Responds to Re Decommissioning of Facility.Nrc Cannot Enter Into Formal Agreement Relinquishing Ultimate Regulatory Responsibility & Authority Over License
ML19350E320
Person / Time
Site: Wood River Junction
Issue date: 06/12/1981
From: Hendrie J
NRC COMMISSION (OCM)
To: Garrahy J
RHODE ISLAND, STATE OF
Shared Package
ML19350E321 List:
References
NUDOCS 8106170297
Download: ML19350E320 (2)


Text

SQ ESC J

'e UNITED STATES s

'h

[ "

,M NUCLEAR REGULATORY COMMISSION y

.I WASHINGTON, D. C. 20555

?

Y !

g June 12, 1981 g

yt lf, CHAl8WAN

~ f' % : p. g l 6 Lqg V

The Honorable J. Joseph Garrahy

~M Governor of Rhode Island Providence, Rhode Island 02903 4

/

y

Dear Governor:

Thank you for your letter dated May 7,1981 concerning the decommissioning of the Uniteu Nuclear Corporation (UNC) facility at Wood River Junction, Rhode Islard.

Regerding some of the concerns mentioned in your letter, I can assure you that it has been the Comission's intention that the UNC site (facilities and grounds including the underground aquifer) must be decontaminated to levels acceptable for unrestricted release. is a copy of Amendment No.

10 to NRC's License No. SNM-777 which reflects this intent. ' Enclosure 2 is a Corporate Coi iitment'from UNC Resources, Inc. to fund this decontamination effort. is Licence Amendment No.17 issued on May 12, 1981, which deleted the expiratiori date of the license and provided that the license shall remain in effect until action is taken by the Commission to terminate it.

Regarding the survey of the unrestricted area, the Commission has contracted with Dak Ridge Associated Universities (0RAU) to survey the area. A repre-sentative of ORAU has visited the site, as you noted, and present plans call for ORAU to survey the area late this summer. A copy of the survey plan will be submitted to you'r staff for review and coment upon receipt from ORAU.

With regard to your concern about shipments of waste to the Beatty, Nevada burial site, we understand this may be due to certain restrictions imposed by Nevada. We furtner understand that DOE is considering your request to accept this waste.

If this were done, it would obviate the need to send the material to Nevada.

Either way, all such wastes will have to be removed from the UNC site prior to termination of the license.

I am confident that our staffs an reach aCreement on mutually acceptable decontamination standards and timing for termination of the license. We are ccmmitted to considering Rhode Island's views and concerns.

We have assigned Mr. W. T. Crow of the NRC staff to work with your staff in this endeavor.

Mr. Crow has spoken with Mr. Malcolm Grant of your staff, and they have agreed on a meeting date. You should recognize, however, thst NRC cannot enter into any formal agreement that would relinquish NRC's ultimate reguiatory responsibility r,d authority over this license.

l y

l M106170297

o.

g.

.'m The Honorable.J. Joseph Garrahy.

. I l'ook forward to an early and satisfactory resolution of this mitter.

If

"'tdditional questions-arise, please let us know.

s S

\\x incerely,

\\\\

[

s y

Os\\spnM.Hendrie M

Enclosures:

1.

Amendment No.10 to NRC's

.L'icense No. SNM-777 2.

Corporate Comitment from 4

UNC Resources 3.

License Amendment No. 17 1

3 w

a d

i s

e 4

'g FEB 2 81980

~

FCle:RLS70-820

/-

SNM-777, Amendment No.10-United Nuclear Corporation 1

ATTH: Mr. C. E. Bowers, General Manager Fuel Recovery Operations One Narragansett Trail Wood River Junctior., Rhode Island 02894 h[.

Gentleman:

~

In accordance with your application dated May 18, 1979, as supplemented February S,1980, and pursuant to Title 10, code of Federal Regulations.

Part 70, Special Nuclear Material License No. SNf4-777 is hereby amended -

to include your decomissioning plan and financial comitment.

Accordingly, Condition No. 21 is replaced with the following:

Condition 21. At the end of plant life, the licensee shall decontar3nate the facilities and site in accordance with the i.Q general decomissioning plan submitted in the enclosure to the letter dated May 18,1979,-so that these facilities 'and grounds can be released to unrestricted use.

The financial comitment fromDUNC Resources, Inc., to assure that funds will be available for decomissionir.g. given in the letter dated February 5,1.980, is hersby incorporated as a condition of the

. li cense.

All otf>er conditions of this license shall verain the same.

FOR THE NUCLEAR REGULATORY COMMISSION

~

(Sened) R. G. Page R. G. Page, Acting Chief Uranium Fuel Licensing Branch Division of Fuel Cycle and Paterial Safety l

W P00R BRIGINAI.

E lc3 I7(903?

,/..

UnC RESOURCES UNO Crescen:Raza Fabs Churh, %rg rua 22o43

), ;, ;

7700 Leesourg Ne Te% phone 7c3/8217900

.;. 3 5 February 1980 i-

=

' acwe c wa rm U. S. Nuclear Regulatory Comission sw vce presc n:

Attn:

Robert L. Stevenson

.~

Cruf FearceiOfk:ar Uranium Fuel Fabrication Section Fuel Processing and Fabrication Branch

. ' ~.

Division of Fuel Cycle and Material Safety

' q.,

5~;

Subject:

Financial Surety for Deco:m:issioning Wood River Junction Plant License SNM-777

Reference:

1)

FCPF:RLS70-820

Dear Mr Stevenson:

In response to the request contained in your above referenced letter. UNC Resources Inc. comits to provide the fund when needed for decontamination and decomissioning of its United

~

Nuclear Corporation Wood River Juncti.on site.

~

4&.:.

5...

Sincerely, p.

-w

=

Fi' RCW:sfs 3;>p;T...

c Z-l s

,te we

- 0 l 5. ~.

c wg e oew" P00R ORIGINAI.

v y

E"Cl osure 3 NAY 1 2 1981

()Y, FCUP:RLS -

l

~

70-820

~

Sh777 Amendment No.17 k:

United Nuclear Corporation

'~

ATTN:

Mr. Glenn O. Amy, General Manager UNC Recovery Sys*m s One Narragansett Trail Wood P.tver Junction, Rhode Island *02894 Gentlemen:

~{x;e.

In accordance with a recent teJephone conversi. tion, between yo_ur Mr. Robert Gregg and W. T. Crow of my staff and pursuant to Title 10, Code of Federal Regulations, Part 70, Special Nuclear Material License No. SNM-777 is here-by amended to delete Item 4 (Expiration date:

June 30, 1981) of this license.

Accordingly, SNM-777 shall remain in effect until action is t: ken by the Coennission to terminate it and you are so notified in writing.

All other conditions of your license shall remain the same.

~

FOR THE NUCLEAR REGULATORY COMMISSION Original Signed by s

R. G. Page, Chief Uranium Fuel Licensing Branch Divis',on of Fuel Cycle and Paterial Safety t