a 2-out-of-3 logic configuration would be acceptable provided all four channels are sufficiently independent. However, in order for us to make such a finding, we require elaboration of the independence of the four channels in each system.

Therefore, we request that you provide, within 90 days of your receipt of this letter, the results of your investigation into the adequacy of both physical and electrical separation to determine channel independence of the four sensing channels. This investigation should include separation of the parameter sensors, transmitters and cable runs from the transmitters to the RPS and ESFAS cabinets in the control room. Channel independence within the cabinets and other enclosures which house the plant protection system should also be reviewed.

l l

8104 2 8 Ohb l

P r

. As you know, our staff conducted an on-site RPS review at the Calvert Cliffs and St. Lucie units. A copy of the resultant Safety Evaluation for St. Lucie, presenting the finding of the RPS review (pages 3 to 5),

is provided for your information as Enclosure 2.

Our conclusion was that allowing indefinite bypass of one nf the four RPS is not justified, but since the four channel CE systen does have sone independence, bypassing for 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> during testing or maintenance of one RPS channel is justified.

As an alternative to the requested review of RPS and ESFAS channel separation, we will consider issuance of the Calvert Cliffs and St. Lucie type TS for your RPS and ESFAS if you provide an application including documentation of design similarity to those of Calvert Cliffs and 5t. provides sample TS for your use. Any such Lucie.

application should be submitted within the same 90 days of your receipt of this letter.

If your have questions on this subject, please contact your NRC Project Manager.

Sincerely,

'~]l-i

(

i ;... k

-~

~

j u. w.....

Robert A. Clark, Chief Operating Reactors Branch #3 Division of Licensing

Enclosures:

1.

Minutes of meeting 2.

Safety Evaluation for St. Lucie 3.

Calvert Cliffs TS cc:

See next page I

l l

l l

I

Omaha Public Power District cc:

Director, Criteria and Standards Division Marilyn A. Tebor Office of Radiation Programs (ANR-460)

~

LeBocuf, Lamb, Leiby & MacRae U.S. Environmental Protection Agency

,1333 New Hampshire Avenue, N.W.

Washington, D. C.

20036 Washington, D. C.

20460 U.S. Environmental Protection Agency Mr. Emmett Rogert Chairman, Washington County Region VII Board of Supervisors ATTN: EIS COORDINATOR Blair, Nebraska 68023 324 East lith Street Kansas City, Missouri 64106 Omaha Public Power District ATTN: Mr. Spencer Stevens Plant Manager Fort Calhoun Plant 1623 Harney Street Omaha, Nebraska 68102 Director, Nebraska Departnent of Environmental Control P. O. Box 94877, State House Station Mr. Frank Gibson W. Dale Clark Library Lincoln, Nebraska 68509 215 South 15th Street Omaha, Nebraska 68102 Alan H. Kirshen, Esq.

Fellman, Ramsey & Kirshen 1166 Woodmen Tower Omaha, Nebraska 68102 Mr. Dennis Kelley U.S.N.R.C. Resident Inspector P. O. Box 68 Fort Calhoun, Nebraska 68023 -

Mr. Charles B. Brinkman l

Manager - Washington Nuclear Operations C-E Power Systems Conbustion Engineering, Inc.

4853 Cordell Avenue, Suite A-1 Bethesda, Maryland 20014 3