ML19339B044
| ML19339B044 | |
| Person / Time | |
|---|---|
| Site: | FitzPatrick |
| Issue date: | 10/29/1980 |
| From: | Stello V NRC OFFICE OF INSPECTION & ENFORCEMENT (IE) |
| To: | Berry G POWER AUTHORITY OF THE STATE OF NEW YORK (NEW YORK |
| Shared Package | |
| ML19339B045 | List: |
| References | |
| EA-80-044, EA-80-44, NUDOCS 8011060216 | |
| Download: ML19339B044 (2) | |
Text
.
L f b 4-b;,
UNITED STATES c.
NUCLEAR REGULATORY COMMISSION
.f j
WASHINGTON. D. C. 20555 e
OCT 2 9 E80 Docket No. 50-333 EA-80-44 Power Authority of the State of New York ATTN:
Mr. George T. Berry President and Chief Operating Official 10 Columbus Circle New York, New York 10019 Gentlemen:
Subject:
Inspection No. 50-333/80-06 We have received your letter dated September 12, 1980, which enclosed your Response to the Notice of Violation sent to you with our letter dated August 18, 1980.
The Notice of Violation accompanying our August 18, 1980 letter identified nineteen items of noncompliance found during a Nuclear Regulutory Commission inspection or. April 14-18, and April 23-25, 1980 of the implementa-tion of your physical security program at the James A. FitzPatrick Nuclear Power Plant, Scriba, New York.
During a Region I inspection conducted on August 18-22, 1980 (Office of Inspection and Enforcement Inspection Report No. 50-333/80-13), the corrective steps taken, the corrective steps p.> posed to avoid further items of noncom-pliance, and the results achieved to date, were reviewed and found to be in accorct with your Response dated September 12, 1980.
We have no further ques-tions regarding your actions in this regard at this time.
In our letter of August 18, 1980, we also requested that you address actions taken or planned to improve the effectiveness of the management of your physical security system.
You have responded adequately to this concern.
The measures undertaken by you to improve the security program management will be examined during subsequent inspections of your licensed program.
In your Response to the Notice of Violation enclosed with your letter dated September 12, 1980, it is admitted that each item of noncompliance occurred as stated.
Further, you chose not.to protest the proposed imposition of civil penalties by a written answer as permitted in Appendix B, Notice of Proposed Imposition of Civil Penalties, sent to you with our letter of August 18, 1980.
After careful review of this matter, we have concluded that there is no basis for mitigation.
Accordingly, we hereby serve the enclosed Order on the Power.
Authority of the State of New York imposing civil penalties in the aggregate amount of Forty.-eight Thousand Dollars.
CERTIFIED MAIL RETURN RECEIPT REQUESTED 8011060 2ff
Power Authority of the State of DCT 2 91980 New York In accordance with Section 2.790(d) of the NRC's " Rules of Practice," Part 2,
. Title 10, Code of Federal Regulations, control.and accounting procedures for safeguarding special nuclear materials and facility security measures for physical' protection are~ deemed to be commercial or financial information within the meaning of 10 CFR 9.5(a)(4) and are subject to disclosure only in accordance with the provisions of 10 CFR 9.12.
Therefore, the enclosure to your letter dated September 12, 3980 will not je placed in the.Public Document Room and will receive limited distribution.
Sincerely,
/s/
\\c Victor Stello, J.,
Director Office of Inspection and Enforcement
Enclosure:
Order Imposing Civil Monetary-Penalties cc w/ encl:
R. J. Pasternak, Resident Manager J. P. Bayne, Senior Vice President-Nuclear Generation A. Klausmann, Director, Quality Assurance M. C. Cosgrove, Site Quality Assurance Engineer J. F. Davis,. Chairman, Safety Review Committee C. M. Pratt, Assistant General Counsel G. M..Wilverding, Manager-Nuclear-Licensing M. J. Maltese, Director, Security and Safety e
a m.
w s.
==-..
4 A
-e
-