ML19343A055

From kanterella
Jump to navigation Jump to search

12-9-19 Email Transmitting Cover Letter for Request for Additional Information Westinghouse Electric Company Topical Report WCAP-16045-P-A, Addendum 2, Revision 0, and WCAP-16045-NP-A, Addendum 2, Revision 0 Updated Nexus Cross-Section Meth
ML19343A055
Person / Time
Site: Westinghouse
Issue date: 12/09/2019
From: Ekaterina Lenning
Licensing Processes Branch
To: Zozula C
Westinghouse
References
EPID L-2019-TOP-0026, WCAP-16045-NP-A, WCAP-16045-P-A
Download: ML19343A055 (1)


Text

From: Lenning, Ekaterina To: zozulact@westinghouse.com Cc: Hosack, Korey L; Maurer, Bradley F. (maurerbf@westinghouse.com)

Subject:

REQUEST FOR ADDITIONAL INFORMATION RE: WESTINGHOUSE ELECTRIC COMPANY TOPICAL REPORT WCAP-16045-P-A, ADDENDUM 2, REVISION 0, AND WCAP-16045-NP-A, ADDENDUM 2, REVISION 0, UPDATED NEXUS CROSS-SECTION METHODOLOGY Date: Monday, December 09, 2019 8:08:00 AM

SUBJECT:

REQUEST FOR ADDITIONAL INFORMATION RE: WESTINGHOUSE ELECTRIC COMPANY TOPICAL REPORT WCAP-16045-P-A, ADDENDUM 2, REVISION 0, AND WCAP-16045-NP-A, ADDENDUM 2, REVISION 0, UPDATED NEXUS CROSS-SECTION METHODOLOGY (EPID L-2019-TOP-0026)

Dear Ms. Zozula:

By letter dated June 26, 2019 (Agencywide Documents Access and Management System Accession No. ML19179A091), Westinghouse Electric Company (Westinghouse) submitted to U.S. Nuclear Regulatory Commission (NRC) WCAP-16045-P-A, Addendum 2, Revision 0, and WCAP-16045-NP-A, Addendum 2, Revision 0, Updated NEXUS Cross-Section Methodology, for review and approval. Upon the review of TR and completion of the closed audit conducted by the NRC staff on October 8 through October 9, 2019, at the Westinghouse office in Cranberry, PA, the NRC staff has determined that additional information is needed to complete the review. On December 5, 2019, Westinghouse, and NRC staff agreed that the NRC staff will receive your response to the enclosed second set of the Request for Additional Information (RAI) questions within 90 days of the receipt of RAIs.

Proprietary file containing RAIs will be transmitted to Brad Maurer, Westinghouse, via BOX shortly.

If you have any questions regarding the RAI questions, please contact me at 3014153151.

Sincerely, Ekaterina Lenning, Project Manager Licensing Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission