Forwards IE Insp Repts 50-352/80-15 & 50-353/80-13 on 800805 & 07-08.No Noncompliance Noted
ML19351D396
Person / Time
Site: Limerick  Constellation icon.png
Issue date: 08/21/1980
From: Robert Carlson
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Kemper J
PECO ENERGY CO., (FORMERLY PHILADELPHIA ELECTRIC
Shared Package
ML19351D397 List:
References
NUDOCS 8010100062
Download: ML19351D396 (2)


See also: IR 05000352/1980015

Text

f%

j#

g

W

UNITED STATES

4

p

-' *g

NUCLEAR REGULATORY COMMisslON

j

j

REGION B

$31 PARK AVENUE

W

' ,f

d

e

KING OF PRUS$1 A. PENNSYt.V ant A 19406

AUS 2 1 Bil

Docket Nos. 50-352

50-353

Philadelphia Electric Company

ATTN: Mr. John S. Kemper

Vice President

Engineering and Research

2301 Market Street

Philadelphia, Pennsylvania 19101

Gentlemen:

Subject: Combined Inspections 50-352/80-15 and 50-353/80-13

f

This refers to the routine inspection conducted by Mr. S. Reynolds, Jr. of this

office on August 5, 7 and 8,1980, at Limerick Generating Station, Limerick,

Pennsylvania, of activities authorized by NRC License Nos. CPPR-106 and CPPR-107

and to the discussions of our findings held by Mr. Reynolds with Mr. D. DiPaolo

of your staff at the conclusion of the inspection.

Areas examined during this inspection are described in the Office of Inspection

and Enforcement Inspection Report which is enclosed with this letter. Within

these areas, the inspection consisted of selective examistions of procedures

and representative records, interviews with personnel, and observations by the

inspector.

Within the scope of thi= inspection, no items of noncompliance were observed.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2, Title

10, Code of Federal Regulations, a copy of this letter and the enclosed inspection

report will be placed in the NRC's Public Document Room.

If this report contains

any information that you (or your contractor) believe to be proprietary, it is

necessary that you make a written application within 20 days to this office to

withhold such information from public disclosure. Any such application must be

accompanied by an affidavit executed by the owner of the information, which

identifies the document or part sought to be withheld, and which contains a

statement of reasons which addresses with specificity the items which will be

considered by the Commission as listed in subparagraph (b) (4) of Section

2.790.

The information s>;ght to be withheld shall be incorporated as far as

possible into a separate grt of the affidavit.

If we do not hear from you in

this regard within the specified period, the report will be placed in the Public

Document Room.

.

801010coroA

g

._

.

.

!

Philadelphia Electric Company

i

l

2

No reply to this letter is required; however, should you have any questions

concerning this inspection, we will be pleased to discuss them with you.

Sincerely,

Y

a

Robert T. Carlson, Chief

Reactor Construction and Engineering

Support Branch

Enclosure:

Combined Office of Inspection and Enforcement Inspection Report

Numbers 50-352/80-15 and 50-353/80-13

l

cc w/ enc 1:

l

V. S. Boyer, Senior Vice President, Nuclear Power

l

l

l

!

.

__

_

. _. .- .