ML19353A882

From kanterella
Jump to navigation Jump to search
Insp Repts 50-445/89-71 & 50-446/89-71 on 891004-1107. Violations Noted.Major Areas Inspected:Applicant Actions on Followup to violations/deviations,10CFR50.55(e) Deficiencies Identified by Applicant & Allegation Follow Up
ML19353A882
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 12/01/1989
From: Latta R, Livermore H
Office of Nuclear Reactor Regulation
To:
Shared Package
ML19353A878 List:
References
50-445-89-71, 50-446-89-71, GL-88-17, IEB-85-003, IEB-85-3, NUDOCS 8912080035
Download: ML19353A882 (20)


See also: IR 05000445/1989071

Text

v

-_

.

!

APPENDIX B

U. S. NUCLEAR REGULATORY COMMISSION

OFFICE OF NUCLEAR REACTOR REGULATION

I

NRC Inspection Report:

50-445/89-71

Permits: CPPR-126

50-446/89-71

CPPR-127

. Dockets: 50-445

Construction Permit

50-446

Expiration Dates:

Unit 1: August 1, 1991

Unit 2: August 1, 1992

Applicant:

TU Electric

Skyway Tower

400 North Olive Street

Lock Box 81

Dallas, Texas

75201

.

Facility Names

Comanche Peak Steam Electric Station (CPSES),

'

Units 1 & 2

Inspection At:

Comanche Peak Site, Glen Rose, Texas

Inspection Conducted:

October 4 through November 7, 1989

-

Mb

//Are F'7

' Inspector:

R. M. Latta, Resident Inspector

Date

(Electrical) (paragraphs 2, 3, 4, 5, 6, 7 and 8)

Consultants:

W. D. Richins, Parameter (paragraph 6)

J. L. Taylor, Parameter (paragraphs 2, 3, 4, 5,

and 7)

DIAArun> -

I L- \\ - 3

Reviewed by:

L

!!. B. Livermore, Lead Senior Inspector

Date

8912000035 891201

KDR

ADOCK 0500Qg5

_

,

t

.,

.

,.

i

-2-

I

Inspection Sunsnary:

,

Inspect:.on Conducted: October 4 through November 7 1989 (Report

50-445/09-71

50-446/89-71)

Areas Inspected: Unannounced, resident safety inspection of the

applicant's actions on follow-up to violations / deviations,

!-

10 CPR 50.55(e) deficiencies identified by the applicant, allegation

F

follow up, electrical components and systems, safety-related.

,

mechanical components, and Ceneral plant area tours.

'

?

.Results:

Within the areas inspected, a weakness was identified in

the applicant's procurement program in that it failed to provide

adequate receipt inspection criteria for vendor procured thermolag

,

material (paragraph 3.1).

Additionally, during this inspection

'

. period, two violations were identified which involved the

'

-applicant's response to SDAR CP-89-25, " Site Fabricated Thermo-lag

Material."

The first violation concerned the applicant's failure to

follow procedures during the dry film thickness measurements of site

.

fabricated thermolag in that defective material was inspected and

accepted by the applicant's QC organization (paragraph 3.1).

The

second violation involved the applicant's failure to properly

identify the required corrective measures associated with defective-

.

site fabricated thermolag in that the identification of the cause of

the condition adverse to quality, the generic implications, and the

,

,

l

establishment'of measures to preclude repetition were not adequately

.

addressed in the response provided in TU Electric's letter TXX-89737

l

(paragraph 3.1).

i

!

l

.

'

.

l

L

<

-

.

.

_

-- __

..

-

__.

1

'

..

yy

{}

"

3_

DETAILS

i

1.

Persons Contacted-

  • M.

Axelrad, Newman and Holtzinger

  • J.

L.: Barker, Manager, ISEG, TU Electric

-j

'*D.'P. Barry, Senior, Manager, Engineering, Stone and Webster

~

Engineering Corporation (SWEC)-

  • J. W. Beck, Vice Prosilent. Nuclear Engineering, TU Electric
  • J.LE. Bentham, President, The Bentham Group, Inc.
  • 0.

Bhatty, Issue' Interface Coordinator, TU Electric

'

  • M.

R. Blevins, Manager of Nuclear Operations Support,

TU Electric

,

  • H. lD. Bruner, Senior Vice President, TU Electric
  • A.

R. Buhl, IAG-

  • W.

J. Cahill, Executive Vice President, Nuclear, TU_ Electric

  • H.

M. Carmichael', Senior Quality Assurance (QA( Program

Manager, CECO

  • W.

G. Counsil, Vice Chairman, Nuclear, TU Electric

'

  • C. G. Creamer, Manager, Unit 1 Completions-Engineering,

MNJ Electric

  • B.

S. Dacko, Licensing Engineer,'TU Electric

1

.

  • R.

J. Daly,. Manager, Startup, TU Electric

  • G.

G. Davis, Nuclear Operations Inspection Report Item

' Coordinator, TU Electric

  • D..E. Deviney, Deputy Director, QA, TU Electric
  • N.

M. Eifert, Chief Engineer EA, SWEC

  • J.

C. Finneran, Jr., Manager, Civil Engineering,

l

TU Electric

L

  • C.

A. Fonseca, Deputy Director, CECO

,

  • S.-P.

Frantz, Newman and Holtzinger

  • J.

L. French, Independent Advisory Group

.

  • B '. .P.

Garde, Attorney, CASE

  • J.

Greene, Site Licensing,1NJ Electric

.

  • W.

G. Guldemand, Manager of Site Licensing, TU Electric

  • T.

L. Heatherly, Licensing Compliance Engineer,

.TU Electric

'*J.

C.' Hicks, Licensing Compliance Manager, TU Electric

~

  • C.

B. Hogg, Chief Manager, TU Electric

  • R. T. Jenkins, Manager, Unit 1 Operations Support Engineering,

E

TU Electric

  • J.

J. Kelley, Plant Manager, TU Electric

  • 0. W. Love, Director of Engineering, TU Electric
  • F. W.' Madden-, Mechanical Engineering, Manager, TU Electric
  • S.

G. McBee, NRC Interf ace,1NJ Electric

  • J. W. Muffett, Manager of Project Engineering, TU Electric

g

!

  • S. S. Palmer, Project Manager, TU Electric

L

  • W.

O. Porter,-Operations Suyr. ort Engineering, TU Elect +ic

-

  • P.

Raysircar, Deputy Director / Senior Engineer Manager. CECO

'

  • A. B. Scott, Vice President, Nuclear Operations, TU Electric
  • J.

C.

Smith, Plant Operations Staff, TU Electric

  • R.

L. Spence, TU/QA Senior Advisor, TU Electric

l

..

.

.

p

fws,;

~

3-

1

. y '

.7

~

gyW

.

.-

~4~

J

.

R

  • J.

F. Streeter, Director,-QA,:TU Electric-

  • C. L. Terry, Manager of Projects, TU Electric

.

  • R'.

D. Walker, Manager of Nuclear. Licensing, TU Electric

  • J.'E.

Woods, Assistant Project Engineer, SWEC/ CECO

-The'NRC inspectorsLalso interviewed other applicant employees

during this inspection period.

  • Denotes personnel present at the November.7, 1989, exit.

3

meeting.

2.

F,ollow-up on Violations / Deviations (92702)

a.

.(Closed) Violation (EA86-09, Appendix A.I.B.1):

Failure

'

to satisfy the minimum separation requirements of IEEE

Standards.

This violation involved the applicant's

failure.to properly translate IEEE standard requirements

to instructions and drawings, as well as several examples

n' electrical separation deficiencies which were not in

acecrdance with the controlling drawings.

The applicant performed Issue-Specific Action Plan.

i

(ISAP) I.b.1, among others, to address this issue.

Subsequent NRC staff evaluations of the ISAPs-were

reported as satisfactory in SSER 10, Appendix A.

Addi-

J

tionally, as reported in previous NRC Inspection Reports,

the Post-Construction Hardware Validation Program (PCHVP)

-

which includod-Field Verification Method (FVM)-088 was

-I

reviewed and determined to be acceptable.

The NRC

4

inspectors also followed the implementation aspects of the

separation portion of-FVM-088 as previcualy documented in

NRC' Inspection Reports 50-445/89-15, 50-446/89-15;

50-445/89-22, 50-446/89-22; and 50-445/89-49, 50-446/89-49

and determined that it was acceptable.

The NRC inspector subsequently examined a sample of 4 out

,

of approximately 70 equipment panels and determined that:

i

E

proper inspections had been performed; nonconformance

p?

reports (NCRs) had been initiated where required; and that

l

these NCRs had been properly closed.

The panels selected

L

for review were CP1-EPSWEA-02-02, cpl-ECDPPC-03,

P

cpl-ECPRCB-06, and cpl-ECPRLV-17.

Based on the above

(

reviews and inspection activities, the NRC inspector

L

concluded.that the applicant had taken adequate corrective

L

action to prevent reoccurrence.

Therefore, this violation

is closed.

b.

(closed) Violation (445/8964-V-01):

Bypassing hold point.

This violation occurred when a Quality Control (QC) hold

point was bypassed and a section of electrical cable tray

was welded prior to a QC inspection of the lifted cables.

_

_

.

--

-.

.

.

V' ,; w

.g

. , .

. . .

-5-

In~ response to this violation,'the applicant issued

'NCR 89-9245, Revision 0, to document the missed hold point

and to verify that no cable damage resulted from the.

-welding._ Also, the personnel involved were counseled, a

~ memorandum to all craft personnel was issued by the

electrical craft manager, and additional craft training

was conducted.

Based on the above actions, this violation.

is closed.

c..

(Closed) Deviation (445/8964-D-02):

Missed commitment

date for Class lE meter replacement.

This deviation

1

occurred when the Class lE Unit 1 diesel generator watt

meters were replaced subsequent to Hot Functional Testing.

(HFT) rather than prior to HFT as committed to in.

TU Electric's letter TXX-88294 dated March 25, 1988.

4

e

The applicant's response to this deviation stated that

this occurrence was the result of an error in.the manual

transcription of data to a new commitment tracking system-

j

(CTS) database.

The applicant's corrective actions

'

'

included enhancing the procedures regarding the use of the

CTS and' review of the CTS database.

Based on the'above corrective actions delineated in.

1

TU Electric's letter TXX-89743 dated October 26, 1989, the

NRC: inspector determined that adequate measures had been

implemented to correct the process which allowed this

deviation.

Therefore, this item is closed.

3.

Action on 10 CFR'Part 50.55(e) Deficiencies Identified by the

Applicant-(92700)

L

a.

(Closed - Unit 1 only) Construction Deficiency

!

L

(SDAR CP-86-03):

" Sealing of Class 1E Devices."

This

deficiency initially addressed an apparent failure to

j

L

install Class lE limin switches in accordance with the

L

manufacturer's requirements concerning both the applica-

tion of qualified conduit thread sealant and the torquing

!

of conduit threads.

Subsequently, the scope of this

,.

.

construction deficiency was expanded to include a poten-

L

tial design deficiency involving the failure to include

L

the required electrical conduit seal assemblies (ECSAs) in

l

the applicable Specification 2323-ES-100.

ECSAs are

L

necessary to preserve the environmental qualification of

',

'

the equipment when located in a harsh environment.

'

In response to this issue, the applicant reviewed

Installation Procedure EEI-21 as well as 20 construction

'

travellers and concluded that the initial aspect of the

deficiency was not substantiated in that both the thread

sealant and the torque requirements were addressed during

li

7

-

-

.

-

-

-

--

.

.

~n,~.'

'

,

'

-

.

-6-

4

,

i;

,

the installation'of limit switches.

Corrective Action

Request (CAR)-048 was initiated to address the'second

aspect of this deficiency and it included the following

corrective actions:

clarification between1the specific.

project engineering requirements and the generically

applied manufacturer's instructions, revision.of Specifi-

cation 2323-ES-28 to include-all lE devices requiring-

'

qualification,'and the revision of Electrical Specifi-

cation 2323-ES-100 to identify devices by type when ECSAs

are required and to list their inspection requirements.

Additionally, the NRC inspector determined that certain.

aspects of this deficiency were addressed by the Correc-

tive Action Program (CAP).

"

. Based on a review of the actions implemented by CAR-048,

the: revision of Electrical Specification 2323-ES-100 and

.the evaluation of the associated = design change authoriza-

tions (DCAs) and NCRs, the NRC inspector determined that.

the' applicant's actions regarding Unit 1 activities-were

acceptable.

Therefore,.this SDAR is closed.

b.

(Closed - Unit 1 only) Construction Deficiency

(SDAR CP-86-40):

" Application of Non-Qualified Agastat-

Relays."

The applicant verbally reported this deficiency-

on May 20, 1986.

It involved the procurement and use.of

,

nonqualified Agastat relays in Class-lE applications,

j

The reportability analysis.and the associated corrective

actions were reported by TU Electric letter TXX-6017 dated.

October 10, 1986. LAs stated in this correspondence, the

corrective actions included:

revising.the vendor designed

equipment drawings to require the use of prequalified.

components,.the revision of the. applicable procurement:

. procedures, the updating of the nuclear operations _

j

L

defective items list (NODIL), and the replacement of the

"

nonqualified relays.

The NRC inspector reviewed the NODIL, Revision 7;

Procurement Procedure WHS-002, Revision 11, as well as

L

various DCAs which replaced the existing relays with

"E"

prefix types; and NCR PE-87-606, Revision 0, which

l

implemented the subject DCAs.

The NRC inspector also

randomly inspected 4 out of approximately 14 affected-

)

cabinets and determined that the relays involved were the

correct

"E" prefix types.

L

Based on the above reviews and inspections, the NRC

L

inspector determined that the applicant's actions for

j

Unit 1 were acceptable; however, pending the implementa-

1

tion of corrective actions for Unit 2, this SDAR is closed

for Unit 1 only.

i

-

.

.-

-

.

.

-

-

-

r .

,_ QY

ls' '

'

)ldi

.n.

-7-

c.

,(Closed,. Unit 1 only) Construction Deficiency

(SDAR CP-86-68):

" Weather Protection for Class 1E-

L

Components:"

Specifically, this deficiency involved rust-

and. water observed inside the exposed Class 1E terminal

boxes.-

The applicant's corrective actions as delineated in

3

TU Electric's letter TXX-88607 dated August 11, 1988,

included the clarification of Electrical Specification

2323-ES-100 pertaining to outdoor conduits / junction boxes

sealing requirements, the performance of walkdowns in.

accordance with FVM-089, and the issuance of 6 NCRs.

The

implementation aspects of FVM-089 have been previously

inspected and accepted as documented in NRC Inspection

Reports- 50-445/88-38, 50-446/88-32; 50-445/88-53,

i:

50-446/88-49; 50-445/89-36, 50-446/89-36; 50-445/89-15,

L

50-446/89-15, and 50-445/89-28, 50-446/89-28.

The NRC

inspector'also reviewed the pertinent changes to

Specification 2323-ES-100 and the 6 NCRs associated with

j

Lthis' issue.

,

Based on the-above documentation reviews and inspections

L

of selected Class 1E terminal boxes, the NRC inspector

= determined-that the applicant's corrective actions.

appeared to have been adequately implemented for Unit 1.

However, in that no work has been performed =on Unit 2,

,

i

_this SDAR is closed for Unit 1 only.

!

d.

(Closed - Unit 1 only) Constructicn Deficiency (SDAR

CP-88-09):

" Electrical Penetration Overload Protection."

As. reported by the applicant, this significant deficiency

p;

involved the potential overloading and lack of backup'

'

' protection devices for electrical penetrations.

This

'

deficiency involved the following three_ subjects:

backup

protection incomplete or nonexistent, protection devices-

uncoordinated with penetration ~ conductor ratings, and.

L

momentary short-circuit currents of module conductors

l'

exceeding the penetration ratings.

The NRC inspector determined that the applicant's

corrective action included the7 incorporation of the

penetration-protection-design criteria in the Design Basis

Document (DBD)-EE-062.

Additionally, compliance with the

applicable design criteria has been addressed >by the

implementation of hardware changes involving the rerouting

^

of cables, the paralleling of penetration conductors, the-

resetting of protective relays, and the replacement or

addition of relays.

The NRC inspector reviewed DBD-EE-062

c

!

and the portions of calculation 16345-EE(B)-048 which were

,

related to this issue.

The NRC inspector also reviewed a

sample of the approximately 32 DCA packages including

DCAs 71741, 75070, 78248, and 85145 which implemented

.

.

.

.

- -

.

,

. -.-

~ ~

~

= ~- '

age

,

,

,

,

i M Vi

i'

yg[ '~ ~

w

.

,.

3+

b

-B-

,

U

~

corrective acticns.

No discrepancies-were_ identified-

4

during this review process.

'The NRC inspector also. conducted inspections of the work.

,

associated withEDCAs 71741 and 85145 and determined that.

the specified hardware changes appeared-complete.

Based _on-the~above reviews.and inspection activities, the

NRC11nspector determined'that the programa and procedures.

a

in~effect appear 1to' adequately control the corrective

actions pertaining to the identified penetration overload 1

_ protection-issues for Unit 1.

This SDAR is considered.

t

closed for Unit 1 only.

e.

'(Closed) Construction Deficiency (SDAR CP-88-35):

"M&TE

Program."

Specifically,;this'SDAR involved deficiencies ~

in-the applicant's calibration' procedures and inadequate /

inaccurate, calibration standards which could have rendered

-

the-accuracy of. measuring and' test equipment (M&TE)

'

indeterminate.~

In response to these issues, CAR 88-029 and several NCRs

were initiated to address the deficiencies which

originated in-the Brown & Root (B&R) calibration facility-

'

on site.

Among other actions, the-CAR discontinued'B&R.

calibration. facility activities, checked /recalibrated

standards'and transferred-them to the applicant's calibra-

. tion facility, and evaluated the effects of calibration'

'

-standard inaccuracies on plant hardware acceptance tests.

In order to evaluate the applicant's actions regarding-

this issue, the NRC inspector reviewed the results of

-CAR 88-29 and Procedure-STA-608, " Control of M&TE," as

i

. well as several specific M&TE calibration procedures and

L

the completed dispositions of 4 out of approximately

i

50 NCRs.

Additionally, the NRC inspector interviewed

selected facility personnel.and observed various activi-

'

ties at the current calibration facility, including the

conduct of specific M&TE calibrations.

As a result of the above reviews and inspection related.

activities, the NRC inspector concluded that the appli-

cant's determination of nonreportability was acceptable-

.

in that no hardware changes-or invalidated tests resulted-

from the completed NCRs.

The'NRC inspector determined-

that, although seme minor issues involving nenprocedur-

alized administrative handling of M&TE records existed,

they did not adversely impact the results of the M&TE-

calibration program.

.

.

..

- .

.

.

-

.

.

_

-

.y.

' [.;^

'

-9-

. 5

i

Based' on the . above reviews- and inspection efforts, the- NRC

inspector determined that the applicant.'s actions in

,

-response to this deficiency were adequate.

Therefore,

this SDAR is closed.

.

,

.

f.

(Closed - Unit 1 only) Construction Deficiency

'

(SDAR CP-88-41):

"W-2-Type Cell Switches." ' Subsequent to

the issuance of ' NRC Information Notice- 87-61 and its-

.

associated supplement-dated May 3',

1988, the applicant

notified the NRC of a deficiency involving Westinghouse

circuit breaker W-2 type cell switches-on' December 2,

.

'

1988.

The applicant's; response to this reportable deficien'cy

a;

included,the. replacement of-four. deficient switches which-

.

were'found during the-performance of: inspections directed _

'

'

by NCR 88-15325, the initiation of DCA-85927 to replace'

I

W-2' switches, and~ implementation-of Maintenance-Proce-

dure MSE-PO-6002 which directed-the inspection of cell.

switches at half the Westinghouse recommended interval.

Based on review of the above documentation and program-

matic evaluations, the NRC inspector determined-that the

applicant's actions in response to this issue were

,

acceptable.

Therefore, this SDAR is closed.

.g.

(Closed) Construction Deficiency'(SDAR CP-89-03):

'" Gamma-Metrics Neutron Flux Monitoring."

This reportable.

deficiency involved Gamma-Metrics' supplied cable:assem-

blies which are used for post-accident neutron-flux

monitoring.

In particular, Gamma-Metrics issued a 10 CFR-

Part 21 notification that identified potential leaks at

the threads / solder connections of the neutron. flux monitor-

cable assemblies.

As stated in TU Electric's final.

response to this issue contained in their letter TXX-89643

dated September 1, 1989, the applicant had received four

of the subject cable assemblies from Gamma-Matrices.

The NRC inspector reviewed the documentation associated-

with this deficiency including the identifying correspond-

ence from Gamma-Metrics to TU Electric dated February 22

and May 10, 1988, and to the Office of Inspection and

Enforcement dated February 19, 1988.

The NRC inspector

also. reviewed NCR 88-19400, Revision 0, which documented

the potential deficiency involving the soldered joints on

the neutron flux monitors and which directed the return of

these devices to the vendor for repair in accordance with-

CPSES purchase order 665-70037.

The subject cable assem-

blies were subsequently returned to the site and were

installed by the vendor for Unit 1.

The Unit 2 cable

assemblies were similarly repaired and placed in storage

,

em . -

mm. - -

-

-

.

- .-

- -

. m

w-

y i n. .

en

,) g

A'

f

-10-

r

l

in the applicant's warehouse.

Concurrently, five of the

detector assemblies (one spare) were returned to Gamma-

Metrics for-inspection, testing, and rework.

The corree-

tive actions associated with the Unit 1 assemblies have-

'

'

been implemented as committed to by TU Electric in their

response to this issue, and the Unit 2 detector assemblies.

1

-

,will be corrected prior to Unit 2 fuel. load.

i

Based-on the above documentation reviews, the NRC

inspector determined that the applicant's corrective

actions regarding this reportable occurrence were-

H

acceptable.

This SDAR is_ closed for Units 1 and 2.

'

h.

(Closed - Unit 1 only) Construction Deficiency-

1

-(SDAR CP-89-21):

"Limitorque MOV Spring' Packs."

The

applicant reported a deficiency involving configuration of

limitorque actuator spring packs which was subsequently.

determined.to,be reportable.

In particular, the model

No.60-600'0022-1 spring packs which were being replaced.

-

had only 11 of the 12 Belleville washers. required for

proper operating characteristics and the replacement-model

No. 0301-113 spring packs had apparently been supplied.

J

with' improper Belleville washer configurations and missing-

^

. locknut setscrews.

Based on communications with.

Limitorque, the' applicant was able to obtain sufficientu

.information;to correctly configure the new spring packs.

1

Further investigation by the NRC inspector revealed that

the-applicant-had questioned:Limitorque regarding the

possible Part 21 action regarding the-misconfigured spring

packs originally provided.

Limitorque-informed-the

applicant that the "-0022" spring packs had been changed-

to model "-0044," and that there was no safety signifi-

,

cance associated with this modification in that the torque-

characteristic of the "-0044" pack was essentially the.

same as the "-0022" pack consequently, no Part 21 action

was contemplated.

As specified in the applicant's closecut documentation,

the corrective actions included the inspection of all-

safety-related MOVs utilizing the "-0022" pack, the

inspection of at least one of each type of spring pack in

all other safety-related=MOVs, and the incorporation of

baseline spring pack configuration data verified by

Limitorque, into the appropriate maintenance procedures.

,

In addition, torque switch setting and operational testing

of safety-related MOVs are continuing in response to NRC

IE Bulletin 85-03.

The NRC inspector reviewed NCRs 89-7483, 6320, 6321,

and 2361 involving MOV spring packs.

Additionally, the

NRC inspector witnessed the complete configuration testing

of the spring pack for 1HV-4286 on work order C89-12527.

-

-

.

- - . . - - - - - -

-

-- .

.-

__

,

y [?:

}

1

CO

-. <

.- s

?

'

-11-

j

,

4

i:

This testing included parts: measurement, configuration

documentation, and load profiling.

During this process,

it was observed that QC was:present for the required.

portions: of the test and no discrepancies were identified.

Based on these reviews and inspection activities, the NRC

4

inspector-determined that.the: applicant's responsesto the.

deficiency was adequate.

In addition, the NRC inspector-

will continue to follow-up MOV' testing and the results of

j

these activities will be documented-in a future NRC

i

inspection report as part of NRC IE Bulletin 85-03

closure. 'Therefore, this SDAR is closed-for Unit 1 only.

.

i.

(Open)z Construction Deficiency (SDAR CP-89-25):

" Site

L

. Fabricated.Thermo-Lag Panels."

This issue concerned site-

h

fabricated thermolag panels which were inspected and_

L

accepted by the applicant's QC organization.

The panels.

were inspected for a,1/2-inch minimum' dry film thickness

(DFT) and were subsequently-determined to be'less than the-

'

specified dimension.

As stated in the applicant's

'

response to'this reportable' condition in TU E3ectric's

letter-TXX-89737 dated October 12, 1989, this material

deficiency impacted approximately 2,000 square' feet of

thermolag that was-installed on cable trays and conduits-

i

in Unit 1 and approximately 11,000 square feet of material

!

that was in the-applicant's warehouse.

Also, during'the

' removal'of site-fabricated panels >from Unit 1, it was

determined that some installed 1 configurations were in

i

disagreement-with the Installation Specification

2323-MS-38H, Revision-2, " Cable Raceway Fire Barrier

Materials."

Specifically, certain thermolag panels were

identified-as having less than the' required 1/2-inch

thickness in the areas of seams', joints, edges, and bolted

L

joints.

Additionally, some of the removed panels had been

'

modified to accommodate extended configuration' geometries-

without proper compensation-for the reduced material

thickness.- This issue affected an additional estimatedt

12,000 square feet of installed thermelag.

As stated in

the applicant's final response to this deficiency, had

this condition remained-uncorrected, the potential existed

that a fire could have breached the barrier and adversely

affected-the ability to safely shut down-the plant.

'

In order to evaluate this issue, the NRC inspector

reviewed the associated documentation including NCRs

89-8519, 89-9313, and 89-09314; Construction Hold Notice

-

Form 572; Procedure ECC 10.07, " Application of Fire

.

'

Protection Materials"; Procedure NQA 3.09-1.07, "Inspec--

tion of Fire Protection Cable Raceway and Structural

Steel"; CAR 89-009; Specification .2323-MS-38H, " Cable

Raceway Fire Barrier Materials"; and the subject material.

-.

..

-

7 3 : :. -

- - ~

-

e

.

e

[.

,q .;

-12-

l

-

.

i

'

These reviews indicated that the applicant's 3.nitial

corrective actions as prescribed-by the-above-mentioned-

NCRs included the scrapping of'the defective: (site .

.

fabricated thermolag) panels in the warehouse.

Also, the

.

.

questionable configurations-installed on cable trays and

L

,

l

conduits in the plant were removed and were'-replaced-with

p

thermolag purchased from an approved vendor-(Thermal-

Science, Inc.).

Additionally, the NRC inspector conductedu

evaluations of work in progress in both the Safeguards and.

the Auxiliary buildings duringrthe removal of defective

thermolag and the subsequent-replacement process where

,

. vendor supplied' material was utilized.

These' efforts were-

H-

generally conductrd'in accordance-with the-insta11ationx

K

specification with-the exception of the deficient condi-

L

tions documented on NCR 89-11142, Revision 1.

This NCR

,

-

l

identified discrepancies associated-with the vendor'

L

supplied (prefabricated sheets) of thermolag which were

L

determined to haveivariations in-thickness ranging from-

3/8. inch to 1L1/4 inch,

c

'

L'

The'NRC inspector reviewed the applicant's technical _

L

disposition of NCR. 89-11142, Revision 1,.and determined-

R

that although the basis'for accepting the reported-

l

condition = appeared-adeqcate in that this condition-was

,

l

determined by the supplier to not be detrimental to-the

fire-resistant response'of the' panel, this~ anomaly could

have been avoided-had~the-applicant not deleted-its site

QC inspection requirements for the thickness attribute-

from Verification Plan 89-2092.

Based on discussions with

members of the applicant's QA and QC staff, it was: deter-

mined that these inspection criteria were deleted-from-the

receipt inspection verification plans by-Procurement

Engineering'(Change Order 6C33604).

This action was

reportedly the result of the supplier's status (with no

restrictions) on TU Electric's approved vendor-list.

This decision by-the applicant's procurement Engineering

organization was apparently made in the absence of-histor-

'

'

ical information-relative to thermolag discrepancies.

The

applicant's failure to provide ~ adequate receipt inspection

criteria for the vendor procured thermolag material, which

could have detected this deficient condition and averted

the potential for significant rework-, is identified as a

weakness within the procurement program.-

The NRC inspector also examined-the process whereby

site-fabricated-thermolag which did not comply with the

"

required dry film thickness (DFT) had been inspected and

accepted by the applicant's QC staff.

This examination

revealed that the-material in question had been inspected

-

.

.

.

.

- -

s.

,.

,

h;

s:

-13-

under.the auspices of Procedure QI-QP-11.20-1 which was in-

effect from- October 1982 through December: 1986. - _ Although--

J

K

this procedure underwent:several revisions during this:

time frame,.the-requirement to verify'a DFT of-1/2-inch.

j

minimum was continuously mandated during-the preapplica-

tion inspection process.

' Additionally, the controlling;

i

'

~

Specification'2323-MS-38H, Revision-2, " Cable Raceway-Fire'

Barrier- Materials,": stated-, in part, that-Thermelag 330-1

.j

(site; prefabricated sections) shall have-a dry film-

thickness-of 1/2 inch ~-to 3/4' inch.

J

As delineated in NCR 89-8519, the deficiency in the-DFT

.

involving the site-fabricated thermolag was identified on

,

- Julyc28, 1989.

This NCR indicated that several panels-

were examined by engineering personnel and all boards.

selected. were determined to exhibit. a DFT measurement' of-

L

less than the required 1/2-inch minimum.

As described-by

representatives'of the applicant's QC organization'during-

a' meeting.with members'of the NRC Resident-Inspector's

i

staff on October? 26, 1989, the reported' condition was

L

potentially attributable to fabrication techniques util--

,

imed by the applicant during the manufacturing of,thermo-

lag panels on-site which did not provide-for a proper cure:

L

time: prior to:DFT measurements,

Thus, subsequent to DFT

measurements, the- site-f abricated panels " settled" produc -

1

ing the nonconforming condition.

As described-by the-

applicant during the referenced meeting, the-recommended.

cure time: for these panels was approximately -20 days;-

however, this consideration was:not factored-into the

inspection verification plan 1and'no mechanism existed-to-

_

'

detect this defect following-the fabrir,ation DFT

- inspections.

Based on the NRC inspector's . review of the associated-

documentation, system inspections, and the-results of

-

- several meetings with representatives of the-applicant's-

QA/QC and licensing organizations, it-was determined that

the dimensional inspections required by the applicant's

Materials Specification 2323-MS-38H, Revision 2, and by

Inspection Procedure QI-QP-11.20-1 to insure a minimum DFT

of 1/2-inch minimum to 3/4-inch maximum were-inadequate

and were not properly performed to insure that the

specified-inspection criteria were maintained.

This example of failure to follow procedures during

QC inspections performed on deficient site-fabricated-

thermolag material is identified as a violation

(445/8971-V-01).

Additionally, during the assessment of SDAR CP-89-25, the-

NRC inspector identified several questionable issues

concerning the applicant's response-to this event.

In

.

Y

" "

w

&

Wes

o

s

,+

'

'

'

f J.

,

, gy

-

>

  • .

44

L

-14-

'

I

o

particular, the-documented actions relative to this

reportable deficiency contained, in part, in CAR 89-09,

E

neglected?to address the inadequate' inspection tech-

L.

niques/ criteria which allowed the deficient site -

'

L

fabricated thermolag material to be inspected and accepted

for' installation without detection.

As stated in this

..

CAR, the actions to preclude. recurrence simply concluded 1

l

-that site-fabricated;thermolag panels would not be used

for future applications. .Furthermore,.the generic

' implications: stated 11n the CAR were. inadequately-addressed:

I

in-that the conclusion indicated that there were no

o"

-generic implications.

This conclusion. ignored-the

I

ramifications implicit in a QC program which failed'to

detect a significant deficiency.

The applicant's final response to the issue, contained in

j

TU Electric's letter TXX-89737, failed to adequately

i

'

identify _the cause of this significant condition. adverse.

1

L

to quality.in that the conditions which allowed the

E

deficient site-fabricated material to be inspected,

1

'

L

accepted by QC, and subsequently. installed were not

I

adequately addressed.

No specificity was provided in this

'

response.to provide assurance that the cause of the

condition.had been-properly determined or that.the

'

' corrective actions to prevent reoccarrence were adequate.

Collectively these deficiencies in the applicant's

response-to this event which represented a1significant

condition adverse to quality are identified as a violation-

!

(445/8971-V-02):

failure to' assure that the cause of the.

condition is detennined and corrective action is. taken to

preclude repetition.

4.[

Allegation Follow-up (99014)

!

a.

(Closed) Allegation (OSP-89-A-86):

This. allegation

involved the termination of a worker subsequent to the

,

incorrect cutting of safety-related. wires associated with.

_l

the heating, ventilation, and air-conditioning (HVAC)

'

system.

The alleger stated his concerns to members of the

NRC. Resident Inspector's office at Comanche Peak on

4, y

'-

September. 14, 1989.

1

The alleger stated that he had been formerly employed as a.

4

,

.'

' journeyman: electrician by an onsite contractor, but that

I

he had been terminated on or about August 15, 1989.

The

alleger went on to state that immediately preceding his

termination he had been performing safety-related work

(Train A) on the 852 foot level in the safeguards build-

ing, room 150, when he was directed by his foreman to cut

specific wires in a pull box.

The alleger also stated

that the work was being performed in accordance with a DCA

_ _

__

_

, ft ur

<

,

t

,n.?

-

a

4

-15 ~'

(unspecified)zwhich was associated with the' repair of an

electrical. seal that was out.of service in the room.

The

-alleger stated that an electrical QC inspector was present

,

'

below the work area, and that after. confirming with his

r

foreman which wires were to be. cut, he completed the-

.

action by severing the conductors.

Subsequent to this

activity, the alleger was advised by-the QC inspector that-

he had cut the wrong conductors and that an NCR was being

written.

The alleger stated that he had been specifically directed-

by his foreman.to. accomplish this activity and that the-

'

punitive action taken against him was unfair.

The alleger

also stated that he had provided his concerns to SAFETEAM.

The NRC inspector asked the alleger if there_were any

other, witnesses to.this. event or if the QC inspector could-

corroborate his statements regarding the verbal directions--

provided;to'the alleger by'his foreman.

The alleger

stated that there were no other witnesses and that the QC

1

inspector could not substantiate his statements.

Subse-

quent to the alleger's identification of this issue, the

NRC inspector conducted a field walkdown of the associated:

equipment including junction . box JB11A11330 and conduit .

C14021429. -These components 1were the subject of

-NCR 89-8417, Revision 3, which stated, in part, that due

,

to a craf t: error, cable E0146318 had been. cut in JB1A11330

rather than at-the condulet as required in Revision 2 of.

this NCR.

The NRC inspector also examined.the SAFETEAM files

concerning this. issue including Corporate Security's

investigation which appeared to have been. thorough in thats

all persons involved. including the alleger, his foreman,

the general foreman, the -QC inspector. involved in

identifying and reporting this condition, and.a. fellow

worker who was assigned to this work activity were

interviewed.

As. stated in this report, the alleger's

assertion that he had been unfairly terminated for viola-

ting procedures in that he was following his foreman's

instructions was not supported.by the investigation.

Corporate Security's investigation concluded that this

individual was dismissed for negligence.

Although the termination of this individual appears

unnecessarily harsh, given that the technical dispositial

of NCR>89-8417, Revision 3, concluded that the cutting of

cable E0146318 at JB1A11330 had no impact on the disposi-

tion of the. subject NCR, the. statements from the indivi-

duals interviewed indicated that the alleger was instruct-

ed to cut the cable inside the condulet, and then pull

them from the junction box.

The NRC inspector also

.

. .

.

.

.

-

~~

l

n .

.

.,

e..<.-

i

Lej

x

-16-

,

..

examined the findings of the Termination Review Committee:

,

which reviewed this case and affirmed the recommendation!

)

for termination.on August 15, 1989.

'

Based on the above reviews, discussions with the

applicant'sfSAFETEAM and Corporate Security personnel; and

related inspection activities, the NRC inspector deter-

mined thatLthe alleger had incorrectly cut safety-related

wires associated with the HVAC system at junction box:

JBilA11330 and that his assertion that he was only follow '

ing the. instructions of his foreman.could not be substan--

tiated.. However, given the minimal effect of this appar-

c

ent miscommunication between an electrical foreman and an.

electrician on the system work being performed, the.

termination action. appears to be extreme,

b.

(Closed) Allegation (OSP-89-A-69):

Directed procedure.

violations and.SAFETEAM: conflict of interest.

This.

allegation involved the circumventing of M&TE procedures-

at the direction of a group leader and the associated.

inability"to communicate-these concerns to SAFETEAM in;

that the group leader's spouse.was employed at SAFETEAM.

The NRC-inspector reviewed the M&TE facility, the-

governing procedures, and.in-process calibrations as part.-

of the closure process for.SDAR CP-88-35 (see para-

graph.3.e of-this report).

As noted in.~the closure of.

this item, minor weaknesses were noted in the.M&TE program'

but no additional. allegations or evidence of deliberate-

procedure violations were identified by the NRC inspector.

A review of SAFETEAM records 1 revealed no additional

concern specifically regarding the subject. group leader;

however,.a previous concern, No. 11630, did. involve the.

i

apparent. conflict of interest _resulting from the SAFETEAM

member /M&TE group leader relationship.

The NRC inspector

determined that the. applicant.had addressed;this potential-

conflict by implementation of policy constraints.which

,

specified that-the subject SAFETEAM member involved.would:

remove themselves from any concern related to the group:

leader or CPSES operations in general.

However,'the NRC.

inspector's invcutigation indicates that the current.

allegation supports the perception by plant personnel.that

1

there is a conflict which could. impede.the free flow of

1

information to-SAFETEAM.

In that the NRC inspector was-

unable to substantiate the procedural violation aspects of

'

this allegation, this item is considered closed.

No violations or deviations were identified.

5.

Electrical Components and Systems (51053, 51063, 52053)

During this reporting period, the NRC inspectors performed.

direct inspections of work performance to determine if the

technical requirements contained in the applicant's Final

.

. . .

- -

~.

.

. .

-

_ _ .

._

.

_

,,;;4

,lQl

..,

-17--

SafetyiAnalysis Report (FSAR) for safety-related electrical

systems and components.had been adequately translated into.

applicable: drawings, procedures, and. instructions.

Addition-

. ally,- the NRC inspectors evaluated the applicant's work control

program-to ' determine. if the specified documents and procedures:

.were of sufficient detail to provide adequate. work performance:

and. control.

As part of the inspection. requirements for IE Bulletin 85-03,

the NRC inspector observed. dynamic motor operated valve testing:

(MOVAT) of 1HV-2493A, auxiliary feedwater isolation valve. .The

valve performed properly on closing and opening against an

operating differential. pressure of approximately 1515 psig.

Review of the valve signature data revealed no discrepancies of

torques, motor current, etc.

I

The NRC inspector also observed work in progress for package.

ECE-89-01073, " Tag Maintained Space Cables During Train A

~

Outage.89-091."

The NRC inspector determined that this work.

~

was being performed in accordance with DCA 77139 and work order:

~C89-0013439 at the.480v motor control center MCC XEB1-2.

The

NRC inspector observed that the labels identifying " maintained

space" cables were being properly affixed where cables were not

'

already identified.. The NRC inspector's review of the package-

and work. process.didinot reveal any. discrepancies,and it was-

observed that a QC representative was present at-the job site

for the performance of specified witness points.

Within the. instrumentation. area, the NRC inspector observed the

installation of 1PT-3616 in accordance with work. package:

SWP-Z-5714.

This work also involved the implementation of-

DCAs 89836.and 84502 and work packages lLT-3615 A and B in

response to NRC Generic Letter 88-17 regarding reactor coolant

level' monitoring during mid-loop operations.

Additionally, the

NRC inspector _ observed installation.of conduit supports-

.

involving. conduit C14036219.

During the conduct of these

activities, no discrepancies were identified by the NRC

inspector.

No violations.or deviations were identified.

6.

Safety-Related Components, Mechanical (50071, 50073)

Reverse Flow Testing of Borg-Warner Check Valves

As a follow-up to the events which identified multiple failures

'

of Borg-Warner check valves in the auxiliary feedwater system,

previously documented in NRC Inspection Reports 50-445/89-30,

50-446/89-30; and 50-445/89-64, 50-445/89-64, the NRC inspector

j

-

-

.

.

. .

_

.

.

. .

. -

..

-_

m

7 c,

w.

.-

cop

k

'

,

18 -

-

. witnessed the: reverse flow leak testing of the.following.

.Borg-Warner check valvest.

,

lAF-057.

3" pressure seal

Procedure EGT-328A.

lAF-083

4" pressure seal

Procedure EGT-328A

1AF-093-

4" pressureiseal

Procedure EGT-328A

1AF-167

8" bolted bonnet:

Procedure EGT-165

'

u

.The NRC inspector determined that the test personnel involved;

appeared knowledgeable and that they efficiently performed-the

l

. required evaluations.

All reverse flow tests witnessed had~

-

satisfactory results and no: discrepancies were-identified;

j

I

during either the; performance or the documentation phase.of

this program.

,,

The reverse flow testing.of.the 80 Unit 1 Borg-Warner. check-

valves is approximately 65% complete.

The NRC inspector;

,

previously reviewed the applicant's program and procedures form

i

testing the operability of Borg-Usxaer check valves and.

!

witnessed:two additional, tests as-documented in NRC Inspection:

l

I

Report.50-445/89-73; 50-446/89-73.

Due to differences in.

sister- configuration, the availability of drain and test

valves,.etc.,-diverse methods are employed to test the rubject:

i

' valves.

These methods include theLfollowing configuration:

options:

Test Method

No. of

System Valves

Demin Water Pressure Test

37

l

System pressure

9

Radiograph. Test

26

10 CFR 50, Appendix J, Local Leak Rate Test

6

Air Pressure Test

2

,

Total.

80

The NRC inspector has reviewed the film records from several

radiograph tests and determined that they were of good quality

and provided a definitive test methodology.

To date, four valves have required rework following their

initial: failure to pass the reverse flow leak test.

The root

_

cause and corrective action for these valves is summarized:

below:

Valve 1AF-0083;(valve body / bonnet) was rotatively misaligned

,

and the disc-stud was bent.

A new disc-stud assembly was

'

installed, the valve internals were reinstalled, and the

reverse flow leak testing was satisfactory.

Valve ICA-0016 exhibited excessive seat leakage.

The swing arm

"

and bushing were replaced and the valve was blue checked.

The

~

,

,,

--

,

- - , - - , - , -

, , , ,

,,----a

+-,m

,

e -

~

m

.

.

t. : w ,y

-

.

y;

-o

E ?.i

..-

-

r

-19-

-

NM

. valve internals were reinstalled and the subsequent reverse.

flow leak testing-was satisfactory.

.

Valve 1AF-0057 exhibited . unacceptable valve body / bonnet:

rotational misalignment and incorrect bonnet elevation.

The

valve was disassembled and supplemental measurements'were-

taken, the. valve internals were reinstalled using the new-

height specification, and the valve was successfully testedrin

+

the reverse flow direction.

' Valve 1SW-0048 was determined to have an excessively long swing'

arm bushing.

The bushing length was reduced by 0.08" and

replaced in the disk-stud. assembly.

The valve internals were-

1

reinstalled and.the valve was successfully tested in the-

reverse flow direction.

In conjunction with-the above documented activities,.the.

l

applicant has revised the Borg-Warner check valve reassembly'

procedure and designed a specialized set of tools tx) allow for.

the establishment of more precise rotational alignment of then

bonnet to the valve body. .The NRC inspector witnessed a

t

demonstration of the new tools and technique in the mechanical.

maintenance shop and.the reassembly of valve 1AF-045 in the

plant.

The NRC inspector concluded. that the new procedure will

enhance the rotational. alignment between the valve bonnet and.

body.

L

During the latter portion of this reporting period,

approximately 13 Borg-Warner check valves in the auxiliary

'

feedwater and feedwater cystems were identified by the

applicant as having excessive body to bonnet external leakage.

These valves are presently being: disassembled,. honed to remove-

scratches in the valve body throat and-provide better sealing-

surfaces, reassembled, and leak tested.

NRC inspection of

,

these activities will be continued.:

'.

.

No violations or deviations were identified.

'

7.

Plant Tours (51063)

The NRC inspectors conducted routine plant tours during this

inspection period which included evaluation of work.in progress.

as well as completed work to' determine if activities involving

safety-related electrical systems and components including'

electrical cable were being controlled and accomplished.in.

accordance with regulatory requirements, industry standards,

and the applicant's procedures.

No violations or deviations were identified.

.

.-. . -

e

.

.

.

e'

e:

tl *

..

'o

-20 -

8.

' Exit Meeting (30703)

An exit meeting'was conducted November 7,.1989, with the.

applicant's representatives identified in paragraph 1 of this.

report.

No written material was provided to the applicant by

the inspectors during this reporting period.

The applicant'did..

-

not-identify as proprietary any of the materials provided to or.

reviewed by the inspectors during this inspection.

During this.

meeting, the NRC inspectors summarized the scope and findings:

of the. inspection.

l

!'

1

l-

_ . _

. . . . . . . . .

. _ . . , _

.-

_ _