Confirms 810304 Mgt Meeting at Facility to Discuss Regulatory Performance.No Response Required.Agenda Encl
ML19347C835
Person / Time
Site: Pilgrim
Issue date: 02/06/1981
From: Grier B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Howard J
BALTIMORE GAS & ELECTRIC CO.
References
NUDOCS 8103100030
Download: ML19347C835 (2)


Text

6 a

b

/ "*%

UNITED STATES 4g g,

4g NUCLEAR R EGULATORY COMMISslON g*

j REGION I g

$31 PARK AVENUE KING OF PRUS$5 A, PENNSYt.V ANI A 19406 FEB 0 61981 Doci et No. 50-293 w

Boston Edison Company M/C Nuclear y

4 s

ATTN:

J. E. Howard

/g y-L, Vice President - Nuclear

.q FEB2'q 19815

-_g 800 Boylston Street Boston, Massachusetts 02199 t

u.s j

Gentlemen:

y

/s. -

Subject:

Management Meeting K.*

This letter confirms our plans for a management meeting to be held at Pilgrim Nuclear Power Station at 1:30 p.m. on March 4,1981, to discuss the regulatory performance of your facility as noted in the enclosed agenda.

Arrangements for this meeting were made during discussions with Mr. R. Machon of your staff on January 13, 1981.

No reply to this letter is required; however, if you should have any questions concernir.g this meeting, we will be pleased to discuss them with you.

Sincerely, m1711 Offan yce H. Grier f & ector

Enclosure:

Agenda for Boston Edison Company Management Meeting cc_w/ encl:

R. Machon, Nuclear Operations Manager - Pilgrim Station A. Morisi, Nuclear Operations Support Manager C. Mathis, Deputy Nuclear Operations Manager

""*m 9

ENCLOSURE AGENDA FOR BOSTON EDISON COMPANY MEETING MARCH 4, 1981 I.

Arrive on Site - 9:00 A.M.

II.

Facility Tour - 9:30 - 11:30 A.M.

III.

Lunch IV.

Opening Remarks - 1:30 P.M.

B. Grier, Director USNRC, Region I V.

Discussion of Evaluation Topics -

J. Johnson, Senior Resident - Inspector a.

Enforcement History b.

Inspection Findings c.

Reportable Events d.

Performance Evaluation T. Martin, Chief, Reactor Projects Section #3, Region I Overall effectiveness and attitudes of personnel e.

in complying with NRC regulatory requirements to assure safe operation E. Brunner, Chief, Reactor Operations and Nuclear Support Branch, Region I f.

Proposed regional followup actions VI.

Closing Remarks B. Grier, Director, Region I 1