a ug
UNITED STATES
8
n
NUCLEAR REGULATORY COMMISSION
,
$
nE
REGION ll
101 MARIETTA ST.. N.W., SUITE 3100
ATLANTA. GEORGIA 3o303
- ..+
In Reply Refer To:
RII:BRC
50-364/80-33
Alabama Power Company
ATTN:
R. P. Mcdonald
Vice President-Nuclear Generation
P. O. Box 2641
Birmingham, AL 35291
Gentlemen:
.
This refers to the inspection conducted by B. R. Crowley of this office on
August 25-27, 1980, of activities authorized by NRC Construction Permit No.
CPPR-86 for the Farley facility, and to the discussion of our findings held with
W. G. Hairston at the conclusion of the inspection.
Areas examined during the inspection and our findings are discussed in the
enclosed inspection report.
Within these areas, the inspection consisted of
selective examinations of procedures and representative records, interviews with
personnel, and observations by the inspector.
We have examined actions you have taken with regard to previously reported
unresolved items.
The status of these items is discussed in the enclosed
report.
During the inspection, it was found that certain activities under your license
appear to be in noncompliance with NRC requirements. This item and references
to pertinent requirements are listed in the Notice of Vio'lation enclosed herewith
as Appendix A.
This notice is sent to you pursuant to the provisions of Section
2.201 of the NRC's " Rules of Practice," Part 2, Title 10, Code of Federal Regula-
tions. Section 2.201 requires you to submit to this office, within-20 days of
your receipt of this notice, a written statement or explanation in reply including:
(1) corrective steps which have been taken by you and the.results achieved; (2)
corrective steps which will be taken to avoid further noncompliance; and (3) the
date when full compliacce will be achieved.
In accordance with Seucion 2.790 of the NRC's " Rules of Practice," Part 2,
Title 10, Code of Federal Regulations,
a copy of this letter and the enclosed
inspection report will be placed in the NRC's Public Document Room.
If this
report contains any information that you (or your contractor) believe to be
proprietary, it is necessary that you make a written application within 20 days
to this office to withhold such information from public disclosure. Any such
application must include a full statement of the reasons on the basis of which
it is claimed that the information is proprietary, and should be prepared so
that proprietary information identified in the ' application is contained in a
separate part of the documen .. If we do not hear from you in this regard within
the specified period, the report will be placed in the Public Document Room.
8 012020 goo
..
.
-
.
5
SF P 181980
Alabama Power Company
-2-
,
Should you have any questions concerning this letter, we will be glad to discuss
them with you.
Sincerely,
h)
2"
7
C. E. Murphy, Chief
Reactor Construction and Engineering
Sunport Branch
Enclosures:
1.
Appendix A, Notice of Violation
2.
Inspection Report No. 50-364/80-33
cc w/ enc 1:
A. R. Barton, Executive Vice President
II. O. Thrash, Manager, Nuclear Generation
F. L. Clayton, Jr. , Senior Vice President
W. C. Petty, Manager-Quality Assurance
(Design and Construction)
W. G. Hairston, III, Plant Manager
R. E. Hollands, Jr. , QA Supervisor
O. D. Kingsley, Jr. , Man;ger, Nuclear Engineering
and Technical Services