|
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARIR 05000412/19990071999-10-21021 October 1999 Refers to Special Team Insp 50-412/99-07 Conducted from 990720-29 & Forwards Nov.Two Violations Identified.First Violation Involved Failure to Implement C/A to Prevent Biofouling of Service Water System ML20217M1591999-10-19019 October 1999 Forwards NRC Rept Number 17, Requal Tracking Rept from Operator Licensing Tracking Sys.Rept Was Used by NRC to Schedule Requalification Exam for Operators & Record Requal Pass Dates L-99-143, Informs That Subsequent Review of Approval Ltrs & SE for Relief Requests 1TYP-2-B5.40-1 (Rev 0),BV1-RV-AUG (Rev 1), BV2-RV-AUG (Rev 1),BV3-IWA-1 (Rev 1) & BV3-IWA-2 (Rev 1) Identified Erroneous Statements Which Dl Wishes to Correct1999-10-11011 October 1999 Informs That Subsequent Review of Approval Ltrs & SE for Relief Requests 1TYP-2-B5.40-1 (Rev 0),BV1-RV-AUG (Rev 1), BV2-RV-AUG (Rev 1),BV3-IWA-1 (Rev 1) & BV3-IWA-2 (Rev 1) Identified Erroneous Statements Which Dl Wishes to Correct L-99-152, Submits Relief Request BV3-N-533-1,rev 0,requesting Use of ASME Approved Code Case N-553-1, Alternative Requirements for VT-2 Visual Examination of Class 1,2 & 3 Insulated Pressure Retaining Bolted Connections1999-10-11011 October 1999 Submits Relief Request BV3-N-533-1,rev 0,requesting Use of ASME Approved Code Case N-553-1, Alternative Requirements for VT-2 Visual Examination of Class 1,2 & 3 Insulated Pressure Retaining Bolted Connections ML20217C6741999-10-0808 October 1999 Forwards RAI Re Licensee 970128 Response to GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions, . Response Requested within 60 Days of Receipt of Ltr L-99-151, Responds to NRC Re Violations Noted in Insp Rept 50-412/99-07.Corrective Actions:Condition Repts Were Written for Listed Issues So That Repts Could Be Addressed Using BVPS Corrective Action Program1999-10-0707 October 1999 Responds to NRC Re Violations Noted in Insp Rept 50-412/99-07.Corrective Actions:Condition Repts Were Written for Listed Issues So That Repts Could Be Addressed Using BVPS Corrective Action Program ML20217E0301999-10-0707 October 1999 Forwards Insp Repts 50-334/99-06 & 50-412/99-06 on 990809-13 & 990823-27.Violation Noted Involving Failure to Correctly Translate Design Change Re Pertinent Operating Logs & Plant Equipment Labeling ML20212M2661999-09-30030 September 1999 Forwards Order Approving Transfer of Licenses for Beaver Valley from Dlc to Pennsylvania Power Co & Approving Conforming Amends in Response to 990505 Application ML20212K8071999-09-30030 September 1999 Informs That on 990916,NRC Staff Completed mid-cycle Plant Performance Review (PPR) of Facility.Staff Conducted Reviews of All Operating NPPs to Integrate Performance Info & to Plan for Insp Activities at Facility ML20216J9621999-09-30030 September 1999 Forwards Insp Repts 50-334/99-05 & 50-412/99-05 on 990725-0904.Two Violations Noted & Being Treated as Ncvs.One Violation Re Failure to Follow Operation Manual Procedure Associated with Configuration Control Identified L-99-149, Informs NRC That Items Identified in 990629 Response to GL 98-01 Have Been Completed.Attached Table Submitted with Has Been Updated to Reflect Completion1999-09-28028 September 1999 Informs NRC That Items Identified in 990629 Response to GL 98-01 Have Been Completed.Attached Table Submitted with Has Been Updated to Reflect Completion L-99-148, Notifies NRC of License Withdrawal of M Linch,License SOP-11478 IAW 10CFR50.74.M Linch Resigned from Employment at Bvps,Effective 9908171999-09-24024 September 1999 Notifies NRC of License Withdrawal of M Linch,License SOP-11478 IAW 10CFR50.74.M Linch Resigned from Employment at Bvps,Effective 990817 ML20212G0601999-09-23023 September 1999 Forwards Answer of Duquesne Light Co to Petition to Waive Time Limits & Suppl Comments of Local 29, Intl Brotherhood of Electrical Workers.Copies of Answer Have Been Served to Parties & Petitioner by e-mail or Facsimile ML20212C5521999-09-21021 September 1999 Forwards for Filing,Answer to Firstenergy Nuclear Operating Co & Pennsylvania Power Co in Opposition to Petition to Waive Time Limits & Suppl Comments of Local 29 Intl Brotherhood of Electrical Workers L-99-144, Forwards NRC Form 536 Which Addresses Util Proposed Operator Licensing Exam Schedule,In Response to Administrative Ltr 99-031999-09-20020 September 1999 Forwards NRC Form 536 Which Addresses Util Proposed Operator Licensing Exam Schedule,In Response to Administrative Ltr 99-03 ML20212B3291999-09-16016 September 1999 Forwards for Filing,Petition to Waive Time Limits in 10CFR2.1305 & Supplemental Comments of Local 29,Intl Brotherhood of Electrical Workers Re Beaver Valley Power Station,Units 1 & 2 L-99-134, Provides Addl Info to Support 990617 LAR 127,proposing Mods to Heatup,Cooldown & Overpressure Protection Curves.Info Is Provided to Formally Docket Info Discussed During 990820 Telcon with NRC1999-09-15015 September 1999 Provides Addl Info to Support 990617 LAR 127,proposing Mods to Heatup,Cooldown & Overpressure Protection Curves.Info Is Provided to Formally Docket Info Discussed During 990820 Telcon with NRC ML20211Q3431999-09-0808 September 1999 Informs That During 990903 Telcon Between L Briggs & T Kuhar,Arrangements Were Made for NRC to Inspect Licensed Operator Requalification Program at Plant,Unit 1.Insp Planned for Wk of 991115 ML20211Q5601999-09-0707 September 1999 Forwards Insp Rept 50-412/99-07 on 990720-29.Three Apparent Violations Noted & Being Considered for Escalated Ea. Violations Involve Failure to Implement C/As to Prevent bio- Fouling of Svc Water Sys L-99-138, Forwards Rev 37 to Issue 4 for BVPS Physical Security Plan (PSP) (Base Plan,Safeguards Contingency Plan & Training & Qualification Plan).Changes to Plan Are Listed.Encls Withheld Per 10CFR2.790(d)1999-09-0303 September 1999 Forwards Rev 37 to Issue 4 for BVPS Physical Security Plan (PSP) (Base Plan,Safeguards Contingency Plan & Training & Qualification Plan).Changes to Plan Are Listed.Encls Withheld Per 10CFR2.790(d) L-99-136, Forwards Data Point Library (Dpl) Changes,Iaw Provisions of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6, Administrative Implementation Requirements. Ten Listed Dpls Have Specific Setpoint Values Removed,Per Unit 2 Dpls1999-09-0202 September 1999 Forwards Data Point Library (Dpl) Changes,Iaw Provisions of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6, Administrative Implementation Requirements. Ten Listed Dpls Have Specific Setpoint Values Removed,Per Unit 2 Dpls L-99-098, Forwards Proposed Changes to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Change Would Reduce Operations QA Program Description Commitments by Limiting Required Onsite Safety Committee Reviews of Mods1999-09-0202 September 1999 Forwards Proposed Changes to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Change Would Reduce Operations QA Program Description Commitments by Limiting Required Onsite Safety Committee Reviews of Mods L-99-137, Forwards Issue 3,rev 3 to Bvps,Unit 1 Inservice Testing Program for Pumps & Valves. Encl 1 Provides Summary of IST Program Changes Which Have Been Incorporated Into Issue 3, Rev 31999-08-31031 August 1999 Forwards Issue 3,rev 3 to Bvps,Unit 1 Inservice Testing Program for Pumps & Valves. Encl 1 Provides Summary of IST Program Changes Which Have Been Incorporated Into Issue 3, Rev 3 L-99-022, Forwards Issue 2,Rev 1 to Bvps,Unit 2 Inservice Testing (IST) Program for Pumps & Valves. Summary of Changes,Encl1999-08-31031 August 1999 Forwards Issue 2,Rev 1 to Bvps,Unit 2 Inservice Testing (IST) Program for Pumps & Valves. Summary of Changes,Encl L-99-012, Forwards Proposed Change to Bvps,Units 1 & 2,operations QA Program Description,Per 10CFR50.54(a)(3)(ii),including Description of Proposed Change,Reason for Change & Basis for Concluding Revised Program Satisfy 10CFR50,App B1999-08-30030 August 1999 Forwards Proposed Change to Bvps,Units 1 & 2,operations QA Program Description,Per 10CFR50.54(a)(3)(ii),including Description of Proposed Change,Reason for Change & Basis for Concluding Revised Program Satisfy 10CFR50,App B L-99-037, Forwards Proposed Change to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Attachment 1 Further Describes Proposed Change & Identifies Reason for Change1999-08-30030 August 1999 Forwards Proposed Change to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Attachment 1 Further Describes Proposed Change & Identifies Reason for Change L-99-132, Forwards fitness-for-duty Program Six Month Rept for 990101-990630 for Bvps,Units 1 & 21999-08-26026 August 1999 Forwards fitness-for-duty Program Six Month Rept for 990101-990630 for Bvps,Units 1 & 2 05000412/LER-1999-007, Forwards LER 99-007-00, Forced Shutdown Due to Inoperable EDG, Per 10CFR50.73(a)(2)(i).Rept Is Delayed Due to Util Needing Addl Three Days to Address Event Issues on Reportability & Provide Addl Safety Implications Info1999-08-19019 August 1999 Forwards LER 99-007-00, Forced Shutdown Due to Inoperable EDG, Per 10CFR50.73(a)(2)(i).Rept Is Delayed Due to Util Needing Addl Three Days to Address Event Issues on Reportability & Provide Addl Safety Implications Info ML20211A5111999-08-18018 August 1999 Forwards Insp Repts 50-334/99-04 & 50-412/99-04 on 990613- 990724.One Violation Noted & Treated as Non-Cited Violation Involved Failure to Maintain Containment Equipment Hatch Closed During Fuel Movement L-99-127, Provides Response to NRC Ltr Requesting Review & Comment of NRC Reactor Vessel Structural Integrity Database by 990901.Inconsistencies Noted in Way Data Characterizes Condition of Reactor Vessel1999-08-17017 August 1999 Provides Response to NRC Ltr Requesting Review & Comment of NRC Reactor Vessel Structural Integrity Database by 990901.Inconsistencies Noted in Way Data Characterizes Condition of Reactor Vessel L-99-124, Requests Withdrawal of Editorial Changes That Do Not Pertain to Transfer of Operating Authority or Plant Ownership That Are Proposed in LARs 269 & 144.Revised mark-up License Pages Reflecting Changes,Attached1999-07-30030 July 1999 Requests Withdrawal of Editorial Changes That Do Not Pertain to Transfer of Operating Authority or Plant Ownership That Are Proposed in LARs 269 & 144.Revised mark-up License Pages Reflecting Changes,Attached L-99-121, Submits Data Point Library (Dpl) Changes,Iaw Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,rev 1,Section 3.6, Administrative Implementation Reqiurements1999-07-28028 July 1999 Submits Data Point Library (Dpl) Changes,Iaw Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,rev 1,Section 3.6, Administrative Implementation Reqiurements L-99-118, Forwards Response to NRC AL 99-02,request for Info Re Estimate of Number of New Licensing Actions Expected to Be Submitted in Fy 2000 & 20011999-07-25025 July 1999 Forwards Response to NRC AL 99-02,request for Info Re Estimate of Number of New Licensing Actions Expected to Be Submitted in Fy 2000 & 2001 L-99-120, Forwards Annual Rept of Facility Changes,Tests & Experiments for BVPS Unit 1,IAW 10CFR50.59.Rept Provides Brief Description of Each Facility & Procedure Change & Summary of Safety Evaluations1999-07-22022 July 1999 Forwards Annual Rept of Facility Changes,Tests & Experiments for BVPS Unit 1,IAW 10CFR50.59.Rept Provides Brief Description of Each Facility & Procedure Change & Summary of Safety Evaluations L-99-119, Forwards Rev 17 to UFSAR for Beaver Power Station,Unit 1. Submittal Reflects Changes to Facility & Procedures as Described in UFSAR That Were Completed During Annual Reporting Period Endinig 9901221999-07-20020 July 1999 Forwards Rev 17 to UFSAR for Beaver Power Station,Unit 1. Submittal Reflects Changes to Facility & Procedures as Described in UFSAR That Were Completed During Annual Reporting Period Endinig 990122 L-99-113, Forwards Final,Typed TS Pages for LARs 262 & 135,previously Submitted with Editorial Changes Identified by1999-07-15015 July 1999 Forwards Final,Typed TS Pages for LARs 262 & 135,previously Submitted with Editorial Changes Identified by L-99-111, Forwards Revised Final Typed Pages for LARs 109 & 115, Previously Submitted by 990615 & 28 Ltrs.Revised Pages Replace Those Previously Provided for LARs 109 & 115.With Summary of Editorial Changes1999-07-15015 July 1999 Forwards Revised Final Typed Pages for LARs 109 & 115, Previously Submitted by 990615 & 28 Ltrs.Revised Pages Replace Those Previously Provided for LARs 109 & 115.With Summary of Editorial Changes L-99-112, Responds to NRC Questions Made During 990518 Meeting with Util Re LARs 220 & 88,for Bvps,Units 1 & 2.Copy of Ltr DLC-99-743,which Is non-proprietary Version of DLC-96-310 & Westinghouse Technical Bulletin ESBU-TB-96-07-R0 Also Encl1999-07-14014 July 1999 Responds to NRC Questions Made During 990518 Meeting with Util Re LARs 220 & 88,for Bvps,Units 1 & 2.Copy of Ltr DLC-99-743,which Is non-proprietary Version of DLC-96-310 & Westinghouse Technical Bulletin ESBU-TB-96-07-R0 Also Encl L-99-110, Forwards Changes to ERDS for Unit 1,IAW Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.61999-07-14014 July 1999 Forwards Changes to ERDS for Unit 1,IAW Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6 ML20209G5701999-07-12012 July 1999 Discusses Closure of TACs MA0525 & MA0526 Re Response to RAI Concerning GL 92-0,Rev 1,Suppl 1, Rv Structural Integrity. Info in Rvid Revised & Released as Ver 2 as Result of Review of Response ML20207H6621999-07-0808 July 1999 Forwards RAI Re Util 981112 Response to IPEEE Evaluations for Plant,Units 1 & 2.RAI Was Discussed During 990628 Telcon in Order to Ensure Clear Consistent Understanding by All Parties of Info Needed L-99-105, Forwards Response to NRC 990420 RAI Re Previous Responses to GL 95-07, Pressure Locking & Thermal Binding of SR Power-Operated Gate Valves1999-07-0808 July 1999 Forwards Response to NRC 990420 RAI Re Previous Responses to GL 95-07, Pressure Locking & Thermal Binding of SR Power-Operated Gate Valves ML20209D8191999-07-0707 July 1999 Forwards Insp Repts 50-334/99-03 & 50-412/99-03 on 990502- 0612.No Violations Noted.Program for Maintaining Occupational Exposures as Low as Reasonably Achievable (ALARA) & for Training Personnel,Generally Effective L-99-109, Forwards Inservice Insp Ninety-Day Rept Bvps,Unit 2 Outage 7,Year 1999, IAW ASME Boiler & Pressure Vessel Code,Section Xi,Article IWA-62301999-07-0707 July 1999 Forwards Inservice Insp Ninety-Day Rept Bvps,Unit 2 Outage 7,Year 1999, IAW ASME Boiler & Pressure Vessel Code,Section Xi,Article IWA-6230 L-99-108, Requests Withdrawal of Change Proposed for TS Bases Page B 3/4 2-2 from LARs 1A-262 & 2A-135,originally Submitted by Licensee to NRC1999-07-0707 July 1999 Requests Withdrawal of Change Proposed for TS Bases Page B 3/4 2-2 from LARs 1A-262 & 2A-135,originally Submitted by Licensee to NRC L-99-104, Responds to GL 98-01,Suppl 1, Y2K Readiness at Nuclear Power Plants. Disclosure Rept Encl1999-06-29029 June 1999 Responds to GL 98-01,Suppl 1, Y2K Readiness at Nuclear Power Plants. Disclosure Rept Encl L-99-093, Provides Response to RAI on Proposed Change to Operations QA Program Description.Attachment 2 Provides Revised Markup for Proposed Changes to Affected UFSAR Section 17.2.51999-06-25025 June 1999 Provides Response to RAI on Proposed Change to Operations QA Program Description.Attachment 2 Provides Revised Markup for Proposed Changes to Affected UFSAR Section 17.2.5 L-99-102, Forwards Typed,Final TS Pages for LARs 259 & 131.Summary of Description of Plant Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages,Encl1999-06-22022 June 1999 Forwards Typed,Final TS Pages for LARs 259 & 131.Summary of Description of Plant Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages,Encl L-99-101, Submits Response to NRC Oral RAI Concerning Qualifications for Senior Nuclear Executive Ref in 10CFR50.80 Submittal1999-06-22022 June 1999 Submits Response to NRC Oral RAI Concerning Qualifications for Senior Nuclear Executive Ref in 10CFR50.80 Submittal L-99-062, Forwards Final TS Pages for LARs 262 & 135,including Summary Description of Plants Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages1999-06-17017 June 1999 Forwards Final TS Pages for LARs 262 & 135,including Summary Description of Plants Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages 1999-09-08
[Table view] Category:INCOMING CORRESPONDENCE
MONTHYEARL-99-152, Submits Relief Request BV3-N-533-1,rev 0,requesting Use of ASME Approved Code Case N-553-1, Alternative Requirements for VT-2 Visual Examination of Class 1,2 & 3 Insulated Pressure Retaining Bolted Connections1999-10-11011 October 1999 Submits Relief Request BV3-N-533-1,rev 0,requesting Use of ASME Approved Code Case N-553-1, Alternative Requirements for VT-2 Visual Examination of Class 1,2 & 3 Insulated Pressure Retaining Bolted Connections L-99-143, Informs That Subsequent Review of Approval Ltrs & SE for Relief Requests 1TYP-2-B5.40-1 (Rev 0),BV1-RV-AUG (Rev 1), BV2-RV-AUG (Rev 1),BV3-IWA-1 (Rev 1) & BV3-IWA-2 (Rev 1) Identified Erroneous Statements Which Dl Wishes to Correct1999-10-11011 October 1999 Informs That Subsequent Review of Approval Ltrs & SE for Relief Requests 1TYP-2-B5.40-1 (Rev 0),BV1-RV-AUG (Rev 1), BV2-RV-AUG (Rev 1),BV3-IWA-1 (Rev 1) & BV3-IWA-2 (Rev 1) Identified Erroneous Statements Which Dl Wishes to Correct L-99-151, Responds to NRC Re Violations Noted in Insp Rept 50-412/99-07.Corrective Actions:Condition Repts Were Written for Listed Issues So That Repts Could Be Addressed Using BVPS Corrective Action Program1999-10-0707 October 1999 Responds to NRC Re Violations Noted in Insp Rept 50-412/99-07.Corrective Actions:Condition Repts Were Written for Listed Issues So That Repts Could Be Addressed Using BVPS Corrective Action Program L-99-149, Informs NRC That Items Identified in 990629 Response to GL 98-01 Have Been Completed.Attached Table Submitted with Has Been Updated to Reflect Completion1999-09-28028 September 1999 Informs NRC That Items Identified in 990629 Response to GL 98-01 Have Been Completed.Attached Table Submitted with Has Been Updated to Reflect Completion L-99-148, Notifies NRC of License Withdrawal of M Linch,License SOP-11478 IAW 10CFR50.74.M Linch Resigned from Employment at Bvps,Effective 9908171999-09-24024 September 1999 Notifies NRC of License Withdrawal of M Linch,License SOP-11478 IAW 10CFR50.74.M Linch Resigned from Employment at Bvps,Effective 990817 ML20212G0601999-09-23023 September 1999 Forwards Answer of Duquesne Light Co to Petition to Waive Time Limits & Suppl Comments of Local 29, Intl Brotherhood of Electrical Workers.Copies of Answer Have Been Served to Parties & Petitioner by e-mail or Facsimile ML20212C5521999-09-21021 September 1999 Forwards for Filing,Answer to Firstenergy Nuclear Operating Co & Pennsylvania Power Co in Opposition to Petition to Waive Time Limits & Suppl Comments of Local 29 Intl Brotherhood of Electrical Workers L-99-144, Forwards NRC Form 536 Which Addresses Util Proposed Operator Licensing Exam Schedule,In Response to Administrative Ltr 99-031999-09-20020 September 1999 Forwards NRC Form 536 Which Addresses Util Proposed Operator Licensing Exam Schedule,In Response to Administrative Ltr 99-03 ML20212B3291999-09-16016 September 1999 Forwards for Filing,Petition to Waive Time Limits in 10CFR2.1305 & Supplemental Comments of Local 29,Intl Brotherhood of Electrical Workers Re Beaver Valley Power Station,Units 1 & 2 L-99-134, Provides Addl Info to Support 990617 LAR 127,proposing Mods to Heatup,Cooldown & Overpressure Protection Curves.Info Is Provided to Formally Docket Info Discussed During 990820 Telcon with NRC1999-09-15015 September 1999 Provides Addl Info to Support 990617 LAR 127,proposing Mods to Heatup,Cooldown & Overpressure Protection Curves.Info Is Provided to Formally Docket Info Discussed During 990820 Telcon with NRC L-99-138, Forwards Rev 37 to Issue 4 for BVPS Physical Security Plan (PSP) (Base Plan,Safeguards Contingency Plan & Training & Qualification Plan).Changes to Plan Are Listed.Encls Withheld Per 10CFR2.790(d)1999-09-0303 September 1999 Forwards Rev 37 to Issue 4 for BVPS Physical Security Plan (PSP) (Base Plan,Safeguards Contingency Plan & Training & Qualification Plan).Changes to Plan Are Listed.Encls Withheld Per 10CFR2.790(d) L-99-136, Forwards Data Point Library (Dpl) Changes,Iaw Provisions of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6, Administrative Implementation Requirements. Ten Listed Dpls Have Specific Setpoint Values Removed,Per Unit 2 Dpls1999-09-0202 September 1999 Forwards Data Point Library (Dpl) Changes,Iaw Provisions of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6, Administrative Implementation Requirements. Ten Listed Dpls Have Specific Setpoint Values Removed,Per Unit 2 Dpls L-99-098, Forwards Proposed Changes to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Change Would Reduce Operations QA Program Description Commitments by Limiting Required Onsite Safety Committee Reviews of Mods1999-09-0202 September 1999 Forwards Proposed Changes to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Change Would Reduce Operations QA Program Description Commitments by Limiting Required Onsite Safety Committee Reviews of Mods L-99-137, Forwards Issue 3,rev 3 to Bvps,Unit 1 Inservice Testing Program for Pumps & Valves. Encl 1 Provides Summary of IST Program Changes Which Have Been Incorporated Into Issue 3, Rev 31999-08-31031 August 1999 Forwards Issue 3,rev 3 to Bvps,Unit 1 Inservice Testing Program for Pumps & Valves. Encl 1 Provides Summary of IST Program Changes Which Have Been Incorporated Into Issue 3, Rev 3 L-99-022, Forwards Issue 2,Rev 1 to Bvps,Unit 2 Inservice Testing (IST) Program for Pumps & Valves. Summary of Changes,Encl1999-08-31031 August 1999 Forwards Issue 2,Rev 1 to Bvps,Unit 2 Inservice Testing (IST) Program for Pumps & Valves. Summary of Changes,Encl L-99-037, Forwards Proposed Change to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Attachment 1 Further Describes Proposed Change & Identifies Reason for Change1999-08-30030 August 1999 Forwards Proposed Change to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Attachment 1 Further Describes Proposed Change & Identifies Reason for Change L-99-012, Forwards Proposed Change to Bvps,Units 1 & 2,operations QA Program Description,Per 10CFR50.54(a)(3)(ii),including Description of Proposed Change,Reason for Change & Basis for Concluding Revised Program Satisfy 10CFR50,App B1999-08-30030 August 1999 Forwards Proposed Change to Bvps,Units 1 & 2,operations QA Program Description,Per 10CFR50.54(a)(3)(ii),including Description of Proposed Change,Reason for Change & Basis for Concluding Revised Program Satisfy 10CFR50,App B L-99-132, Forwards fitness-for-duty Program Six Month Rept for 990101-990630 for Bvps,Units 1 & 21999-08-26026 August 1999 Forwards fitness-for-duty Program Six Month Rept for 990101-990630 for Bvps,Units 1 & 2 05000412/LER-1999-007, Forwards LER 99-007-00, Forced Shutdown Due to Inoperable EDG, Per 10CFR50.73(a)(2)(i).Rept Is Delayed Due to Util Needing Addl Three Days to Address Event Issues on Reportability & Provide Addl Safety Implications Info1999-08-19019 August 1999 Forwards LER 99-007-00, Forced Shutdown Due to Inoperable EDG, Per 10CFR50.73(a)(2)(i).Rept Is Delayed Due to Util Needing Addl Three Days to Address Event Issues on Reportability & Provide Addl Safety Implications Info L-99-127, Provides Response to NRC Ltr Requesting Review & Comment of NRC Reactor Vessel Structural Integrity Database by 990901.Inconsistencies Noted in Way Data Characterizes Condition of Reactor Vessel1999-08-17017 August 1999 Provides Response to NRC Ltr Requesting Review & Comment of NRC Reactor Vessel Structural Integrity Database by 990901.Inconsistencies Noted in Way Data Characterizes Condition of Reactor Vessel L-99-124, Requests Withdrawal of Editorial Changes That Do Not Pertain to Transfer of Operating Authority or Plant Ownership That Are Proposed in LARs 269 & 144.Revised mark-up License Pages Reflecting Changes,Attached1999-07-30030 July 1999 Requests Withdrawal of Editorial Changes That Do Not Pertain to Transfer of Operating Authority or Plant Ownership That Are Proposed in LARs 269 & 144.Revised mark-up License Pages Reflecting Changes,Attached L-99-121, Submits Data Point Library (Dpl) Changes,Iaw Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,rev 1,Section 3.6, Administrative Implementation Reqiurements1999-07-28028 July 1999 Submits Data Point Library (Dpl) Changes,Iaw Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,rev 1,Section 3.6, Administrative Implementation Reqiurements L-99-118, Forwards Response to NRC AL 99-02,request for Info Re Estimate of Number of New Licensing Actions Expected to Be Submitted in Fy 2000 & 20011999-07-25025 July 1999 Forwards Response to NRC AL 99-02,request for Info Re Estimate of Number of New Licensing Actions Expected to Be Submitted in Fy 2000 & 2001 L-99-120, Forwards Annual Rept of Facility Changes,Tests & Experiments for BVPS Unit 1,IAW 10CFR50.59.Rept Provides Brief Description of Each Facility & Procedure Change & Summary of Safety Evaluations1999-07-22022 July 1999 Forwards Annual Rept of Facility Changes,Tests & Experiments for BVPS Unit 1,IAW 10CFR50.59.Rept Provides Brief Description of Each Facility & Procedure Change & Summary of Safety Evaluations L-99-119, Forwards Rev 17 to UFSAR for Beaver Power Station,Unit 1. Submittal Reflects Changes to Facility & Procedures as Described in UFSAR That Were Completed During Annual Reporting Period Endinig 9901221999-07-20020 July 1999 Forwards Rev 17 to UFSAR for Beaver Power Station,Unit 1. Submittal Reflects Changes to Facility & Procedures as Described in UFSAR That Were Completed During Annual Reporting Period Endinig 990122 L-99-111, Forwards Revised Final Typed Pages for LARs 109 & 115, Previously Submitted by 990615 & 28 Ltrs.Revised Pages Replace Those Previously Provided for LARs 109 & 115.With Summary of Editorial Changes1999-07-15015 July 1999 Forwards Revised Final Typed Pages for LARs 109 & 115, Previously Submitted by 990615 & 28 Ltrs.Revised Pages Replace Those Previously Provided for LARs 109 & 115.With Summary of Editorial Changes L-99-113, Forwards Final,Typed TS Pages for LARs 262 & 135,previously Submitted with Editorial Changes Identified by1999-07-15015 July 1999 Forwards Final,Typed TS Pages for LARs 262 & 135,previously Submitted with Editorial Changes Identified by L-99-112, Responds to NRC Questions Made During 990518 Meeting with Util Re LARs 220 & 88,for Bvps,Units 1 & 2.Copy of Ltr DLC-99-743,which Is non-proprietary Version of DLC-96-310 & Westinghouse Technical Bulletin ESBU-TB-96-07-R0 Also Encl1999-07-14014 July 1999 Responds to NRC Questions Made During 990518 Meeting with Util Re LARs 220 & 88,for Bvps,Units 1 & 2.Copy of Ltr DLC-99-743,which Is non-proprietary Version of DLC-96-310 & Westinghouse Technical Bulletin ESBU-TB-96-07-R0 Also Encl L-99-110, Forwards Changes to ERDS for Unit 1,IAW Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.61999-07-14014 July 1999 Forwards Changes to ERDS for Unit 1,IAW Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6 L-99-105, Forwards Response to NRC 990420 RAI Re Previous Responses to GL 95-07, Pressure Locking & Thermal Binding of SR Power-Operated Gate Valves1999-07-0808 July 1999 Forwards Response to NRC 990420 RAI Re Previous Responses to GL 95-07, Pressure Locking & Thermal Binding of SR Power-Operated Gate Valves L-99-108, Requests Withdrawal of Change Proposed for TS Bases Page B 3/4 2-2 from LARs 1A-262 & 2A-135,originally Submitted by Licensee to NRC1999-07-0707 July 1999 Requests Withdrawal of Change Proposed for TS Bases Page B 3/4 2-2 from LARs 1A-262 & 2A-135,originally Submitted by Licensee to NRC L-99-109, Forwards Inservice Insp Ninety-Day Rept Bvps,Unit 2 Outage 7,Year 1999, IAW ASME Boiler & Pressure Vessel Code,Section Xi,Article IWA-62301999-07-0707 July 1999 Forwards Inservice Insp Ninety-Day Rept Bvps,Unit 2 Outage 7,Year 1999, IAW ASME Boiler & Pressure Vessel Code,Section Xi,Article IWA-6230 L-99-104, Responds to GL 98-01,Suppl 1, Y2K Readiness at Nuclear Power Plants. Disclosure Rept Encl1999-06-29029 June 1999 Responds to GL 98-01,Suppl 1, Y2K Readiness at Nuclear Power Plants. Disclosure Rept Encl L-99-093, Provides Response to RAI on Proposed Change to Operations QA Program Description.Attachment 2 Provides Revised Markup for Proposed Changes to Affected UFSAR Section 17.2.51999-06-25025 June 1999 Provides Response to RAI on Proposed Change to Operations QA Program Description.Attachment 2 Provides Revised Markup for Proposed Changes to Affected UFSAR Section 17.2.5 L-99-102, Forwards Typed,Final TS Pages for LARs 259 & 131.Summary of Description of Plant Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages,Encl1999-06-22022 June 1999 Forwards Typed,Final TS Pages for LARs 259 & 131.Summary of Description of Plant Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages,Encl L-99-101, Submits Response to NRC Oral RAI Concerning Qualifications for Senior Nuclear Executive Ref in 10CFR50.80 Submittal1999-06-22022 June 1999 Submits Response to NRC Oral RAI Concerning Qualifications for Senior Nuclear Executive Ref in 10CFR50.80 Submittal L-99-062, Forwards Final TS Pages for LARs 262 & 135,including Summary Description of Plants Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages1999-06-17017 June 1999 Forwards Final TS Pages for LARs 262 & 135,including Summary Description of Plants Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages ML20196A6601999-06-16016 June 1999 Forwards Master Decommissioning Trust Agreements Revised After 1990 for Ohio Edison Co,Cleveland Electric Illuminating Co,Toledo Edison Co & Pennsylvania Power Co Re Bvnps,Units 1 & 2,DBNPS,Unit 1 & Perry Unit 1 ML20195H4651999-06-16016 June 1999 Forwards for Filing Answer of Firstenergy Corp in Opposition to Petition for Leave to Intervene of Local 29, Intl Brotherhood of Electrical Workers. Copies of Answer Have Been Served Upon Parties & Petitioner by e-mail ML20195J5221999-06-16016 June 1999 Forwards Answer of Duquesne Light Co to Petition to Intervene of Local 29,International Brotherhood of Electrical Workers in Listed Matter.With Certificate of Svc L-99-100, Forwards Typed,Final TS Pages for LAR 109 Re Rcs.Summary Description of Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages Is Provided in Attachment B-1091999-06-15015 June 1999 Forwards Typed,Final TS Pages for LAR 109 Re Rcs.Summary Description of Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages Is Provided in Attachment B-109 L-99-095, Provides Addl Info to Support LARs 262 & 135,in Response to NRC 990527 Verbal Request.Info Describes Performance of Unit 1 Rod Position Indication Sys & Provides Some Background Info Re Normal Operation of Sys1999-06-15015 June 1999 Provides Addl Info to Support LARs 262 & 135,in Response to NRC 990527 Verbal Request.Info Describes Performance of Unit 1 Rod Position Indication Sys & Provides Some Background Info Re Normal Operation of Sys L-99-099, Requests Partial Withdrawal of LAR 120,which Requested Review of USQ Due to Increased Calculated Doses for Locked Rotor Event & Use of Unapproved Methodology for Evaluating Small Break LOCA Doses Involving W Natl Safety Advisory Ltr1999-06-14014 June 1999 Requests Partial Withdrawal of LAR 120,which Requested Review of USQ Due to Increased Calculated Doses for Locked Rotor Event & Use of Unapproved Methodology for Evaluating Small Break LOCA Doses Involving W Natl Safety Advisory Ltr ML20195H3731999-06-0303 June 1999 Forwards Petition to Intervene of Local 29,Intl Brotherhood of Electrical Workers in Matter of Firstenergy Nuclear Operating Co,For Filing L-99-090, Forwards Summary Review Completed to Verify Adequacy of Design Basis Accident Thermal Overpressure Protection for BVPS Unit 2 Containment Penetrations,Per Request1999-06-0202 June 1999 Forwards Summary Review Completed to Verify Adequacy of Design Basis Accident Thermal Overpressure Protection for BVPS Unit 2 Containment Penetrations,Per Request L-99-086, Forwards Bvps,Unit 2 SG Exam Rept for Aug 1998.Rept Provided to Document Results of SG Eddy Current Exams Performed in Aug 1998.Summary of Insps Provided in Encl 11999-05-28028 May 1999 Forwards Bvps,Unit 2 SG Exam Rept for Aug 1998.Rept Provided to Document Results of SG Eddy Current Exams Performed in Aug 1998.Summary of Insps Provided in Encl 1 L-99-089, Forwards Annual Financial Repts,Including Certified Financial Statements,Of Dqe,Firstenergy Corp,Ohio Edison Co,Pennsylvania Power Co,Cleveland Electric Illuminating Co & Toledo Edison Co,Iaw 10CFR50.71(b)1999-05-28028 May 1999 Forwards Annual Financial Repts,Including Certified Financial Statements,Of Dqe,Firstenergy Corp,Ohio Edison Co,Pennsylvania Power Co,Cleveland Electric Illuminating Co & Toledo Edison Co,Iaw 10CFR50.71(b) L-99-084, Forwards Revised marked-up TS & UFSAR Pages to 990303 LARs 259 & 131 Which Revised Qualifications for Operations Mgt & Incorporated Generic Position Titles in Ts.Encl Pages Incorporate NRC Requested Changes,Per Recent Telcon1999-05-27027 May 1999 Forwards Revised marked-up TS & UFSAR Pages to 990303 LARs 259 & 131 Which Revised Qualifications for Operations Mgt & Incorporated Generic Position Titles in Ts.Encl Pages Incorporate NRC Requested Changes,Per Recent Telcon L-99-082, Dockets Licensee Plan for Bvps,Unit 1,safety-related Small Bore Piping Evaluation Project Discussed in NRC 990311 Public Meeting at BVPS1999-05-17017 May 1999 Dockets Licensee Plan for Bvps,Unit 1,safety-related Small Bore Piping Evaluation Project Discussed in NRC 990311 Public Meeting at BVPS L-99-071, Notifies of License Withdrawal for J Scott,License SOP-11481,due to Resignation from Employment at BVPS1999-05-12012 May 1999 Notifies of License Withdrawal for J Scott,License SOP-11481,due to Resignation from Employment at BVPS 1999-09-03
[Table view] Category:VENDOR/MANUFACTURER TO NRC
MONTHYEARML20059E0601990-08-0707 August 1990 Requests That Proprietary Suppl 3 to WCAP-12093, Evaluation of Pressurizer Surge Line Transients Exceeding 320 F for Beaver Valley Unit 2, Be Withheld Per 10CFR2.790(b)(4) ML18094B4141990-03-27027 March 1990 Outlines Plan & Basis for Plan to Update Steam Generator Tube Fatigue Evaluations Performed by Westinghouse in Response to NRC Bulletin 88-002 ML20246H2601989-08-28028 August 1989 Requests That Suppl 2 to WCAP-12093, Addl Info in Support of Evaluation of Thermal Stratification for Beaver Valley Unit 2 Pressurizer Surge Line, Be Withheld from Public Disclosure Per 10CFR2.790 ML20248E8731989-03-0101 March 1989 Application for Withholding Proprietary WCAP-12141, Beaver Valley Unit 2 Evaluation for Tube Vibration Induced Fatigue (Ref 10CFR2.790) ML20245H6201989-02-20020 February 1989 Requests Withholding of Proprietary Suppl 1 to WCAP-12093, Addl Info in Support of Evaluation of Thermal Stratification for Beaver Valley Unit 2 Pressurizer Surge Line, (Ref 10CFR2.790) ML20245G6811988-12-22022 December 1988 Requests That WCAP-12058, Resistance Temp Detector Bypass Elimination Licensing Rept for Beaver Valley Unit 1, Be Withheld (Ref 10CFR2.790) ML20151G3491988-06-16016 June 1988 Requests Withholding of Proprietary Suppl 7,Rev 0 to WCAP-10170, Westinghouse SPDS Design & Verification... Process for Beaver Valley Unit 1 Nuclear Station, from Public Disclosure (Ref 10CFR2.790) ML20154A6511988-04-13013 April 1988 Requests Proprietary WCAP-11799, Beaver Valley Unit 1 Evaluation for Tube Vibration Induced Fatigue, Be Withheld Per 10CFR2.790(b)(4) ML20236S0731987-11-0606 November 1987 Requests That Proprietary Suppl 2 to WCAP-11317, Verification of Fracture Mechanics Analysis Techniques Used in Support of Technical Justification for Eliminating Large Primary Loop Pipe Rupture..., Be Withheld Per 10CFR2.790 ML20236A9631987-10-26026 October 1987 Requests That Proprietary WCAP-11419, Westinghouse Setpoint Methodology for Protection Sys Beaver Valley Unit 1, Be Withheld,Per 10CFR2.790(b)(4) ML20235J4491987-09-18018 September 1987 Requests That Proprietary WCAP-11317,Suppl 1, Addl Info in Support of Technical Justification for Eliminating Large Primary Loop Pipe Rupture as Structural Design Bases... Be Withheld from Public Discloser Per 10CFR2.790 ML20237L3031987-07-0707 July 1987 Requests That Proprietary WCAP-11522, Response to NRC Question on LOCA Hydraulic Forces Analysis of Beaver Valley Power Station Unit 2, Be Withheld (Ref 10CFR2.790). Affidavit for Withholding Rept Encl ML20206E4521987-03-24024 March 1987 Requests Withholding of Proprietary Addl Info on Beaver Valley Power Station Unit 2 SER Confirmatory Issue 032, from Public Disclosure (Ref 10CFR2.790) ML20209B2041987-01-0909 January 1987 Requests Withholding of WCAP-11366, Westinghouse Setpoint for Protection Sys,Beaver Valley Unit 2, Per 10CFR2.790. Affidavit Encl ML20198J5121986-05-0606 May 1986 Forwards Nonproprietary & Proprietary Addl Info on SER Confirmatory Item 32 Re Analysis of Feedwater Malfunction Event.Affidavit Also Encl.Proprietary Info Withheld (Ref 10CFR2.790) ML20151Z3281986-01-28028 January 1986 Forwards Proprietary Affidavit AW-77-18 Re Withholding Proprietary WCAP-11061, Unit 1 & Unit 2 Differences Analyses,Accident Analyses Per 10CFR2.790.Affidavit Withheld NRC-85-3041, Requests That WCAP-9735, Multiflex 3.0 - Fortran IV Computer Program for Analyzing Thermal-Hydraulic-Structural Sys Dynamics (III) Advanced Beam Model, Be Expeditiously Reviewed & Approved1985-06-18018 June 1985 Requests That WCAP-9735, Multiflex 3.0 - Fortran IV Computer Program for Analyzing Thermal-Hydraulic-Structural Sys Dynamics (III) Advanced Beam Model, Be Expeditiously Reviewed & Approved ML20100E1051985-03-20020 March 1985 Requests That Proprietary Seismic Response Spectrum at Reactor Vessel Supports Be Withheld (Ref 10CFR2.790) ML20107G1131984-12-27027 December 1984 Requests Withholding of Proprietary Technical Bases for Eliminating Large Primary Loop Pipe Rupture as Structural Design Basis for Beaver Valley Unit 1, (Ref 10CFR2.790) ML20140D5721984-12-0404 December 1984 Requests Proprietary Rev 1 to WCAP-9736, Multiflex 3.0, FORTRAN-IV Computer Program for Analyzing Thermal-Hydraulic- Structural Sys Dynamics (III) Advanced Beam Model Be Withheld (Ref 10CFR2.790).Affidavit Encl ML20101F7361984-11-0606 November 1984 Application for Withholding Study Re ESF Actuation Sys Setpoint Methodology (Ref 10CFR2.790) ML20098C8591984-08-14014 August 1984 Alleges That Unqualified Suppliers Awarded Contracts from Plants to Provide Flexible Conduits Unqualified Under IEEE Stds 323 & 344 Despite IEEE Bid Requirements.Meeting Re NRC Position on safety-related Installations Requested ML20093G8991984-06-0606 June 1984 Requests That WCAP 10565, Technical Bases for Eliminating Large Primary Loop Rupture as Structural Design Basis for Beaver Valley Unit 2, Be Withheld from Public Disclosure, Per 10CFR2.790 ML20083P7631984-03-0909 March 1984 Requests Withholding WCAP-10493, Third Cycle Performance of Beaver Valley Unit 1 Fuel, from Public Disclosure,Per 10CFR2.790.Authorizes Use of Affidavit AW-76-35 in Support of Util Request ML20082P8901983-11-10010 November 1983 Application for Withholding Proprietary Steam Line Break Blowdown Data (Ref 10CFR2.790).Affidavit Encl ML20074A0151983-04-20020 April 1983 Application for Withholding Proprietary WCAP-10196, Second Cycle Performance of Beaver Valley Unit 1 Fuel, Per 10CFR2.790.Affidavit Encl ML20028C7361982-12-31031 December 1982 Forwards Proprietary & Nonproprietary Incore Detector Thimble Reduction Study, Submitted in Support of 821216 Proposed Tech Spec Change Request 75.Proprietary Rept Withheld (Ref 10CFR2.790).Affidavit Encl ML20008G1421981-06-11011 June 1981 Advises That Facility Should Be Deleted from 810610 Part 21 Rept Re Missile Penetration Analysis ML19350C9491981-04-0808 April 1981 Authorizes Use of Encl Previously Furnished Affidavit for Withholding Portion of Cycle 2 Rod Misalignment Analysis (Ref 10CFR2.790) ML19347D4311981-01-21021 January 1981 Forwards Affidavit Requesting That Analytical Results of Impact of Increased Rod Misalignment on Peaking Factors Be Withheld (Ref 10CFR2.790) ML19347C7401980-12-23023 December 1980 Requests That Proprietary Info Submitted as Responses to NUREG-0737 Re Instrumentation for Inadequate Core Cooling Be Withheld from Public Disclosure (Ref 10CFR2.790).Affidavit Encl ML19249E8941979-09-19019 September 1979 Notifies of Failure of Personnel Fabricating Pipe Spools to Comply W/Asme Boiler & Pressure Vessel Code Re Welding Qualifications.Work Ceased Upon Issuance of Rept by Inspectors ML19289E6271979-03-23023 March 1979 in Response to 780922 Part 21 Rept,Informs That Injection Pumps Were Removed & Inspected Using Newly Established Criteria of Suppl 2, & Were Reinstalled on Engines.No Further Action Contemplated ML19289E6241979-03-22022 March 1979 Notification of Test Results Indicated in 780922 Part 21 Rept.Cites Three Causes of Injection Pump Failure.Concludes Pumps Are Now Adequate.No Further Action Contemplated ML19263D6021979-03-22022 March 1979 Notifies NRC Insp Completed Re Exhaust Rocker Arms of Two PC-2 Generator Sets.Unit Free of Potential Defects ML20083P7681976-08-13013 August 1976 Requests Withholding Info,Re Notification of Generic Problems Under 10CFR50.59(a) & 10CFR50.55(e) on Increased Temp in Upper Head & DNB Penalty Re Rod Bow,From Public Disclosure,Per 10CFR2.790.Affidavit Encl 1990-08-07
[Table view] |
Text
{{#Wiki_filter:-
p @,T C
Nuclear Tectnclogy Divisicn Westinghouse Water Reactor Electric Corporation Divisions ec,333 Pitiscurgn Pennsy!vania 15230 Director of Nuclear Reactor Regulation April 8, 1981 Attn: Mr. S. A. Varga, Chief CAW-81-30 Operating Reactor Branch 1 Division of Licensing U. S. Nuclear Regulatory Commission Phillips Building 7920 Norfolk Avenue Bethesda, Maryland 20014
SUBJECT:
Beaver Valley Unit 1 Cycle 2 Rod Misalignment Analysis (Proprietary)
REF: Duquesne Light Company letter, J. J. Carey to S. A. Varga, April 8, 1981
Dear Mr. Varga:
The proprietary material for which withholding is being requested by Duquesne Light Company is of the same technical type as that proprietary material sub-mitted by Westinghouse previously in application for withholding AW-76-8, and was accompanied by an affidavit signed by the owner of the proprietary infor-mation, Westinghouse Electric Corporation.
Further, the affidavit AW-76-8 submitted to justify the previous material was approved by the Commission on November 9,1977, and is equally applicable to the subject material. The subject proprietary material is being submitted in support of Duquesne Light Company, Beaver Valley Unit 1.
Accordingly, this letter authorizes the utilization of the previously furnished affidavit in support of Duquesne Light Company, Beaver Valley Unit 1. A copy of the affidavit is attached.
Correspondence with respect to the proprietary aspects of the application for withholding or the Westinghouse affidavit should reference CAW-81-6 and should be addressed to the undersigned.
Very truly yours,
/bek Robert A. Wiesemann, Manager Attachment Regulatory & Legislative Affairs cc: E. C. Shomaker, Esq.
Office of the Executive Legal Dirtctor, NRC 810.4100 g
AW-76-8 AFFIDAVIT COMMONWEALTH OF PENNSYLVANIA:
C011NTY OF ALLEGHENY:
Before me, the undersigned authority, personally appeared Robert A. Wiesemann, who, being by me duly sworn according to law, de-poses and says that he is authorized to execute this Affidavit on behalf of Westinghouse Electric Corporation (" Westinghouse") and that the aver-ments of fact set forth in this Affidavit are true and correct to the best of his knowledge, information, and belief:
t' ! M'??(Uut Robert A. Wiescmann, Manager Licensing Programs l .
Sworn to and subscribed before me this #8 day
) of d/imI 1976.
l 0 s l
I L. & #4@
/Notary Public/
~
l ..
j
AW-76-8 (1) I am Manager, Licensing Programs, in the Pressurized Water Reactor Systems Division, of Westinghouse Electric Corporation and as such, I have been specifically delegated the function of reviewing the proprietary information sought to be withheld from public dis-closure in connection with nuclear power plant licensing or rule- ,
making proceedings, and am authorized to apply for-its withholding l
on behalf of the Westinghouse Water Reactor Divisions.
f (2) I am making this Affidavit in confomance with the provisions of 10 CFR Section 2.790 of the Commission's regulations and in con-l junction with the Westinghouse application for withholding ac-companying this Affidavit.
- (3) I have personal knowledge of the criteria and procedures utilized by Westinghouse Nuclear Energy Systems in designating infomation as a trade secret, privileged or as confidential comercial or l financial information.
(4) Pursuant to the provisions of paragraph (b)(4) of Section 2.790 of the Comission's regulations, the following is furnished br consideration by the Commission in determining whether the in-famation sought to be withheld from public disclosure should be withheld.
l ~
l (1) The information sought to be withheld from public disclosure l is owned and has been held in confidence by Westinghouse.
i 1
AW-76-8 (ii) The information is of a type customarily held in confidence by Westinghouse and not customarily disclosed to the public.
Westinghouse has a rational basis for determining the types of information customarily held in confidence by it and, in that connection, utilizes a system to determine when and whether to hold certain types of information in confidence.
The application of that system and the substance of that system constitutes Westinghouse policy and provides the rational basis required.
Under that system, information is held in confidence if it falls in one or more of several types, the release of which might result in the loss of an existing or potential com-petitive advantage, as follows:
(a) The information reveals the' distinguishing aspects of a process (or component, structure, tool, method, etc.)
where prevention of its use by any of Westinghouse's competitors without license from Westinghouse consti-tutes a competitive economic advantage over other companies.
(b) It consists of supporting data, including test data, relative to a process (or component, structure, tool, method, etc.), the application of which data secures a competitive economic advantage, e.g. , by optimization or improved marketability. ..,
AW-76-8 (c) Its use by a competitor would reduce his expenditure of resources or improve his competitive position in the design, manufacture, shipment, installation, assurance of quality, or licensing a similar product.
It reveals cost or price information, production cap-
~
(d) '
acities, budget levels, or commercial strategies of Westinghouse, its customers or suppliers. -
(e) It reveals aspects of past, present, or future West-inghouse or customer funded development plans and pro-grams of potential commercial value to Westinghouse.
(f) It contains patentable ideas, for which patent pro-taction may be desirable.
(g) It is not the property of Westinghouse, but must be
! treated as proprietary by Westinghouse according to agreements with the owner.
j There are sound policy reasons behind the Westinghouse system which include the following:
(a) The use of such information by Westinghouse gives l
Westinghouse a competitive advantage over its com-l peti tors. It is, therefore, withheld from disclosure to protect the Westinghouse competitive position.
l l
l l
. . l l
1 i
AW-76-8 (b) It is information which is marketable in many ways.
The extent to which such information is available to competitors diminishes the Westinghouse ability to sell products and services involving the use of the information.
(c) Use by our competitor would put Westinghouse at a competitive disadvantage by reducing his expenditure of resources at our expense. ,
(d) Each component of proprietary information pertinent i
to a particular competitive advantage is potentially as valuable as the total competitive advantage. If i competitors acquire components of proprietary infor-mation, any one component may be the key to the entire i
puzzle, thereby depriving Westinghouse of a competitive advantage.
l ,
(e) Unrestricted disclosure would jeopardize the position of prominence of Westinghouse in the world market, and thereby give a market advantage to the competition in those countries.
(f) The Westinghouse capacity to invest corporate assets in research and development depends upon the success l
in obtaining and maintaining a competitive advantage.
i
'O AW-76-8 (iii) The information is being transmitted to the Commission in confidence and, under the provisions of 10 CFR Section 2.790, it is to be received in confidence by the Commission.
(iv) The information is not available in public sources to the best of our knowledge and belief.
(v) The proprietary information sought to be withheld in this submittal is that which is appropriately marked in the attach-ment to Westinghouse letter number NS-CE-ll39, Eiche1dinger to Stolz, dated July 19, 1976, concerning supplemental infor-mation for use in the Augmented Startup and Cycle 1 Physics Program. The letter and attachment are being submitted as part of the above mentioned program in response to concerns of the Advisory Committee on Reactor Safeguards with the new Westinghouse PWR's, which are rated at higher power densities than currently operating Westinghouse reactors.
This information enables Westinghouse to:
(a) Justify the Westinghouse design correlations.
(b) Assist its customers to obtain licenses.
(c) Provide greater flexibility to customers assuring them
~
of safe reliable operation.
(d) Optimize performance while maintaining a high level of fuel integrity.
AW-76-8 (e) Justify operation at a reduced peaking factor with a wider target band than normal.
(f) Justify full power operation and meet warranties.
Further, the information gained frem the Augmented Startup and Cycle 1 Physics Program is of commercial value and is sold
- for considerable sums of money as follows: ,
(a) Westinghouse uses the information to perform and justify analyses which are sold to customers.
(b) Westinghouse uses the information to sell to its customers for the purpose of meeting fEC requirements for full power licensing.
(c) Westinghouse could sell testing services based on the experience gained and the analytical methods developed using this information.
Public disclosure of this information concerning the Augmented Startup program is likely to cause substantial harm to the competitive position of Westinghouse by allcwing its ccm-petitors to develop similar analysis methods and models at a much reduced cost.
AW-76-8 The analyses performed, their methods and evaluation repre-sent a considerable amount of highly qualified development effort, which has been underway for many years. If a com-petitor were able to use the results of the analyses in
- the attached document, to normalize or verify their own methods or models, the development effort and monetary expen-I diture required to achieve an equivalent capability would be significantly reduced. In total, a substantial amount of money and effort has been expended by Westinghouse which could only be duplicated by a competitor if he were to invest similar sums of money and provided he had the appro-l priate talent available.
Further the deponent sayeth not.
I O
OLWP0-42 bec: M. H. Judkis 4L, 4A J. A. Triggiani ll, l A B. Voltig 1L NSD Central File 3L, 3A r
I f
1 l
l
,s .
BEAVER VALLEY UNIT 1 CYCLE 2 ROD f1ISALIGNME!!T ANALYSIS Backaround During the Cycle 2 startup of Beaver Valley Unit 1 (DLW), Duquesne Light Co.
(DL Co.) experienced problems with their Analog Rod Position Indicators (ARPI's).
The cause of the problem was the temperature sensitivity of the ARPI hardware.
~
l Because of the changing temperature of the control rod drive shaft with changes in power level, the ARPI calibration performed at HZP temperatures was not main-tained as the plant escalated to higher powers. Consequently, DL personnel saw significiant deviations in the ARPI readings relative to the bank' demand step counters. The deviations stabilized to approximately 30 steps as transient thermal effects dissipated. It should be emphasized that DL Co. did not observe actual rod misalignments; rather, they observed indicated rod misalignments as the result of temperature induced misreadings by the ARPI's.
l To circumvent the problem, DL Co. silb.nitted a Tech Spec change which would allow an alternate method for inferring rod position. The ARPI system utilizes a linear variable transfamer consisting of primary and secondary coils alternately stacked on a stainless steel cylindrical tube. An extensi.on shaft from the rod drive
{ mechanism extends up into the tube and serves as the variable " core" for the transfomer. As the rod moves, the voltage at the secondary and primary coils.
changes due to the position change of the transformer " core". The ARPI, then, infers the rod position by sensing the voltage changes at the secondary coils.
l DL Co. has found, however, that the primary coil voltage is less sensitive to temperature than the secondary coil voltage. The alternate method proposed in the Tech Spec change perm'.ts utilization of the primary coil voltage to infer rod position in those instances when the ARPI reading indicates a misalignment of i 12 steps or greater. DL Co. is currently using the new spec for Cycle 2 operation.
As an alternative to the Tech Spac change described above, DL Co. wanted to be able to submit another Tech Spec change, if necessary, which would pennit indicated misalignments of greater than i 12 steps. To support this proposed Tech Spec, Westinghouse was asked to evaluate the Cycle 2 peakina factor penalties associated
k with a 132 step misalignment (16 step indicated misalignment olus 16 step ARPI errorallowance). The original Tech Soec permitted a 112 step indicated misalign-ment. This, together with the 12 steo ARPI error allcwance, limited the maximum possible undetected misalignment to 1 24 steps. Thus, the proposed Tech Spec would cermit an additional undetected misalignment of 3 steps (5.1 inches).
c0 3
,i t
i I
, I The objective of this analysis was to assure that the conservatism in the design calculations was maintained with the rod misalignment of 132 steps.
l i
1 l
l
- one rod either fully inserted or fully withdrawn
Methodoloay To support the 1 32 Tech Spec, rod misalignment calculations were performed to assess the peaking factor penalties resulting from 132 step misalignments of single D and C Bank rods. Coarse mesh 3D-TURTLE calculations were done (2x2, 21 axial meshes) with the 3D-TURTLE peaking factors coarse mesh corrected to discrete 2D-TURTLE. Calculations were made at various power levels with control rods positioned at the appropriate insertion Ifmits (Figure 1). The 3D-TURTLE control rod constants were chosen so as to reproduce the discrete TURTLE rod worths.
Each D and C bank rod was misaligned by 1 32 steps and the resulting effects on peaking factors were deterinined (Fxy(z), FaH, Fg ). The Beaver Valley Unit 1 control rod pattern is shown in Figure 2. The potentially misaligned rods are indicated on an eighth core basis.
F g Penalty Table 1 shows the 30-TURTLE calculated misalignment F3g penalty as a function of power level. The 150 MWD /MTU step was used as the base case since peaking was a maximum at that burnup. The calcula3fons assumed equilibrium xenon except at zero power where no xenon was assumed. Note that the penalty is small at high powers where ONB is a concern. At low powers the penalty increases due to the increased rod insertion (especially C-Bank) and reduced feedback effects.
f i
l -
l _
~~
I i Rod Misalionment FyQJ, Worst case Fxy(z) values were collected from the misalignment 3D-TURTLE .ases for each axial mesh. Coarse mesh F,y's were corrected to the 2D-TURTLE discrete base case. Figures 4 and 5 show the maximum calculated Fxy(z) values for power
' - **'M w --m- w,erw- ,p-, , . , , _
levels of 100% and 45%, respectively. Also shown are the axial and cower dependent F
xy limits from the Beaver Valley Unit 1 Tech Specs. The calculated F xy 's include an 3% uncertainty factor.
4,f--
RodMisalignmentFg Associated with the limiting Fxy(z) values discussed above are the limiting Fq (z) values shcwn in Figure 6. These limiting F 's were conservatively generated by n
synthesizing the limiting Fxy(z) with the worst axial relative power for each axial mesh. The reference Fg (z) values are also shown in Figure 6. HFP equilibrium
. xenon conditions were assumed and the rods were set at the HFP insertion limits. ,
The plotted values include the 1.0!i.and 1.03 Tech Spec uncertainty factors.
Note that misalignment penalty occurs primarily at the top of the core (in the rodded region) and that considerable margin to the LOCA Fg envelope exists in all core elevations.
r ._ _ _ _ _ . _ _ _ _ __
l
~~
l l
l l
5-The above argument does not account for the power distribution perturbation resulting from xenon distribution changes induced by the load following misaligned rod. This effect was judged to be small, however, since the axial newer distri-bution in the static misalignment cases was not severely perturbed; [_ _ _ _ _ _ _
~.- _ .
-%c
- J 4L To conclude, the F g enalties p resulting from + 32 step single rod misalignments can be accomodated within the existtng FAC Analysis conservatism.
Measured Peakino ractors The results presented in the previous sections were based entirely on analytical models "or the Beaver Valley Unit 1 Cycle 2 core. Measured power distributions confirm that the models used in this analysis are quite adequate when appropriate uncertainties are aoplied. Table 2 shows the results of several moveable detector incore flux maps. Note that the predicted F 6g peaking factors, with uncertainties applied, are equal to or greater than the measured F H eaking factors (including uncertainties). Thus, it is clear from these results that the nuclear design methods used in this analysis adequately predict peaking factors.
For this analysis, the control rods were conservatively assumed to be at the insertion
( limits shown in Figure 1. It should be noted, however, that as Table 2 indicates, the plant typically operates with control rods essentially withdrawn from the core.
Typically, even at low power, the rods are positioned almost fully out of core.
Consequently, the assumption of rods at the insertion limit used in this analysis conservatively estimates the effect of rod misalfonment on peaking factors.
Sumary
~
I 1 Analysis done here has shown that the peaking factor penalties resulting from mis-alignments of + 32 steps are small at significant power levels and are within the conservatism used in the Cycle 2 design.
Comon practice is to operate the plant with rods essentially withdrawn. This combined with the fact that actual rod misalignments are very rare in Westinghouse plants makes the occurrence of large misalignments very unlikely.
e i
*'M* - -
~* *w= ew..e. .e., ,_-. _. . .
TABLE I Beaver Valley Unit 1 Cycle 2 32 Step Rod Misalignment F vs. Power Check
Discrete Discrete F syn 3D-TURTLE Ff,"with 3
20-TyglE aH Rod Hisal. Misalignment Quadrant Power F,g Including 0% Uncertainty Penalty (1) Penalty Tilt (1)
Ak s
l
~
- TURTLE calculations employed Eq Xenon at all power levels and zero xenon at zero power.
Best estimate power sharings were used for the F 3g synthesis. All calculations were done assuming the rods to be positioned at tlie insertion limits. ,
l
1 TABLE 2 Typical Normal Operation Flux Hap Results AL\ ;
map 8 l Burnup (HWD/HTU) ,
Power (%) :
! D-Bank Insertion (steps) i Heasured 3gF* l 4 Predicted F 3g* '
3g Limit F
1 Heasured Fq Predicted Fq Fq Limit HeasuredTilt(%) !
Predicted Tilt (%)
Tilt Limit !
I L- i
- Measured F 3g includes 4% uncertainty. Predicted F aH values include 8% uncertainty.
i
P00R ORIGIW I e 0 .e
.. ,i_. .. ...... .. ..._
........... ... . . _....e
..g
. ... .. .5.... . .... ......
.e.
.. . .. .. . .... . . (
.. .. l .
....t. !'. .. ... . . . . ...!:.
f'
. .. . . . . . ..... ..I.._... . ..
n...:.8. .....r. .. . . ...
g .. . ,
g2 -
i ! - BANK C 1 -
.l.- h / - 187 Steps 6 .l j. /-- 1
. p- j. -l
. i' ..
-l -
Withdrawn
.{....
.e .
.l. . .j.. .1
.l..:. ... .'-..
g . . . .. .[. .l.
.... .l.. .. . . .
~
g . . }- ..
.. l.. . . .:.,.......:. . . . n: .l; ..:. ..l:..... !
.. l.. .
c3 ..
.r .. ...
.. i.
t ..
.t .
.u
.4 . . . _.. _. _. .. .a. . . . _......_._......_...:_..r.__..._.
.._J... ..
. .... 4, _.. .. . . .._...
.m
. _. .. __t_._._ _.-.____-_._._._..._.1.
. _.. _.. .___ .. .. .t._...
. ._ /. 4 ___. r._._._ t._ _.._ _. ....._._...___
.s_. -=
-114 Steps
- e . . . _ . . . , . . - . . _ , _ _ . . _ . . . _ . .,. _ . . _ _ _ _ . . _
o + ._.. ._. . . _ . _. . . _ __,s___. ---
. . ,, BAN K D . . .
i
, ......t._..__t___._._..._._..._.._._...._._..,......_.._._..__..
. _ . . rawn
- a o .6
- n. .
.t _.. _t _... __ _. .... . ........ ..._..... .. . . _... _ _. .... __.2._._t.........._...._........:.._.._.._.
.x _.. .
,e _.n..._.._................_.........__........s._._........_....r.....-t...--......_-a....-
gg
..t... . ... . . . . ...
m o i. : :
ce l-
. .r .
.8 . . .
t.
.. ... .. . .. .r .... . . ...
.r.. . . . ...... ... . . .
_ .....t....i... . . ..._ .... ...... _. _..._....
. _ . ._. ... . ..... ..__..........r_.
_.......f-- . . _ . - " . ._......._.
_ . ..... _.._.._....r.__ __
" _ " 2,-
"-- ~ ~ " ~ - - - . .........--t-------
1.0
~ " ' '
1 0 .2 .4 .6 .8 1.0 Relative Power (of 2652 MWt)
Fv. % .:. .
Control Rod Insertien Limits as a runction or. .ecwer l
l 1
I E ..
. . ~ . . . . . . . . . . . . . . . . . . . . . . . . _
RPNMLKJHG
~
F ED C ~ 13 A R CRI,Niq ,
,D, A
' 2 A
i SA SA SP b
' C B PL 8 C SB ,
b l SP SB SP _
i
-A B D C O 8 A-
^
SP SA 7
SA -, SB S8 -
i :
' l D PL C PL Ci :PL 'O 270* b 90-l ~9 SA SP SB S8 SA
,D In f D' 8 A 10 A 8 1
SP S8 SP
!t t SB C B PL 8 'O 13 SP SA SA l
1 A OJ A .
Absorber Material:
Ag-In-Cd
-.. ..... riu-rsr of Clusters l5 Cc.':r:. ::n( 0 0*
Control Bank C 8 Centr:1 Eany 3 8 Control Sank A Shutdown Bank S 3 8 Shutdown Sank SA 8 Part length FL g SP (Spare Rod Locations)
FIGURE '2. CONTROL RCD LOCATIONS i
1 -- - - - - _ _ _ _ . . . _ . _ _
J^
- G '
Mr w a. '.". 3 Y - - --' _ b-1: =iu .-- i-' " -bi=:E = 4- *- * ~ -' r= = P ~43 HF55-- ~ -
-- - O
- . -=
.._.~_. .
._.Q. .
=
e- -
~
.-- y .
f 5
-= -)
4, JG -
J=f
_ _ . _ _ - - _x
, _ _ - -~^
w ,
_=.p O
, .__ . g& . . . ___
t # NII i
= _: s: .;
b-
=
=.n -
l :=..: g . =__
= 0
- F.D A-- , =
==
c
~
..:g
=
ID .*,7 *M { _~ .:., -
8 g I* I, * ' tE. * " U .
w - =
= 3
.-~ . :1
_=_--r-.
_. :,: . jj . y.
=
=
0
=
- pf. _ Wi q-
=_.
m
_. I- I
=_
= b
??. : [: 4 2 O
...J-u, 1 E-
=
q y.._.
=
r.wp.-- q=.
- rT . :. :: -
=
0
- l. . ..- . _.< [. ...
g =. ..6 2 --
..g..
2 J
1 0) -
I -
d up w as I _
Je
-J <T- ;- - - -
t me 1
=4g . . --k A- j {_
.og -- - n : = 0.
J_. _;,
"% _ ;_ .5 :
S= P:: _.L r 1 3_,
=3 _E.:.=... [H.=5
=
38 ;-
; . 4-.4 *
.-T. '
[
v
. .-.--..'-. =n
.4= _. ! E_
SL . **
.__ _ -- =_
_=_-._=_:
-.i..-
;,,a e,
--~ . . - - _ - _ . - - _ . . . - - - - . . _ - - _ _ .
_ _ - . .--_=.r..._ , .. _
_ _ . _ _2
._-we--
, Ah
' 6 "', -e.--.
W .- 6
-_m_.g
.--4.i- e
. - .. w -- .-["
- - - - - - - - - - +^- -- ; :-=- =. : -- o==: =.*= =- ==.z=
d=..=_.-_- --.s.----+-
-- -~
t:- = - .:
-u..t. _. . -- . _ :- - ::.
-~ Y 2*
-. ~5EE~.?- 1:::hC~.:-
t :.'* :d -. ~~. :. t v :. t':. . = -~ t: -~--= 'E'
- t-t-y _ w_ = "p.qr.m'- : = syme=.A-= :=.1 . r- - - - - - - - - -
r= ==. .
- 1 : : x= . =p . ._= . .. L-n== :. .. 5. =---= .r- : . s - : - - r=-
! .=:_.1
- - --- t -- - . - - = . .. ,
, . E ~ ~-~ l -- ' 3 7 -~ ~ = E rr . . _ _:_ _ . . _ . - _ . _ . ._ _ _ : .----t _ . . .. - eF E"- i " " - :- r - -i = " ~ F - -
~ ~ - ' - " ~ ~ ~ '-
l= .=. __.. . . = '.-I .: =._. __. . . ' :.:: : .L_.=.. --._w_ =i=i= ~ ~
.r...__ ^= ==:-=' =_. W .-
===r_==+.. ..h_=. . . : _.
~- ~ ~ ~ - + - - ' - - * ' ' ~ ~
\'.*= . r~ . .-. .- - t _.~.
r
_;4 J = :..={: .C. at=-
==:s=.=.== .t = _: -- -- - +- ---"-----~=--:--;;--4=.'=~*t=-.~=--- --
= ::- =.u
9
.e-. ~ -
a g h. W r - T : = = r-- i . . ---j ~=--l- g . <$ - . - : i:. T: t- m .l' -
r:= =- ii;-i-- ; ~ i . ='i' " ; 37. -
_E
. , . ! _ .2. _. :_:i:1_::- '.2 = yii=,Ja., Q p . - e t :; : .. rom. .;. . :
- a. ; .;c.:j t. y -:-fa - .-- g -
- . ~ ~ = _-
- _ . - ;g- w- n e -e# _ : _
- r- __...___
* : r... r- nan r n.c- i q; . - - - .-- - r. -- - . - f - :
! ! .'_"* ! *.;- ~
*.1"'-* .A'- .; sam.':5.L t /T _ '
- t. l' -
- ._ .j r.. g. ff.. t"th . .q .. . .j . , p. . r,.: .i _- J
, $, .a; .+ v. 3._.. . . .
.t .
g ..
j . ,g_2 ma
. . t - - .a
.s...
2.. ---,, ;
, f_._ 3 ._, { . _ , . . ';. .r_
,- u un
.r.. Fr .' -
.fE
- o. - ..1' i ( - fY: I'- -
' -- !- 1 1 m .,. - .
s ._M t- g .u,_
-3 W i ! -+----r----
]--- i.Q :- l: .:- -j. ::p }'- f
); --] . : : a{_ -
- y. V-' !- m :.gi m -
5 ..-i. . :p , rF a s - .+ p. v. t-.;_ _ j____
.p =ii- ; .
'"---t*a -
- :. s .
.,e-- _ s _ i -f:. . .I .l- h:_n"': _.T-+-----
*- 5-t ~~~ a ' 5 :' _ ' *
, =- ; c . p . y 9 :( p-'
p .,. .-- . . .__ ,
, e . .
;; .. __.:1 - E', b
; e ; . 2. l.- ?.L" : l p. i.... g F g .t _ _-
a- =-- 4--+ ! 19 ' ~ - l-. L st-f=t. _
---- W t.. . : .=. . . - - g _~= . - _ _--
;. . == l. .. . .. .c:. t= .r:;_ -- - - - -
- ~~~
%ie-1 .tminiiss-gcgi::pla:=
Ch -- -
~
b.:i -t i~.llf W : l TL#lb='~~ ?
l - p= =- 5=
z _.
=p== l e i=: y==3; .j=:
x.
c g f_,:r_:_ i' " fs.._..Nu..
nia n _ :: . - li.f -
. : 1.:-ki:: 4- ._ .
Z""~
, -- -- . r. m -- ==. :.r : r, -
p - .. -. ._.r--- . - . _ . ___.
===~
- d f~ ~ ===~{Ni . ____
( -f, _ _ _ _ . . ._ _=-=.7.._.3.3-=. -. .
_ "i= N' = ~~
_ _ . = g=_ = := a ., _ _-.
a.
p E ~.=F Ei~#'i; - Xil "ETii2f EL
~
l 3 "- ' p .z 7:j _ . = d._._.= l . .ij;Lt. .-i: _
-i-jii, Y GT 'l "]. T: : === --- 2 f _
2-2___.p _3 .q . 2.
. . p . g_ g_. m q.p. _3--- -
x-e =--- p:- =r=-
h-
__,= 4r = -
gl
$ b -- -i - b :-- "= 1 C d. . .. -
i l N ir-![~.--__ . g
.." *f.*i"*
*3,
< ' .- f *.*" ~ *-" ! .' f . *.b. . f b_ i . . _
! h S - " ~ . ~. I l E l l!5 T.~ ~ l ~~li- ==-
t py
= = a. ; =. _ . 9._ ,: = = = . p _= .9 = . :
. g . - r. - . _ . _
h -- -I i-- .I . i "
.: _ l:IU5:.- '
~ ~
' l _.:. .- t-- -
9 .p. p- - q__ ui: - -::i: , =a--- ; _a r i si+r"==-
l- afi F=- EiE : 5falirzi f' h='h A-a =
,n a
- ==nJT E- EE _E _ TOE--- m-l 2 :_ _l ~=~E.~-@ i
=
, . :=-f = r = --- - i -- --- r-- = iT=- : _
. :_ _: . : w. . . . , _ _
=. =. _ c :=...:..__
3
_:=._2-"
. C- *- : 6._ __
=...- -
-I
~
= 1. - _ -
- . _ g.==.s..
t E. . - - - - ._: =
- . . - :._ Y. g: : y___:-
. .___:__. _ _=_= . ~ .t. _ .=_- +. . _
. ._.t_ _ _. -l .. , _
- r. - _ e _ . .g_.._ - . - - - _ _ . _ .______- _
. *: T. .. . CId" . _ ~ s_-'b.__.
.. ~_ E~ ! ** I '*I""**1T.="--f*""*~" ' * . . ' ' * , ,
' = h'. j : _4E =ifEE:iii.j- IF-'i-+r- ~---- T
" ~ -
-T' l *- 8 ; =P~ : ' F=3 *=* ='4" ! 'j =E-
-- ::.y - :- -[:- j--p ,:_ - l - -- r- : l 33- ri--- :}- 21 T " i ~-'= ~T ~ i:T =i F+i~' L :- '
. , g -- .:.:;, . p..p..y .
. . y g y. . [: 7 . f .. .; ,_ .. [ r 7:- ~ T-- ~1"
-q . p.c . .pr y g- , . _q . . . . _. , . _ . _ p = gq . ; p ;- ; =p p 3- p- .
=i : l.:.u. . p. .. j -
. . =4g = . g- .. ; . _=q==. . t : . p i. .p j ,. . L y- t. : i.
t i !- t- T: ; r r.:F l i i i 1 i ! I i g s n e 4
,,3 -t- - -
d
P "_ G u v _
7._.__...___..__.._._.._..._.
. . , : -. . __. t - - .
r-+__.._
~ .. -._ - _. _
__._---------r-_.--:----------
_ _ . __- _ _. -. -. +_-_- -_- .- __ ._. _=. . .
. p. . . _ . ...._._._:._._____=.=..__.__:._..=__._
_c .
.;=
t-._.=..
=- -=__._.....,=__=._;--==._-____:__g
.w _ , , _ . _ .
= - ..
.x- ..:.-u--. : . :- :--- - : _____._s ._._.___.._______._._,.. . ._ .. . . . . _ . __
N . _ -! : - i - - . I: i _..Ex -D2N:~.E-lhrS'? i : ' i - @ -J . O P r- M r -- q ._ ;l - - - . .;.=. . . c .-- . l - _; ; . ! c_.
.; . c._ ;. =__ ;
_ _ . _ . . . _._ . _: ;u .~.'*
. : ...M --
x- -
- .=r= :- .
G.l[ - - *
- - l:: 3 . ---- n : _ _- -
1 1 :_- .
._.1
. . _. . t w r. . * - -.
4
. p 4 i r r-e s rt:=2 v t .==
- - . _ . :-- - - - :- , - r- _, ;_ 7_ . : . .. _, 7__-
.y e } -p lm : : t t".+
.i:
i- I n . .___..,
M- i - I l- .l: . i -- pq c x --
, _ _ g_ p . . t. . . t. . . .. p. . . .
gg f n7 .._ _ -
#.,4=~= sN=- :t= . = =-n 2=r := =ts g . g.. .; .. ; y m fQ AI -
. ..= .p._ p ._
. g.42 _; ._ ,
~
e :lct:L w:\;.. --ht:x 1.mi=f= ~
c
)i. n- :.- : _... - ] =. :...:.t.; r::; . ^h_.
.u. .
- l. _i. .=c.---
- .=..
2 N- ! .7"k -
~-- b'I' l ~ _f_~
h, ,_ .=_ : __ - e __ .g =_g. _ . .___. _t --.; -- -
y 4c. . - -- i ,_ Tc
==.__:.=--
} :
L- N:4 : =l= ..
;= !
Z -~- r Ti i f. RE_-t G t:r=;t- ==. . _ _ _ _ _ . . -
L, l l UT h - E-TNfMi_NN_4 3s I' l- ~8 E hr.% : Eil _
@ i--h--+ -P 1--4
~r i!- lZ_' ?.~ -
._.p _4 c. =4.. .p _l.:j::::f .- _Z-~Q=$=-
N 9 =. l.2.;- :l.::ik: .= 5:l= -"= E ;i9 2==__3 :
.: j' . jn ; .= . ei p :- p .5i.-{ali ;- - __
O l
_I l- - } 2; = N F . d..Ei.=2I~ 9 . l:-T_5.
- M I^ f.L:i {_ 2. . kSIM :c : li:.i:2 h-jl. .t t b l. r W t= M t -r= ,S
!.! s
[- -
4_ = _ _p =. : . y . . _ . . g..
, Is H .: ; =-E - _ ^ l-- .,d;t- V"-[--: . .-[ j_ ._ .
_1 z -.__.4...
- 4. . . ._ g. . _ . . f : .4.
g... .t :2..y__..;._ =:-:
4 y.-r ; v. :==r_ _ _
[
y ,
J e_.
-i_
-} -;[
l . = [! W -}4_L%
T
,,.._t7._57~
[
l f _e I
- l. . : . L . ., . i. ; .3
_ , _ . . _ , -. m
'_i *. C=;
l y l-- - _!!_*.**_=['_ -t -1/._ -
_1 ::.:_ _ -
I see ..c- :- ;.
g.:
c~._.I.a_.--
T== r ;"'.r*.:='. :
l g yu_ f.....J._}._
----==:--:__.;_..._ . _ . -- u . - : _r.
N . #~ f- . V : M E -H i;=*- -. =t--
g v I. _..._.... r .._1.-- c_.... .__.
( %
h.:.:.. _. :vc ;
O =__-_r. .ii.--
= { i- T_.q _ r- t=n __ _, _ _ ,__.
- r- = F___ .. . ___ . _ . - . _
_=_ ;:w= =_.. .-_y:u a =.w u . .$a - - -- r - - -- -~ - - -
_= ; n~:_ . -.t===_C. --= q
. ;. . - @ ;;;- L. . ;--";;"j .__ . ._ E _2 - !- ~
E. ._ _-__ _
2: _: = c --- :=_- -
.- = s - . - = -5=. . ===2 . = .= __. -t __.
@.f.~II-ES I ~b E-@.@$~M~II--i [.~-_------ - - -' T=.C- ' i- 1 f- - i _=_ . 2 __ 2.- .: =:. a!.2_.'_3 ~-EN
.l:..:.-x n _, = - .m-
.q - - . ..~t-- ::=. . .7__ - : : L==-- t--
=:= -= --- - - h_- : : = g._=- _ -- - ;
. . : - . - +:-
. := = _ _:. - ;_ : a c==
*-::-"-t=-_
p n=_ :--.
l_ _ _ _. F. . . ;
p-~ f --lp: [ g- T-TI = =-~E T-b --- ;-= _ ; --- '=~--- -:u :=4-~~ J : ="t = =i=~ = f ==.-+= - - ' -
> =_=. t.
I. :. n. f
.s.. H j.-
. .r t .. . :.r2
.s 7 -----
g :
, _ _ 3 ___,_,_y,_ _ : ==. 7: ;_=_ g f . ; - n_r__ i= x s . c.== '_r == _ = - - -
L-. =..._ -s_. e s t- -rs . . t---
- =:-_-
.1 :; . . _ s . .
> _ __ . _ = _z
_._a
______.=-_c---_.=_---=r-
. :_ ._. : . . . . . ; w . . . . . . - . . .
.-,..{~ l% q - -{. . . ' J --{ -QJ { _ ;_ _I,_ J* - "-- *- --]- 1 _= -'g_] . ]:42.,-
e -
O. . e w r- a N. r. N - -
1
- - u.#
/.
AMI . .. - . .
.. a. W . 1-.
l'.ax'-"- CFQ '
- pre _,) versus Axial Core Height During !?c:=al Opers:1cn - Cycle 2 t
. _ . .......t._.._..
- 1. .t. .....
. - ...r.. .
.x ... .... ... ._....... . ._ _
. ... . _._ _ --. . . . - . _ . - . . . _ . _ . . . i e
2.0 .
e o : -
as . :
- s. .
- n. _
w . -
w i
- n .t . _
4 .
I a.
t 1,2 1, g. ....-t.-..--.t-..._-.t........r_...-..+.-..-.t..r.-:....e. . -- . . . . r . l . t .-
. . .. . r.-- - ,. .
0 2 4 & 8 IQ 12 -
Core Enight (feet)
- . - - _ _ _ _ _ _ _ _ _ _ _ - - _ _ _ _ .,v_. _.,.,.. , _ ,.,_,gs, . aqr er .r4*'a.-A.=w