Forwards IE Insp Repts 50-440/80-29 & 50-441/80-27 on 801201-31.No Noncompliance Noted
ML19341D237
Person / Time
Site: Perry  FirstEnergy icon.png
Issue date: 01/26/1981
From: Fiorelli G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Davidson D
CLEVELAND ELECTRIC ILLUMINATING CO.
Shared Package
ML19341D238 List:
References
NUDOCS 8103050198
Download: ML19341D237 (2)


See also: IR 05000440/1980029

Text

. - . _ ~

__

-

.

_.

--

-

7/C

'

g* *C%

UNIT E D STATES

+1

'k

NUCLEAR REGULATORY COMMISSION

,

e

4

'j

REGION ill

D

799 ROOSEVELT ROAD

GLEN ELLYN, ILLINOIS 40137

.....

,JAN 2 6 i;61

.

/

uN

/

(T

I

n

/ ^ ,,(1jj'l f

tu,

G

Docket No. 50-440

'

[g

FEB 2 3 ;ggy n /f:

Docket No. 50-441

,

_

(6~~~

u.s, %w ,,N^ " f)

The Cleveland Electric Illu.ninating

  1. *"

Company

ATTN: Dalwyn M. Davidson

6

4,$

g* [\\

Vice President - System

4

Engineering and Construction

N L

Post Office Box 5000

Cleveland, Ol! 44101

Gentlemen:

,

i

This refers to the inspection conducted by Mr. J. Hughes of this office

on December 1-31, 1980, of activities at the Perry Nuclear Plant Project,

Units 1 and 2, authorized by NRC Construction Permits No. CPPR-148 and

No. CPPR-149 and to the discussion of our findings with Messrs.

M. R. Edelman and G. W. Croscup and others of your staff at the con-

clusion of the inspection.

The enclosed copy of our inspection report identifies areas examined

during the inspection. Within these areas, the inspection consisted of

a selective examination of procedures and representative records, obser-

vations, and interviews with personnel.

No items of noncompliance with NRC requirements were identified during

the course of this inspection.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part

2, Title 10, Code of Federal Regulations, a copy of this letter and the

enclosea inspection report will be placed in the NRC's Public Document

Room, except as follows.

If this report contains information that you

or your contractors believe to be proprietary, you must apply in writing

,

to this office, within twenty days of your receipt of this letter, to

vi~hhold such information from public disclosure. The application must

c

include a full statement of the reasons for which the information is

considered proprietary, and should be prepared so that proprietary

information identified in the application is contained in an enclosure

to the application.

8103050 %

__

__

-

-

_ _ _

.

--

_

.

The Cleveland Electric

-2-

3AN 2'6 f00*

Illuminating Company

We uill gladly discuss any questions you have concerning this

in.pection.

,

Sincerely,

-

B

b-

r'-6'.

Fiorelli, Chief

Reactor Construction and

Engineering Support Branch

Enclosures:

1.

IE Inspection Reports

No. 50-440/80-29

No. 50-441/80-27

cc w/encls:

Central Files

Reproduction Unit NRC 20b

P9R

Local PDR

NSIC

TIC

liarold W.

Kohn, Power

Siting Commission

Mr. Daniel D. Wilt, Attorney

IIelen W. Evans, State of Ohio

1

i