ML19340D880

From kanterella
Jump to navigation Jump to search
Interim Deficiency Rept Re Primary Containment Relief Valves at Facility,Initially Reported on 800326.Expected Conclusion of Investigation Has Been Postponed Until 801205
ML19340D880
Person / Time
Site: Hope Creek  
Issue date: 10/24/1980
From: Martin T
Public Service Enterprise Group
To: Grier B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
Shared Package
ML19340D876 List:
References
10CFR-050.55E, 10CFR-50.55E, NUDOCS 8101050497
Download: ML19340D880 (2)


Text

.

Thomas J. Martin Public Service Electric and Gas Company 80 Park Plaza Newark, N.J. 07101 201/4304316 vicapres.o.n Engineenng and Construction October 24, 1980 Mr. Boyce H. Grier, Director U. S. Nuclear Regulatory Commission Office of Inspection and Enforcement Region 1 631 Park Avenue King of Prussia, Pennsylvania 19406

Dear Mr. Grier:

PRIMARY CONTAINMENT RELIEF VALVES 10CFR50.55(e), POTENTIAL SIGNIFICANT DEFICIENCY NO. 1 UNIT HOPE CREEK GENERATING STATION On March 26, 1980 a verbal report was made to Region 1, Office of Inspection and Enforcement representative, Mr. A. Cerne advising a potential significant item re-garding the primary containment relief valves supplied by GPE Controls.

Supplemental information has been submitted in writing to Region 1, Office of Inspection and Enforcement, indicating that the analysis of this potential problem was continuing.

The most recent submittal was dated August 20, 1980.

The following is an interim report concerning the potential design deficiency in the primary containment relief valves, GPE Controls Model LD240-447.

This report is to establish that the expected conclusion of the investigation by October 24, 1980, indicated in previous correspondence concerning this subject, cannot be met.

The review of seismic calculations has not been l

l 8101050 ff 7

1 Boyce H. Grier

.2-10/24/80 conclusively resolved between GPE Controls and the Bechtel Power Corporation, our Architect Engineer.

The expected completion date of action is December 5, 1980.

PSE&G will respond to you at that time.

Very truly yours, f, I Y y

CC Office of Inspection & Enforcement Div. of Reactor Construction Inspection Washington, DC t