Application to Amend Licenses DPR-53 & DPR-69,changing Tech Specs Sections 3 & 4 to Provide for Redundancy in Decay Heat Removal Capability.Class I & III Fees Encl
ML20002D069
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 01/08/1981
From: Lundvall A
BALTIMORE GAS & ELECTRIC CO.
To: Harold Denton
Office of Nuclear Reactor Regulation
Shared Package
ML20002D070 List:
References
FCR-80-97, NUDOCS 8101190320
Download: ML20002D069 (2)


Text

's BALTIMORE GAS AND ELECTRIC COMPANY P. O. D O X 1475 BALTI M O R E. M ARYLAN D 21203 s.

m:.

b L : -:

January 8,1981 r!O ARTHUR E. Lum ovALL.JR.

Vict Pat s:Di se?

vig su m, C 2, Es3

~

de C

3 Q

Mr. Harold Denton, Director G

3 Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Cormnission Washington, D.C.

20555

Subject:

Calvert Cliffs Nuclear Power Plant Units No. 1 & 2, Docket Nos. 50-317 % 50-318 Request for Amendment (FCR 80-97)

Reference:

NRC letter dated June 11, 1980 from D.G.

Eisenhut to Owners of All Operating Pressurized Water Reactors

Dear Mr. Denton:

Baltimore Gas and Electric Company hereby requests an Amendment to its Operating Licenses Nos. DPR-53 and DRP-69 for Calvert Cliffs Units 1 & 2, respectively, with the submittal of the enclosed proposed changes to the Technical Specifications.

Technical Specification Change Change Unit 1 and Unit 2 Technical Specifications as indicated on the attached marked-up pages of the technical specifications with respect to reactor decay heat removal capability. The technical specifications affected are 3.4.1.1, 3.4.1.2 (new), 3.4.13 (new), 3 9.8.1, 3 9.8.2 (new), 3/4 4.1.4.1 (bases).

Discussion and Justification The attached changes to the technical specifications are being submitted in accordance with the above referenced letter, which requested that we propose technical specification changes that provide for redundancy in decay heat removal capability.

Safety Committee Review These proposed changes to the Technical Specifications have been reviewed by our Plant Operations and Safety Review Committee and Off-Site Safety and Review Committee, and have concluded that implementation of these changes will not result in an undue risk to the public health and safety.

810 us 0120 g

l i

Fee Determination We have determined that the proposed changes constitute a Class III and Class I A:cendment pursuant to 10CFR 170.22 and accordingly a check in the amount of $4,400. is enclosed.

Verg p s,

.)

d o

STATE OF MARYLAND:

TO WIT:

CITY OF BALTIMORE:

Mr. A. E. Lundvall, Jr. being duly sworn, states that he is Vice President of the Baltimore Gas and Electric Company, a corporation of the State of Maryland; that he executed the foregoing Amendment for the purposed therein set forth; hat the statements :cade in said Amendment are true and correct to the best of

h. ' knowledge, information and belief; and that he was authorized to execute the Amendment on behalf of said corporation.

WITNESS my hand and Notarial Seal.