Forwards IE Insp Rept 50-334/80-14 on 800519-23.No Noncompliance Noted
ML19343A460
Person / Time
Site: Beaver Valley
Issue date: 07/18/1980
From: Brunner E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Dunn C
DUQUESNE LIGHT CO.
Shared Package
ML19343A461 List:
References
NUDOCS 8009180001
Download: ML19343A460 (2)


See also: IR 05000334/1980014

Text

Y&

=

,

[ "Dig

UNITED STATES

NUCLEA3 REGULATORY COMMISslON

e

.

f

REGION 1

  • i

g

631 PARK AVENUE

KING Ofr PRUSSI A. PENNSYLV ANI A 19406

+....

JUL 181980

Docket No 50-334

Duquesne Light Company

ATTN: Mr. C. N. Dunn

Vice President

Operations Division

435 Sixth Avenue

Pittsburgh, Pennsylvania 15219

Gentlemen:

Subject:

Inspection No. 50-334/80-14

This refers to the inspection conducted by Mr. G. Napuda of this office on May

19-23, 1980 at the Beaver Valley Power Station, Unit 1 site in Shippingport,

Pennsylvania of activities authorized by NRC License No. DPR-66 and to the

discussions of our findings held by Mr. Napuda with Mr. J. A. Werling and other

members of your staff at the conclusion of the inspection.

Areas examined during this inspection are described in the Office of Inspection

and Enforcement Inspection Report which is enclosed with this letter. Within

these areas, the inspection consisted of selective examinations of procedures

and representative records, interviews with personnel, and observations by the

inspector.

Our inspector also verified the steps you have taken to correct the item of

noncompliance and deviation brought to your attention in a letter dated November

23, 1979. We have no further questions regarding the steps you took to correct

noncompliance Item E and the Deviation.

Within the scope of this inspection, no items of noncompliance were observed.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2, Title

10, Code of Federal Regulations, a copy of this letter and the enclosed inspection

report will be placed in the NRC's Public Document Rnom.

If this report contains

any information that you (or your contractor) believe to be proprietary, it is

necessary that you make a written application within 20 days to this office to

withhold such information from public disclosure.

Any such application must be

accompanied by an affidavit executed by the owner of the infonnation, which

identifies the document or part sought to be withheld, and which contains a

statement of reasons which addresses with specificity the items which will be

considered by the Commission as listed in subparagraph (b) (4) of Section

2.790. The information sought to be withheld shall be incorporated as far as

possible into a separate part of the affidavit.

If we do not hear from you in

this regard within the specified period, the report will be placed in the Public

Document Room.

8009180 0 0

.

.

Duquesne Light Company

2

No reply to this letter is required; however, if you should have any questions

concerning this inspection, we will be pleased to discuss them with you.

Sincerely,

-

_m v

El

n J. Brunner, Chief

Rea tar Operations and Nuclear

Support Branch

Enclosure:

Office of Inspection and Enforcement Inspection

Report Number 50-334/80-14

cc w/ enc 1:

F. Bissert, Technical Assistant Nuclear

R. Washabaugh, QA Manager

J. Werling, Station Superintendent

G. Moore, General Superintendent, Power Stations Department

J. J. Carey, Director of Nuclear Operations

R. Martin, Nuclear Engineer

J. Sieber, Superintendent of Licensing and Compliance, BVPS