Forwards IE Insp Rept 50-346/80-25 on 800818-22,25-29,0902- 05,08-12 & 15-19 & Notice of Violation
ML19343A884
Person / Time
Site: Davis Besse 
Issue date: 10/15/1980
From: Heishman R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Crouse R
TOLEDO EDISON CO.
Shared Package
ML19343A886 List:
References
NUDOCS 8011240103
Download: ML19343A884 (2)


See also: IR 05000346/1980025

Text

.

.

rNeeg

i

UNITED STATES

o

!"

NUCLEAR REGULATORY COMMISSION

'

.#

REGION ill

c

,

799 ROOSEVELT ROAD

f

o

GLEN ELLYN. (LtlNOls Go137

'

% .V

j'

...

E15 30

M

-

Docket No. 50-346

.5

3

li

Toledo Edison Company

[

Gj

ATTN:

Mr. Richard P. Crouse

N

g

Vice President

M

Nuclear

_,

.1

93

Edison Plaza

-

'

4

300 Madison Avenue

3

,,

a

i

Toledo, OH 43652

>

z

w

_

Gentlemen:

This refers to the inspection conducted by Mr. L. A. Reyes and others of

this office on August 18-22, 25-29, September 2-5, 8-12, and 15-19, 1980,

of activities at the Davis-Besse Nuclear Power Station, Unit 1, authorized

by NRC Operating License No. NPF-3 and to the discussion of our findings

with Mr. T. Murray at the conclusion of the inspection.

The enclosed copy of our inspection report identifies areas examined during

Within these areas, the inspection consisted of a selective

the inspection.

examination of procedures and representative records, observations, and

interviews with personnel.

During this inspection, certain of your activities appeared to be in non-

compliance with NRC requirements, as described in the enclosed Appendix A.

Regarding the item of noncompliance, our concern is not so much with your

use of revision 9 rather than revision 10 of Procedure SP 1104.02, since

there is not that much difference between the two revisions; rather, our

concern is with the practice of your control room operators maintaining

in the control room for their use a file of " uncontrolled" copies of

This

certain procedures used routinely during plant startup and shutdown.

Your response to

practice was directly responsible for the noncompliance.

the noncompliance should address this concern.

In addition to the above, we are concerned with your failure to submit

a timely proposal requesting changes to your Technical Specifications to

reflect recent TECo organizational changes.

In your response to this

letter, please indicate your schedule for submittal.

l

This notice is sent to you pursuant to the provisions of Section 2.201 of

the NRC's " Rules of Practice," Part 2, Title 10, Code of Federal Regulations.

Section 2.201 requires you to submit to this office within twenty days of

your receipt of this notice a written statemen' or explanction in reply,

including for each item of noncompliance:

(1) corrective action taken and

the results achieved; (2) corrective action to be taken to avoid further

noncompliance; and (3) the date when full compliance will be achieved.

8013240/03

,

'

h

_ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

_ _

__

.

.

.

.

.

Toledo Edison Company

-2-

'

I-

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,

Title 10, Code of Federal Regulations, a copy of this letter and the en-

closed inspection report will be placed in the NRC's Public Document Room,

except as follows.

If this report contains information that you or your

contractors believe to be proprietar. ,

must apply in writing to this

office, within twenty days of your receip of this letter, to withhold such

information from public disclosure. The application must include a full

statement of the reasons for which the information is considered proprietary,

and should be prepared so that proprietary information identified in the

application is contained in an enclosure to the application.

We will gladly discuss any questions you have concerning this inspection.

Sincerely,

R. F. Heishman, Chief

Reactor Operations and

Nuclear Support Branch

Enclosures:

1.

Appendix A, Notice

of Violation

2.

IE Inspection Report

No. 50-346/80-25

cc w/encis:

Mr. T. D. Murray, Station

Superintendent

Central Files

Reproduction Unit NRC 20b

AE0D

Resident Inspector, RIII

PDR

Local PDR

NSIC.

TIC

Harold W. Kohn, Power-

Siting Commission

Helen W. Evans, State

of Ohio

RIII

RIII

Warnick/np

Hei

10/9/80

/'

/(//5/rt

.