Forwards IE Insp Repts 50-445/81-01 & 50-446/81-01 During Jan 1981.No Noncompliance Noted
ML19347D534
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 02/13/1981
From: Seidle W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Gary R
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
Shared Package
ML19347D535 List:
References
NUDOCS 8103260483
Download: ML19347D534 (2)


See also: IR 05000445/1981001

Text

Y

D

M

4,

UNITED STATES

NUCLEAR REGULATORY COMMISSION

7, g

i

'

%.

_

j

REGION IV

jf

611 RYAN PLAZA DRIVE. SUITE 1000

"'

,% , ,. , . ,s'

ARLINGTON. TEXAS 76011

^

In Reply Refer To:

'

RIV

Docket No. 50-445/Rpt. 81-01

q l J.

50-446/Rpt. 81-01

g

L

yg.

4

.

Texas Utilities Generating Company

5

IMR 2519815 h

ATTN: Mr. R. J. Gary, Executive Vice

9 Woue mmum,, g;

President and General Manager

2001 Bryan Tower

(

)g

Dallas, Texas 75201

Gentlemen:

This refers to the inspection conducted by our Resident Reactor Inspector,

Mr. R. G. Taylor, during January 1981, of activities authorized by NRC

Construction Permits No. CPPR-126 and 127 for the Comanche Peak facility,

Units No. I and 2, and to the discussion of our findings wi+.h Mr. R. G.

Tolson of your staff at the conclusion of the inspection.

Areas examined during the inspection and our findings are discussed in the

enclosed inspection report. Within these areas, the inspection consisted of

selective examination of procedures and representative records, intersiews

with personnel, and observations by the inspector.

Within the scope of the inspection, no violations were identified.

We have also examined actions you have taken with regard to previously identi-

tied inspection findings.

The status of these items is identified in para-

graph 2 of the enclosed report.

l

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,

Title 10, Code of Federal Regulations, a copy of this letter and the enclosed

!

inspection report will be placed in the NRC's Public Document Room.

If the

l

l

report contains any infonnation that you believe to be proprietary, it is

necessary that you submit a written application to this office, within 25 days

!

of the .date of this letter, requesting that such information be withheld from

public disclosure. The application must include a full statement of the reasons

why it is claimed that the information is proprietary.

The application should

OQ

l

8108260

k

s

.

Texas Ur.ilities Generating Company

2

February 13, 1981

be prepared so that any proprietary information identified is contained in an

enclosure to the application, since the application without the enclosure will

also be placed in the Public Document Room.

If we do not near from you in this

regard within the specified period, the report will be placed in the Public

Document Room.

.g

Should you have any questions concerning this inspection, we will be pleased

to discuss them with you.

Sincerely,

,/l'W/ i

L'-

W.C.Seid\\e, Chief

Reactor Construction and

Engineering Support Branch

Enclosure:

IE Inspection Report No. 50-445/Rpt. 81-01

50-446/Rpt. 81-01

cc: w/ enclosure

Texas Utilities Generating Company

ATTN: Mr. H. C. Schmidt, Project Manager

2001 Bryan Tower

Dallas, Texas 75201