ML20003E694
| ML20003E694 | |
| Person / Time | |
|---|---|
| Site: | Beaver Valley |
| Issue date: | 03/27/1981 |
| From: | Grier B NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
| To: | Schaffer S DUQUESNE LIGHT CO. |
| References | |
| IAL-81-16, NUDOCS 8104100061 | |
| Download: ML20003E694 (2) | |
Text
~
6 gg UNITED STATES 4
o NUCLEAR REGULATORY COMMisslON s
R EGION I
$ ' g., )A
,g g
g 631 PARK AVENUE g
gd KING OF PRUS$1 A. PENNSYLV ANIA 19406 f
%v /
$m
'h f 4 p\\ Q
/l'"l RRR 271991 s
/ $4 Docket No. 50-334 v
File No:
IAL-81-16 9
p Duquesne Light Company M(f ATTN: Mr. S. G. Schaffer 9'
President 4
/
435 Sixth Avenue W
Pittsburgh, Pennsylvania 15219 Gentlemen:
This refers to a telephone conversation between Mr. J. J. Carey of your staff and J. M. Allan of this office on March 27, 1981.
On March 23, 1981, the low pressure suction piping on the 1C Centrifugal Charging Pump was overpressurized as a result of a leaking check valve and the failure of a discharge valve, associated with this pump, to seat tightly.
Believing the discharge valve to be fully closed, the pump suction was then isolated. The suction piping was pressurized (to the shut suction valves) causing gasketed joints on the associated piping and valves to defom and leak.
We understand, as a result of this event and with regard to the matters discussed, you have or will take the following actions within 10 days or prior to plant startup (Mode 2):
1 Perform an analysis of the effects of the overpressurization on the suction piping for the pump and detemine any necessary action resulting from that analysis.
2.
Perfom an evaluation of the failure of the lc pump discharge valve to properly :as c.
This evaluat'c*i will include a review of the design and operation of reach rod opert ced valves in all plant safety related systems and radwaste systems to inc4ade necessary modifications to provide assurance of proper operation.
3.
Establish a preventive maintenance program to inspect or test periodici the valve applications described in Items 1 and 2 above.
4.
Perform an evaluation to detemine the appropriateness of design of the 3 and 6 inch Velan check valves.
This evaluation will include this and all previous failures of this type valve, and will include necessary modifica-tions to ensure proper operation.
5.
Perform a review of plant maintenance procedures and switching procedures and revise procedures as necessary to provide specific operational sequences and precautions to assure that system alignment changes do not adversely affect systems, equipment and components outside the boundary of the system B10.41e o O@
Duquesne Light Company 2
gg upon which maintenance is to be performed.
In addition, procedures will be reviewed and revised, as necessary, to ensure nraper equipment or component operation prior to restoring a system to service after maintenance has been performed.
If our understanding of your planned actions is incorrect, please contact this office by telephone and in writing within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.
Sincerely,
/.
WY
/
Bo ce H. Grier Director cc: