Forwards IE Insp Rept 50-438/80-26 on 801113.No Noncompliance Noted
ML19351F007
Person / Time
Site: Bellefonte Tennessee Valley Authority icon.png
Issue date: 12/09/1980
From: Kenna W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Parris H
TENNESSEE VALLEY AUTHORITY
Shared Package
ML19351F008 List:
References
NUDOCS 8012190716
Download: ML19351F007 (2)


See also: IR 05000438/1980026

Text

M

-

.

.

-i

-

21

R

a

In Reply Refer To:

DEC 0 91980

1

m

w

RIJ:BLH -

.2

v. '4

4 0-438/80-26)

$$

g

y

W

G

  1. 5

Tennessee Va. ley Authority

5

EE

3

ATTN:

H. G. Parris

<>

flanager of Power

500A Chestnut Street Tower II

Chattanooga, TN 37401

Gentlemen:

This refers to the inspection conducted by A. Tillman of this office on

November 13, 1980, of activities authorized by NRC License No. SNM-1865

for the Bellefonte facility and to the discussions of our findings held

with W. Dahnke at the conclusion of the inspection.

Areas examined during this inspection included your physical security program

as implemented under the provisions of Title 10, Code of Federal Regulations,

Part 73, " Physical Protection of Plants and Materials" and the specific

requirements of your approved Security Plan. Within these areas, the

inspection consisted of selective examinations of procedures and representa-

tive records, interviews with personnel, performance tests, and observations

by the inspectors.

Within the scope of this inspection, no items of noncompliance were disclosed.

.

In accordance with Section 2.790(d) of the NRC's " Rules of Practice," Part 2,

Title 10, Code of Federal Regulations, activities involving safeguards and

security measures are exempt from public disclosure; therefore, the enclosed

inspection report with the exception of the report cover page, which is an

inspection summary, will not be placed in the Public Document Room.

Should you have any questions concerning this letter, we will be glad to

discuss them with you.

Sincerely,

,

,~

'

i

. , -

. [t wG

4. B. Ken a, Chief

'

Safeguard Branch

Enclosures:

1.

Inspection Summary

(NotExempt)

2.

Inspection Report No. 50-438/80-26

(Exempt from Disclosure)

80121909/(p

p

. - .

.

- ~

.

.

..

..

..

_

. .

- .

_

. - .

_

__ . . . . _ . . _ . _ . _ _ .

.__

_ ._ . ..

OtC 0 91980

.

.

.

Tennessee Valley Authority

-2-

,

cc w/ enc 1:

A. M. Quills, Plant Superintendent

W. R. Dahnke, Project Manager

J. F. Cox, Supervisor, Nuclear

Licensing Section

D. L. Terrill, Project Engineer

H. N. Culver, Chief, Ne;1ea- Safety

Review Staff