ML19344F517

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-458/80-06 on 800609-10,24-27 & 30 & 0703. Noncompliance Noted:Failure to Follow Procedures for Identification of Training Needs & Use of Air Entrainment Admixture in Category 1 Concrete
ML19344F517
Person / Time
Site: River Bend 
Issue date: 07/25/1980
From: Beach A, Gilbert L, Tomlinson D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML19344F502 List:
References
50-458-80-06, 50-458-80-6, NUDOCS 8009150357
Download: ML19344F517 (11)


See also: IR 05000458/1980006

Text

l

-

U. S. NUCLEAR REGULATORY COMMISSION

--

0FFICE OF INSPECTION AND ENFORCEMENT

REGION IV

_

(This Report Contains Investigative

Information in Paragraph 7)

Report No. 50-458/80-06

Docket No. 50-458

Category A2

Licensee:

Gulf -States Utilities

Post Office Box 2951

Beaumont, Texas 77704

Facility Name:- River Bend, Unit No. 1

Inspection'ti ~ River Bend Site

a

Inspection conducted- June'9-10, June 24-27 and June 30-July 3, 1980

Inspectors:

l$

IV L

7/2dM

A. BT Beach, Reactor Inspector, Engineering

'Da t'e

Support Section (Paragraphs 1, 2, 5, 6, 7 & 8)

(June 9-10, June 24-27, and Jane 30-July 3, 1980)

"- ?

7/2 S/96

L. D. Gilbert, Reactor Inspector, Engineering

' Dat'e

Support Section (Paragraph 3)

(June 24-27, 1980)

[A

7-7.6-80

. P. 'Ibrifnson~, Reactor Inspector, Engineering

Date

Support Section (Paragraph 4)

(June 24-27, 1980)

Other Accompanying

Personnel: W. G. Hubacek, Reactor Inspector, Projects

<

Section (June 9, 1980 Interview)

'

8009150 3 6 [

.

.

r:-

.

P. G. Wisco, Nuclear Technologist,'Phillipine

Atomic' Energy Commission

(June 24-27, 1980)

Reviewed:

W

7/Jf')[d

C. R. Oberg, Reac

Inspector, Projects Section

Date

Approved:

7/bf/[O

W.A.Crossman,Chp,ProjectsSection

Date

,

7

!8

... (::C'

e

R.. E. H'all,. Ch'ief,. Engineering Support Section

/ Date

Inspection Summary:

.

.

Inspection on June 9-10, June 24-27 and June 30-July 3, 1980 (Report 50-458/80-06)

Areas Inspected: Routine, unannounced inspection of the reactor containment

vessel welding and NDE, concrete placement activities, and training of construction

personnel. Allegations regarding inadequate training and rejecteu material

in concrete were investigated. The inspection involved one hundred thirteen

.

hours by four NRC inspectors.

Results:

In the areas inspected, one apparent item of noncompliance and one

deviation were found (infraction - failure to follow procedures for the identi-

fication of training needs, paragraph 6; and deviation-use of air-entrainment

admixture in Category 1 concrete, paragraph 5.c.).

i

s

%

d

2

-

r.:

~

~'l

.

DETAILS

1.

Persons Contacted

Principal Licensee Employees

  • T. C. Crouse, Director, Quality Assurance (QA)
  • C. L. Ballard, QA Engineer
  • R.-R. Doggart, QA Engineer
  • K. C. Hodges, QA Engineer
  • R. W. Helmick, GSU Construction
  • J. W. Leavines, Assistant Project Engineer
  • J. Hudson, QA Engineer
  • R. B. Stafford, Supervisor QA
  • W. S. Stuart, QA Engineer
  • M. G. Walton, Nuclear Staff Analyst
  • J. P. Cook, Nuclear Training

J. E. Wimberly, Superintendnet, Site Construction

Stone and Webster Employees

  • R. L. Spence, Superintendent, Field Quality Control (FQC)
  • J. D. Davis, Assistant Superintendent, FQC
  • A. J. Losso, Superintendent of Engineering
  • J. E. Roskoph, Assistant Superintendent of Engineering
  • A. Kamdor,. Resident Engineer

C. D. Lundin, Project QA Manager

  • J. J..Zullo, QA Engineer
  • L. W. Lewis, FQC Training Engineer
  • R. E. Hogan, Training Supervisor
  • H. D. Laford, General Superintendent

W. I.LClifford, Resident Manager, Construction

.

W. Hathaway, Senior Welding Supervisor

J. Howard, Chief Inspection Supervisor

P. West, QC Inspector

Graver Employees

  • L. Sutton, Site Senior QA Engineer

H. Bunn, Surveillance Supervisor

C. Carr, QA Engineer

.

C. McPherson, Welding Inspector

'The IE inspectors also talked with and interviewed other licensee and

contractor employees during the course of the inspection.

  • Denotes those present at the exit interview.

3

t

.-

--

'

.

,

2.

Site Tour.

(

The IE inepe: tors walked through the various areas to observe the general

progress of construction activities.

Concreting form work activities were

-

observed,'as well as the installation of structural steel and general

-housekeeping activities.

No~ items of noncompliance or deviations were identified.

.3.

Reactor Containment Vessel-Welding

a.

Review of Procedures

The IE inspector reviewed Revision 2 of the Graver Nuclear Qua:.ity

Assurance Manual.

In the areas reviewed, the QA Manual was consistent

with the eighteen Criteria of Appendix B to 10 CFR Part 50.

Two of the Graver Welding Procedure Specifications (WPSs) and support-

ing Procedure Qualification Reports (PQRs) were reviewed with no "

'

discrepancies noted from the requirements of the Stone & Webster

Containment Specification- 219.710, Revision 2 and Addenda 2, including

ASME B&PV Code, Sections III (NE) and IX, 1974 edition.

The WPSs

and PQRs reviewed were:

WPS 308N, Revision 9, Procedure Specification for Submerged

Arc Welding

PQR S116, Qualification for WPS 308N

WPS 305N, Revision 8, Procedure Specification for Shielded

Metal-Arc Welding

PQR'176~, Qualification for WPS 305N

_

i

PQR 218, Qualification for WPS 305N

'

PQR SM235, Qualification for WPS 305N

PQR SM241, Qualification for WPS 305N

PQR SM 259, Qualification for WPS 305N

PQR SM 173, Qualification for WPS 305N

b.

Observation of Welding Activities

The IE inspei. tor observed welding activities associated with fillet

welding both horizontal and vertical stiffeners to the cylindrical

portion of the free-standing containment vessel. The weld joints

observed are listed below:

4

'

E

.

.

_ .

,

F

.

,

,

<

\\

'-

3

-

Joint Number

Erection Control Number

HAl'

CCS6-001 Sub-A.

. HA2

CCS6-002 Sub-A-

C-28

CCSS-046 Sub-C Row 3

' C-33-

CCSS-051 Sub'-C Row 3

-The stiffeners were welded'using electrode. type E7018 in accordance

with'WPS 305N.' The E7018 electrode was traced to material test reports

which conformed to the chemical and mechanical requirements of ASME

1

B&PV Code,Section II, Part C.

The heat and lot-numbers.for the elect-

rode inspected were:

Heat Number

Lot Number

.-432H4732 .

..

w

.

._ .

03-1-H907L

.

412J7261

~ "

3A003P06

421J9781

2A007T02

The IE inspector observed the qualification testing of three Graver

.

l

' welders and reviewed documentation for: performance testing of twelve

,

other Graver welders including the welders working on the stiffener

fillet welds identified above.

In the areas inspected, no discre-

,

J

pancies with the requirements of ASME B&PV Code,Section IX were noted.

<

No,i.tems.of noncomplianc.e or. deviations were identified.

.

.

<

- 4.

Reactor Containment Vessel-NDE ~

-'

'

a.

Review of Procedures

.

The IE inspector reviewed the. following Graver Corporation NDE pro-

cedures for compliance with site SAR commitments and the require-

ments of the ASME BVPV Code, Section V:

LPE-9 and LPE-9A.

-Liquid Penetrant Examination

'

MPE-9 and MPE-9A thru C Magnetic Particle Examination

UE-9 and'UE-9A

Ultrasonic Examination

.

RE-9 and RE-9A

Radiographic Examination

-

UE-9

Visual Examination

,

= ,

,

5

_

7~

T

4'

y

w-

w+7-g

y

.y:

w

y

-qv-

ey-y,

yg--ye-%wq

y-

.g7T'

+W

r---

"T

.

-

.

.

-

.-.

-

-

--

'

,

I

The IE inspector also' reviewed the personnel qualification and certi-

fication' records for twenty-three Graver on-site inspectors to assure

compliance withlthe requirements of SNT-TC-1A. Educational records

-and records of experience were checked-along with records of test

scores and the results of current visual' acuity examinations.

4

.The IE. inspector reviewed the-calibration records for all on-site

magnetic particle examination equipment as well as the calibration

'

records for other inspection equipment such as depth gauges and

pyromecers.

No' deviations or items of noncompliance were identified.

b.

Observation of Activities

' I

The IE~ inspector witnessed the magnetic particle examination of sev-

eral areas of the outer dry well wall.

These were. areas where the

i

removal of alignment attachments necessitated the inspections on

Rings 9 and 10.

Traveler yackages and inspection documentation were

j

checked to assure that the scope of work requirements were complete

,

and that proper dispositior. was made of'the-results.

Liquid penetrant examination was witnessed on areds of attachment

removal on Rings 4 and 5 of the outer drywell wall.

Batch numbers

of each of the materials used for this inspection were checked against

i

-the manufacturer's certification of contents to assure compliance with

>

the maximum sulfur and halogen content requirements of the Code.

]

One radiography setup was witnessed on the horizontal weld joint

between Rings 1 and 2 of the free-standing containment vessel.

Radiography was required on a repaired area between one-foot markers

21 and 22.

All film identification, penetrameter selection and

~

placement,' film placement and radiation protection barriers were

-in accordance with approved procedures.

No deviations or items of noncompliance were identified.

c.

Review of Records

,

r

The IE inspector reviewed Graver records of NDE performed on the

free-standing containment vessel horizontal selds for Rings 1-2-3

and'4-5-6.

Records were also checked for vertical welds 2-V-2 and

2-V-10.

Records for inspection, repairs, welding materials and

welder's qualification appeared to be in accordance with the ASME

-Code and Graver documentation procedures.

A review was performed

^

of all . radiographs produced on containment vessel vertical joints

!

2-V-2,.2-V-6 and-2-V-10.

All radiographs exhibited acceptable

j

density, proper placement of identification and correct penetrameter

~

selection.

Original radiographs'and repair shots were reviewed and

interpretations compared with the Graver radiographic result sheets.

All final radiographs appeared to meet the minimum ASME Code require-

4

ments,for weld acceptability.

U

6

.

,

- . - , . .

. - -

.,.y

-

- ~ . ,

.-

,----n_-2

n ~

.

- . .

,

No deviations or items of' noncompliance were identified.

5.

Concrete Placement Activities

-

a.

_Stop-Work Order Issued by GSU on Category I Concrete Placements

On June 22, 1980, a Stop-Work Order was issued by Gulf. States Utilities

for all concreting activities'in Category I structures.

The reason

for the work being. terminated involved " form-work faiiures and apparent

- lack of supervision of concrete placement personnel." The specific

placements referenced in the Stop-Work Order were CBS-W-9411-2 and

CBS-W-94D2 as documented on QAFR 80-6-22-E.

Gulf States Utilities, in a letter RBG-7871, dated June 23, 1980,

directed Stone and Webster to'take specific corrective action before

the Stop-Work Order would be released. The following areas were

addressed for corrective action:

'(1) Allowable concrete placement rates to accomodate the form design.

(2)- Proper vibration techniques during concrete placements.

(3) Procedures for form design and form installation.

(4) Retraining of craft and personnel supervisors.

(5) Procedures for actions to L- .aken on all unplanned construction

joints.

(6) Weather protection procedures to be used during concrete place-

ments.

(7)~ Preplacement meeting effectiveness.

~(8) Field Quality Control (FQC) inspection requirements.

As a result of the Stop-Work Order, the IE inspector toured the

construction areas to observe the areas referenced in QAFR 80-6-22-E.

Observations in the field and discussions with licensee and contractor

personnel. revealed that form displacements had been a~ recurring

deficiency, but proper corrective action to correct the deficiency

had not been taken. -The following form displacements were field

reviewed by the IE inspector:

-Placement Number

Form Displacement Documentation

Date

CB3-W-8515

N&D 4580-1

4/28/80

,

ET5?W-85J6-2-3898

1RS0002011

4/23/80

AB3-W-83P4

N&D 9636

5/24/80

7

  1. 1

,

.

.

-,

.

- . . - - - --

_

_ _ -

- , . - , -

.

,

>:

~

.

.

~ Placement Number

' Form Displacement Documentation

Date-

-

ET5-W-85J6-14136

1RS0002833.

6/5/80

ABS-W-83P4

N&D 9746

6/17/80

.

Stone.and Webster, in.their response to GSU, addressed appropriate

corrective action to the eight areas of concern referenced above.

This-is-documented in their letter of June 27, 1980, C-RBS-01468.

In~ addition, the letter also states that the Project QA Manager.will

hold a meeting, on at least a. monthly basis, "to determine courses

of action'on recurring deficiencies," and to assign responsibilities

for taking proper corrective action.

In addition, the.IE inspector attended a " Form-work and Concrete Place-

ment. Workshop" on. June 26,:1980. The basic purpose of this workshop

was to familiarize carpenter and concrete supervisors with the follow-

ing new procedures:

,

CSI 3.0.2

" Inclement Weather Protection During Concrete

Placement."

CSI 3.0.3

" Unplanned Construction Joints."

CSI 3.3.4

" Concrete Form Alignment."

An explanation of the stop work action was also given, and after this

workshop,-GSU-rescinded the Stop-Work Order.

No items of noncompliance or deviations were identified.

b.

Batch Plant and Site Test Lab Tours

The IE inspector toured the site batch plant facility.

Cement and

aggregate storage facilities were observed, and Cement Mill Test Reports

were reviewed.

Preplacement preparations for concreting were also

~ observed.

The'IE-inspector toured the site test lab facility, and observed test-

ing activities in process. The correlation between ASTM C138, " Unit

Weight, Yield, . 2d Air Content (Gravimetric) of Concrete," and ASTM

C567," Unit Weight of Structural Lightweight Concrete," was being

.

. developed'for concrete mixes' currently being used at the site.

This

correlation assures that-the concrete density exceeds the minimum

requirement of 135 pcf, and establishes the accept / reject criteria for

the ASTM C138 tests. At the conclusion of this inspection, these

test results were not available.

From the records review and the activities observed, no items of

noncompliance or deviations were identified.

8

.

@

.

-

-

,

-

-

g

m,

_ I=;

, -

'!?

.

~

'

-

'

c'. -

Review of Concrete' Placement Records

>

'

The IE inspector reviewed previous concrete placements to assure that.

.the' requirements of the. construction specification were being' met.

Slump results,1 unit weight tests, compressive strength tests and. air

content ~ test results'were reviewed. ~Specifically, the following con-

-

creta= placement records were examined for the test .results referenced

above:

+

Placement

~Date

'

AB2-M-70N5-

-1/23/80

.

'AB1-M-70E5

1/26/PO

AB2-M-70JS

2/'!/80

' B2-M-70N3

3/3/80

_

,

,

AB3-W-83N5

4/19/80

,

ET3-M-66G1

4/8/80-

.

CB1-M-70J1

1/3/80-

ETi-M-6666

1/6/80

' During this - review, the IE inspector noted that the requirements for -

_

air, content were either 5% j- lis% or 0%

' 6%.

Further inspection revealed -

that a ispecification change E&DCR C-75 (dated November 29, 1979)

Construction- Specification 210.'350, '.' Specification for Mixing and

Delivering-Concrete," deleted the min 4=n= total air content require-

"

ment 'for~ structures below' the' frost 'line and interior walls above the -

'

frost line. Air content for concrete in all other Category'1 structures

shalll conform to ACI 301,;" Specifications for Structural Concrete,"

. Table 3.4. ~For concrete mixes"usin'g #57 coarse aggregate, which

were.used in most of the above placements, : the . air content limits

would' be 3.5% - 6.5%.

- All Category 1: structures placed up until the time of this inspection

have been placed below th'e frost line.

Therefore, by specification

change-:E&DCRlC-75,~the allowable-air content limits for concrete

placements would be 0% - 61%.

5

^

The River Bend PSAR,1in L Section 3.8.4.6, requires that concrete. used

in seismiciCategory 1 structures shall' contain an air-entraining . agent

in 'an amount sufficient to satisfy ACI 301-72, Table 3.4, " Total Air

. Content For Various Size of: Coarse Aggregate For Normal Weight ' Concrete,"

However, since many of-;the' total- air.. content valves - for the concrete

Lplacements reviewed were below 3.5%:(total air content value's for

AB1-M-70E5 were as low as 1.9%), the ' specification appears to deviate

from the PSAR. committment to othe total air content values in Table 3.4

_

of.ACI 301-72..

I

(This;istconsidered a deviation.

-_

.s

' -

9

.

_

,

. .

.

.

'

.

6.

Training of Construction Personnel

The IE inspector reviewed records and held discussions with licensee and

contractor personnel concerning construction training.

The Training Pro-

cedure CNN-9.1, " Construction Training Program," was reviewed to ascertain

whether or not the objectives of the construction training program were

being met.

Section 5.5 of this procedure requires that each supervisor be responsible

for identifying construction training needs to the Construction Training

Supervisor.

However, the Construction Training Supervisor stated that the

procedure was to be revised.to take this responsibility away from the

Supervisor and to make it the responsibility of the Construction Training

Supervisor.

He also stated at the time of this inspection, there was no

effective way to identify individual training needs until the Computerized

Training Record System (CTRS) is developed. The only records currently

available are the Training Attendance Sheets. Thus, it is essentially

impossible for each supervisor to be aware of each individuals specific

training needs.

A.GSU Audit MAC-79-F055, Rev. 1, dated February,1980, stated that, "the

Construction Training Supervisor was unable to present, in prompt fashion,

the training files for a basic construction course." Stone and Webster,

in their response, stated that the construction training files were in the

process of being reorganized and that a computer system was being developed.

An audit performed by the Stone and Webster Headquarters Construction

Training Group during May 28-29, 1980, further identified that the CTRS

program had not been implemented. Thus, since no records were available to

show that training needs were being identified and that there was no

effective method to determine training needs, this is considered to be

an item of noncompliance v;th Criterion V of Appendix B to 10 CFR 50; i.e.,

failure to follow procedural requirements for the identification of

construction training needs.

As a result of this finding, Gulf States Utilities, in the letter RBG-7885,

dated June 26, 1980, directed Stone and Webster to develop and implement

a training status system which will reflect training status for all Stone

and Webster individuals employed at the River Bend Site within thirty days.

7.

Allegation Investigations

a.

Investigation Concerning Material Embedded In Concrete

During a labor relations meeting on February 19, 1980, an allegation

was made that certain material was embedded in concrete with a product

'" HOLD TAG" attached.

(HOLD TAG #04384).

A Stone and Webster investigation revealed that the product number in

question was determined to be a " Purchase Order Number" for Unistrut

10

I

F

^

^

~

in

,j

.

material rather than a Hold. Tag Number." " Hold Tag Numbers" are

-issued in numerical sequence, and the last number issued in February

1980.was in the 800-900. range.

.

A review of applicable ini,pection reports was conducted to determine

the amount of,Unistrut material received at the site, and all of the

Unistrut material was accounted for.

This allegation could not be substantiated.

b.

Investigation of an Allegation Concerning Lack Of Training of Personnel

~

at the River Bend Site

g

On' June 6,'1980, the Region IV Reactor Construction and Engineering

Support Branch Office received a call from-a former Stone and Webster

^

employee who stated that the training of personnel at the River Bend

site was not sufficient and was a safety defect.

On-June 9, 1980, two NRC Regional Reactor Inspectors interviewed the

individual at his home to obtain additional information concerning

the allegation. The basic allegation referenced a large number of

Stone and Webster personnel working on site who had not received new

hire orientation, " Job Safety and Work Rules."

Prior to May 2,1980, there were no procedural requirements for

employees who were performing safety-related activities to receive

new hire orientation. Stone and Webster, in their letter of May 2,

-

1980, RBS-4971, now requires that all craft' personnel receive site

and safety orientation as well as craft indoctrination training.

A review of training records for May and June of 1980 revealed that

the orientation and indoctrination classes were being held as required,

and an effort was being made to give these classes to those employees

already working at the site. ~However, as referenced in paragraph 6,

since at the present time there is no effective method to determine

an individual's training needs, there may still be some employees

who have not received new hire orientation training; however, since

this training was.not a requirement, no deficiency was found.

Even though this allegation was partially substantiated, it has no

merit.

8.

Exit Interview

The IE inspectors met with the licensee representatives (denote'd in paragraph

1) at the conclusion of the inspection on July 3, 1980. The IE inspectors

summarized the scope and findings of the-inspection.

D

,