Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in IE Insp Repts 50-354/80-14 & 50-355/80-14.Proposed Corrective Action Re CRDM Housing Support Brackets Requested
ML20003F067
Person / Time
Site: Hope Creek  PSEG icon.png
Issue date: 01/26/1981
From: Robert Carlson
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Martin T
Public Service Enterprise Group
Shared Package
ML20003F063 List:
References
NUDOCS 8104200080
Download: ML20003F067 (2)


See also: IR 05000354/1980014

Text

..

s

/

jh

UNITED STATES

! ' [D

7.

NUCLEAR REGULATORY COMMISSION

d

$

REGION l

]-

.

631 PARK AVENUE

' ' 6'. ,d

KING OF PRUSSIA, PENNSYLVANIA 19406

....

Docket Nos. 50-354

2 6 d.; 331

.

50-355

,

Public Service Electric & Gas Company

ATTN: Mr. T. J. Martin

Vice President

Engineering and Construction

,

80 Park Plaza - 17C

Newark, New Jersey 07101

Gentlemen:

'

Subject: Combined Inspection 50-354/80-14 and 50-355/80-14

This refers to your letter dated December 2, 1980 in response to our letter

dated October 24, 1980.

Thank you for informing us of the corrective and preventive actions documented

in your letter. These actions will be examined during a subsequent inspection

of your licensed program.

In your reply to Item II of Appendix A to our letter and paragraph 4 of the

subject inspection report, you have identified action to be taken to correct a

problem that resulted from not meeting the requirements of AWS D1.1 Code.

However, this response does not address the noncompliance and is therefore not

sati sfactory. The original noncompliance explained that the installation of

the CROM housing support brackets was started without prior establishment of a

code basis. Had AWS been established as the applicable code prior to the

start of work, the problem discussed in your response may never have occurred.

Please address what corrective action is proposed or has been effteted to

i

preclude starting safety related work prior to establishment of a code basis

i

for that work.

Item IV of Appendix A to our letter and paragraph 6 of the inspection report

pointed out that the QC personnel associated with the bolting operation were

not sufficiently aware of the bolting requirements to identify the incorrect

in process operation. This reflects an inadequacy in the QC program regarding

personnel qualification that you did .iot address in your response.

Please

identify the corrective action proposed or implemented to ensure that QC

personnel are fully cognizant of the requirements to which they are required

to inspect.

l

{

i

'

O l O. H a U'IT-

g 104200 0SO

.

--p

,

+_c,

,y---

- - - ,

-,-----m-

y

,

, - - , - -4-

--- --

-p.-

-

w,

,y,-----

p-

-

e - ,, , , -

. _ . .

. . _ .

_

_

.

s

Public Service Electric and Gas

2

Company

You are requested to provide the additional information discussed above to this

office within 20 days.

You should also specify the date when full compliance

was or will be achieved.

Your cooperation with us is appreciated.

Sincerely,

Robert T. Carlson, Chief

Reactor Construction and Engineering

Support Branch

cc:

J. Boettger, General Manager, Corporate QA