.Q
..o f[
'o, UNITED STATES y } 3 # q (,g NUCLEAR REGULATORY COMMISSION
% j'[,/ - j REGION I 0,, 4, D,o#a 631 PARK AVENUE KING OF PRUSSIA, PENNSYLVANIA 19406 Docket Nos. 50-443 50-444 D.C 0 2 m Public Service Company of New Hampshire ATTN: Mr. W. C. Tallman Chainnan and Chief Executive Officer 1000 Elm Street Manchester, New Hampshire 03105 Gentlemen:
Subject:
Interim Report on Cooling Tower Concrete Beams Thank you for your letter, dated November 6,1980, which forwarded an interim report pursuant to 10 CFR 50.55(e) regarding the subject matter.
This matter will be reviewed during our next inspection.
Your cooperation with us is appreciated.
Sincerely,
/dh Robert T. Carlson, Chief Reactor Construction and Engineering Support Branch l
cc-John DeVincentis, Project Manager a
g co 7:
))r.
S
- Y't n
m.
t:
8102030 b
.