p tstoq
[l0
~
+
/
h
UNITED STATES
'*
$*38" h(f)I'3
NUCLEAR REGULATORY COMMISSION
q
n
E
REGION 11
$
'
2
ed
- '
f
101 MARIETT A ST., N.W., SUITE 3100
- n
,
i-
ig
/
ATLANT A, GEORGIA 30303
Q
4....
__
<a
os
a>
.
3
In Reply Refer To:
OCT 0 81980
- y
,"
,
rip BRC
y
7
NJ
A0-424/80-13
73
'
~
U O-425/80-13 ' )
M
2
u
-.
u>
_
Gebrgia Power Company
ATTN:
J. H. Miller, Jr.
Executive Vice President
270 Peachtree Street
Atlanta, GA 30303
Gentlemen:
This refers to the inspection conducted by B. R. Crowley of this office on
September 15-18, 1980, of activities authorized by NRC Construction Permit Nos.
CPPR-108 and CPPR-109 for the Vogtle facility, and to the discussion of our
findings held with H. H. Gregory, III at the conclusion of the inspection.
Areas examined during the inspection and our findings are discussed in the
enclosed inspection report.
Within these areas, the inspection consisted of
selective examinations of procedures and representative records, interviews with
personnel, and observations by the inspector.
Within the scope of this inspection, no items of noncompliance were disclosed.
One new unresolved item resulted from this inspection and is discussed in th'e
enclosed report. This item will be examined during subseq'ient inspections.
In accordance with Section 2.790 of the NRC's " Rules of Practice", Part 2,
Title 10, Code of Federal Regulations, a copy of this letter and the enclosed
inspection report will be placed in the NRC's Public Document Rc
If this
report contains any information that you (or your contractor) be.
'e to be
- proprietary, it is necessary that you make a written application withu. :'O days
to this office to withhold such information from public disclosure. Ar.y such
application must include a full statement of the reasons on the basis of which
it is claimed that the information is proprietary, and should be prepared so
that proprietary information identified in the application is contained in a
separate part of the document. If we do not hear from you in this regard within
the specified period, the report will be placed in the Public Document Room.
Should you have any questions concerning this letter, we will be glad to discuss
them with you.
Sincerely,
C. E. Murphy, Chi
Reactor Construction and Engineering
Support Branch
Enclosure: (See Page 2)
l
8011210
g
r
-
a
OCT 0 8 u8a
Georgia Power Company
-2-
.
a
Enclosure:
Inspecti,a Report Nos. 50-424/80-13
and 50-425/80-13
cc w/ encl:
K.-M.
Gillespie, Construction
Project Manager
E. D. Groover, QA Site Supervisor
D. E. Dutton, Project General Manager
l
1
l