NRC Accepted of Gle Request to Update the Pcsp Revision 8 and Annual Continuous Monitoring Report Revision 4 (GLE-2019-0130)
ML19352E248
Person / Time
Site: 07007016
Issue date: 12/23/2019
From: Matt Bartlett
NRC/NMSS/DFM/FFLB
To: Jenny P
Global Laser Enrichment
MABartlett NMSS/DFM/FFL 415.7154
References
EPID L-2019-SPR-0000
Download: ML19352E248 (3)


Text

December 23, 2019 Ms. Pat Jenny, Security Manager General Electric-Hitachi Global Laser Enrichment, LLC P.O. Box 780 3901 Castle Hayne Road Wilmington, NC 28402

SUBJECT:

ACCEPTANCE OF GLOBAL LASER ENRICHMENT REQUEST TO UPDATE THE PROGRAM CYBER SECURITY UPDATE REVISION 8 AND ANNUAL CONTINUOUS MONITORING REPORT REVISION 4 - ENTERPRISE PROJECT IDENTIFICATION NUMBER L-2019-SPR-0000

Dear Ms. Jenny:

The U.S. Nuclear Regulatory Commission (NRC) staff has received your submittal letter, GLE-2019-0130, dated November 22, 2019 (Agencywide Documents Access and Management System (ADAMS) Number ML19343B620). The submittal provides a revised Revision 8 to the Program Cyber Security Plan (PCSP) in response to U.S. Department of Energy Request for Additional Information issued on November 13, 2019 (ADAMS Accession No. ML19326A211).

In addition, the submittal included an update to the PCSP Annual Continuous Monitoring Report Revision 4.

The NRC staff, in consultation with U.S. Department of Energy (DOE) staff, have completed the acceptance review of your submittal and no administrative omissions or deficiencies were identified that would prevent us from proceeding with a detailed review. Your submittal has been assigned Enterprise Project Identification Number (EPID) L-2019-SPR-0000, Global Laser Enrichment (GLE), Information Security Oversight.

Please note that the NRC staffs technical review of your submittal may identify issues that require additional information. Based on our preliminary evaluation and projection of current review schedules, we anticipate completing our formal review by November 29, 2019. This date could change depending on the findings of our technical review, urgent assignments, or other factors. We will promptly communicate any significant changes to this schedule. In addition, the NRC staff estimates that completing the review of your submittal will require approximately 10 NRC staff hours which corresponds to about $2,780.00 ($278.00/hr.) and an estimated

$3000.00 in contract costs.

Note: a copy of the submittal package was not received by the NRC Document Control Desk which resulted in a delay in processing till December 9, 2019. To avoid this type of delay in the future, please address public and sensitive unclassified non-safeguards information (SUNSI) documents consistent with the Title 10 of the Code of Federal Regulations 70.5, Communications, as follows:

P. Jenny 2 ATTN: Document Control Desk, Director, Nuclear Materials Safety and Safeguards, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001 Or, you may use electronic submission as described at https://www.nrc.gov/site-help/e-submittals.html, which is available for both public and SUNSI documents.

In accordance with Title 10 of the Code of Federal Regulations, Section 2.390 of the NRCs Agency Rules of Practice and Procedure, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of the NRCs ADAMS. ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

If you have any questions regarding this communication, please contact me at 301-415-7154, or via e-mail to matthew.bartlett@nrc.gov.

Sincerely,

/RA/

Matthew A. Bartlett, Project Manager Enrichment and Conversion Branch Division of Fuel Cycle Safety, Safeguards, and Environmental Review Office of Nuclear Material Safety and Safeguards Docket No.: 07007016 License No.: SNM-2019 cc: gle@listmgr.nrc.gov

ML19352E248 OFFICE DFM/FFLB DFM/FFLB DFM/FFLB NAME MBartlett ELee JIZimmerman DATE 12/20/2019 12/23/2019 12/23/2019