ML19352A018
| ML19352A018 | |
| Person / Time | |
|---|---|
| Site: | Calvert Cliffs |
| Issue date: | 12/11/1980 |
| From: | Robert Carlson NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
| To: | Lundvall A BALTIMORE GAS & ELECTRIC CO. |
| Shared Package | |
| ML19352A016 | List: |
| References | |
| NUDOCS 8102250455 | |
| Download: ML19352A018 (2) | |
See also: IR 05000317/1980021
Text
A
e
p Kgg
o
UNITED STATES
g
! f 3 s,
g
NUCLEAR REGULATORY COMMISSION
'
';; '
8
REGION I
o, '
8
631 PARK AVENUE
O'
'
%, ..... d
KING OF PRUSStA, PENNSYLVANIA 19406
j
-
DEC .1 :::)
Docket No. 50-317
Baltimore Gas and Electric Company
ATTN:
Mr. A. E. Lundvall, Jr.
Vice President, Supply
P. O. Box 1475
Baltimore, Maryland 21203
Gentlemen:
Subject:
Inspection 50-317/80-21
This refers to the routine inspection conducted by Mr. E. Jernigan of this
office on October 22-24, November 5-7 and November 13-14, 1980, at Calvert
Cliffs Nuclear Power Plant, Unit 1, at Lusby, Maryland, of activities authorized
by NRC License No. OPR-53 and to the discussions of our findings held by Mr.
Jernigan with Mr. L. Russell at the conclusion of the inspection.
Areas examined during this inspection are described in the Office of Inspection
and Enforcement Inspection Report which is enclosed with this letter.
Within
these areas, the inspection consisted of selective examinations of procedures
and representative records, interviews with personnel, and observations by the
inspector.
Based on the results of this inspection, it appears that one of your activities
was not conducted in full compliance with NRC requirements, as set forth in
the Notice of Violation, enclosed herewith as Appendix A.
This item of noncom-
pliance has teen categorized into the levels as described in our correspondence
to you dated December 31, 1974.
This notice is sent to you pursuant to the
provisions of Section 2.201 of the NRC's " Rules of Practice," Part 2, Title
10, Code of Federal Regulations.
Section 2.201 requires you to submit to this
office, within twenty (20) days of your receipt of this notice, a written
statement or explanation in reply including:
(1) corrective steps which have
been taken by you and the results achieved; (2) corrective steps which will be
taken to avoid further items of noncompliance; and (3) the date when full
compliance will be achieved.
In accordance with Sectiora 2.790 of the NRC's " Rules of Practice," Part 2,
Title 10, Code of Federal Regulations, a copy of this letter and the enclosures
will be placed in the NRC's Public Document Room.
If this report contains any
90 '3I
.
gg-
,
--
w-
y
o
.
Baltimore Gas and Electric Company
2
information that you (or your contractor) believe to be proprietary, it is
necessary that you make a written application within 20 days to this office to
withhold such information from public disclosure. Any such application must be
accompanied by an affidavit executed by the owner of the information, which
identifies the document or part sought to be withheld, and which contains a
statement of reasons which addresses with specificity the items which will be
considered by the Commission as listed in subparagraph (b) (4) of Section
2.790.
The information sought to be withheld shall be incorporated as far as
possible into a separate part of the affidavit.
If we do not hear from you in
this regard within the specified period, the report will be placed in the
Public Document Room.
Should you have any questions concerning this inspection, we will be pleased
to discuss them with you.
Sincerely,
/'
W
d~
Robert T. Carlson, Chief
Reactor Construction and Engineering
Support Branch
.
Enclosures:
1.
Appendix A, Notice of Violation
2.
Office of Inspection and Enforcement Inspection Report Number
50-317/80-21
cc w/encls:
R. M. Douglas, Manager, Quality Assurance
L. B. Russell, Plant Superintendent
T. Sydnor, General Supervisor, Operations QA
R. C. L. Olson, Principal Engineer
J. A. Tiernan, Manager, Nuclear Power
R. E. Denton, General Supervisor, Training and Technical Services