ML19351F262
| ML19351F262 | |
| Person / Time | |
|---|---|
| Site: | Grand Gulf |
| Issue date: | 11/21/1980 |
| From: | Murphy C NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| To: | Stampley N MISSISSIPPI POWER & LIGHT CO. |
| Shared Package | |
| ML19351F258 | List: |
| References | |
| NUDOCS 8101120081 | |
| Download: ML19351F262 (2) | |
See also: IR 05000416/1980025
Text
!
-
-
.
.
,
t
e asog'o
UNITED STATES
,
8
NUCLEAR REGULATORY COMMISSION
0E,
Ag)E
o
.s E
REGION 11
e
+"
101 MARf ETTA ST., N.W., sulTE 3100
g**Q [
ATLANTA, GEORGIA 3o3o3
NOV21ago
In Reply Refer To:
RII:WHM
50-416/80-25
50-417/80-15
Mississippi Power and Light Company
ATTN:
N. L. Stampley
,
Vice President of Production
P. O. Box 1640
Jackson, MS 39205
Gentlemen:
This refers to the inspection conducted by W. H. Miller, Jr. of this office on
October 28-31, 1980, of activities authorized by NRC Construction Permit Nos.
CPPR-118 and CPPR-119 for the Grand Gulf facility, and to the discussion of our
findings held with J. P. McGaugby, Jr. at the conclusion of the inspection.
Areas examined during the inspection and our findings are discussed in the
enclosed inspection report.
Within these areas, the inspection consisted of
selective examinations of procedures and lepresentative records, interviews with
personnel, and observations by the inspector.
We have examined actions you have taken with regard to previously identified
enforcement matters and unresolved items. The status of these items is discussed
in the enclosed report.
One new unresolved item resulted from this inspection and is discussed in the
enclosed report. This item will be examined during subsequent inspections.
During the inspection, it was found that certain activities under your license
appear to be in noncompliance with NRC requirements. This item and references
to pertinent requirements are listed in the Notice of Violation enclosed herewith
as Appendix A.
This natice is sent to you pursuant to the provisions of Section
2.201 of the NRC's " Rules of Practice," Part 2, Title 10, Code of Federal Regula-
tions.
Section 2.201 requires you to submit to this office, within 20 days of
your receipt of this notice, a written statement or explanation in reply including:
(1) corrective steps which have been taken by you and the results achieved; (2)
corrective steps which will be taken to avoid further noncompliance; and (3) the
date when full compliance will be achieved.
During the inspection it was found that certain activities under your license
appear to deviate from commitments to the Commission and from applicable guides,
codes or standards which are approved by the Comm.9sion and have safety signifi-
This item identified in the Notice of Deviation enclosed herewith as
cance.
Appendix B.
Please provide us in writing within 20 days of your receipt of this
,
letter your comments including a description of corrective actions that h.c.ve
been or will be taken, corrective actions which will be taken to avoid further
deviations, and the dato corrective actions were or will be completed.
81033 ROD 37
-
. . _ . _ , _
. .
_
_
_ _ _
_ . . _ . .
_.
.
. . . .
-.
- -~
.
.
.
~
Mississippi Power and Light Company
-2-
.
In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,
Title 10, Code of Federal Regulations, a copy of this letter and the enclosed
inspection report will be placed in the NRC's Public Document Room.
If this
report contains any information that you (or your contractor) believe to be
proprietary, it is necessary that you make a written application within 20 days
to this office to withhold such information from public disclosure. Any such
application must include a full statement of the reasons on the basis of which
it is claimed that the information is proprietary, and should be prepared so
that proprietary information identified in the application is contained in a
separate part of the documer.t. If we do not hear from you in this regard within
the specified period, the report will be placed in the Public Document Room.
Should you have any questions concerning this letter, we will be glad to discuss
them with you.
Sincerely,
C. E. Murphy, ~ Chic
Reactor Construction and Engineering
Support Branch
Enclosures:
1.
Appendix A, Notice of Violation
2.
Appendix B, Notice of Deviation
3.
Inspection Report Nos. 50-416/80-25
and 50-417/80-15
,
cc w/ enc 1:
C. K. McCoy, Plant Manager
,