ML19339A120

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-440/80-16 & 50-441/80-15 on 800801-31. Noncompliance Noted:Inadequate Review of Fire Dampers
ML19339A120
Person / Time
Site: Perry  
Issue date: 09/17/1980
From: Julie Hughes, Williams C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML19339A115 List:
References
50-440-80-16, 50-441-80-15, NUDOCS 8011030093
Download: ML19339A120 (15)


See also: IR 05000440/1980016

Text

Oc

.

.

, .

U.S. NUCLEAR REGULATORY COMMISSION

.

OFFICE OF INSPECTION AND ENFORCEMENT

REGION III

Report Nos. 50-440/80-16; 50-441/80-15

Docket Nos. 50-440; 50-441

License Nos. CPPR-148; CPPR-149

Licensee: Cleveland Electrxc Illuminating Company

P. O. Box 5000

Cleveland, OH 44101

i

Facility Name: Perry Nuclear Power Plant, Units 1 and 2

Inspection At: Perry Site, Perry, OH

Inspection Conducted: August 1-31, 1980

[. [, Whhw

  1. .'

-

Inspector:

J. Hughes

/

't

h

  • WES E %

Approved By:

C. C. Williams, Chief

'7//7/h}

Projects Section 2

//~

'

!

Inspection Summary

Inspection on August 1-31. 1980 (Report No. 50-440/80-16; 50-441/80-15)

Areas Inspected: Routine inspection by the IE Regional Resident Inspector

(RI) of safety related construction activities, including welding of 4160

volt switchgear; concrete placement of Reactor Building vall; installation

of electrical conduit; containment spray brackets and records; and safety

related fluid system piping. This inspection involved 168 inspection hours

by one h3C inspector.

Results:

In the ten areas inspected, one item of noncompliance was identified

(deficiency: Units 1 and 2 - inadequate review).

,

8 011030 0$

1

-

-

__

.-

,

. . - . -

--

.

.

,

DETAILS

.

Persons Contacted

  • M. Edelman, Manager, Nuclear QA Department
  • G. Groscup, Manager, Nuclear Engineering Department

D. Fitzpatrick, Site Construction Manner

  • W. Kacer, General Supervising Engineer, CQS
  • J. Kline, General Supervising Engineer, Construction
  • B. Barkley, General Supervising Engineer, Design
  • P. Martin, General Supervising Engineer, PQS
  • R. Vondrasek, CQS QE. Supervisor

S. Tulk, CQS Electrical Quality Engineer

,

'

K. Combs, CQS Engineering Aide

Other Personnel

  • P. Gibson, CQS QC Supervisor (KEI)
  • T. Arney, QA Program Manager (GAI)

R. Crofton, CQS Lead Piping Quality Engineer (GAI)

J. Connelly, CQS Lead Civil Quality Engineer (GAI)

W. Ware, CQS Lead Civil Quality Engineer (GAI)

G. Parker, CQS Mechanical Quality Engineer (GAI)

l

K. Peck, Assistant Project Manager (GAI)

J. Small, QC Manager (Dick Corp.)

R. Love, QA Manager, (L.K. Comstock)

P. Wang, Laboratory Chief (UST)

L. Young, CQS Mechanical Quality Engineer (KEI)

The inspector also contacted and interviewed other licensee and contractor

personnel during this reporting period.

$

  • Denotes those attending at least one of the exit meetings.

l

Licensee Action on Previous Inspection Findings

(Closed) Unresolved Item (440/78-15-01; 441/78-14-01): Newport News

Industrial Corporation (NNIC) housekeeping in fuel cask area. During

this reporting period the inspector observed housekeeping in the fuel

cask area and found it to be adequate at this time.

(Closed) Unresolved Item (440/79-09-03; 441/79-09-03): Cable trays of

different divisions installed on same hanger support. The inspector

reviewed electrical drawings to determine separation criteria and to

note if fire barriers were going to be installed.

The inspector noted

that the drawings indicated that fire barriers were to be installed and

found it to be adequate at this time.

(Closed) Noncompliance (440/79-10-03; 441/79-10-03): US Testing (UST)

Procedure for qualification of inspection personnel does not meet the

-2-

__

.

.

,

1

intent of ANSI N.45.2.6-1973.

During this reporting period, the inspector

,

reviewed three personnel qualification records, licensee audit report #425

dated July 31, 1980, and the following U5'f procedures; QCP-9 Revision 4,

titled " Responsibilities and Required Qualification Levels of Personnel;"

,

'

QCP-6 Revision 2, titled " Training of Inspection and Test Personnel;" and

UST-TQ-1 Revision 10, titled " Training and Qualification of Inspection,

Test, and Audit Personnel." The inspector determined that the program was

being properly implemented and that the records reviewed did satisfy the

ANSI requirements.

.

(Closed) Unresolved Item (440/80-07-06; 441/80-07-06):

Great Lakes Con-

struction Company (GLCC) level II QC inspector filling out and signing

inspection reports for Level I who witnessed the soil field activities.

The inspector reviewed GLCC procedure No. T/QCP-8, Revision 6, " Excavation

and Backfill," dated May 22, 1980, which has been revised to reflect

changes. The GLCC Level I QC inspector initials the work forms and the

Level II reviews and signs off each daily report.

(Closed) Noncompliance (440/79-03-04; 441-79-03-04):

Newport News Indus-

trial Corporation (NNIC), improper verification signoffs on Manufacture

Installation Instructions (M/II's). The inspector reviewed NNIC's

Nonconformance Report (NR) No. 38-39 dated August 10, 1979, and licensee's

Action Request AR171 dated July 11, 1979 with attachments, and noted that

verification signoffs have been properly done.

Functional or Program Areas Inspected

1.

Plant Tours , Units 1 and 2

One or more plant areas were toured several times each week during

this reporting period to observe general construction practices,

area cleanliness, and storage / maintenance conditions of equipment,

piping, conduit, and cable trays.

One tour was made on back shift.

No items of noncompliance or deviations were identified.

2.

Observation of Concrete Work Activities and Related Quality Records,

Unit 2

Pre-Placement Inspection (RB2-WST4-639). The inspector performed

a pre placement inspection of Placement No. RB2-WST4-639 (reactor

l

building shield wall), containing approximately 47 cubic yards of

concrete and placed by Dick Corporation.

,

.

Placement Inspection (RB2-WST4-639).

a.

In Process Concrete Testing

(1) The United States Testing (UST) field QC personnel

performed slump, temperature, and entrained air tests

as follows:

.

-3-

.

.

,

Ticket No.

Slump (in.)

Temp ( )

% Ent. Air

,

49147

3-1/4"

67

6.5

49148

4"

66

---

49149

3-1/2"

65

---

49151

4"

69

---

All test results were within the allowed limits and performed

at the frequencies pecified.

(2) Field curing houses, which were suitably equipped to maintain

freshly cast compressive strength cylinders at the initial

curing temperature specified by ASTM C-31-69, were inspected.

(3) The inspector reviewed the calibration records for the

testing apparatus used on pour RB2-WST4-639, and found the

following equipment had current calibration data: air

meter #8, Unit weight bucket #3, field scale #15, and

thermometers #119, #136 and #204. Thermometer #119 was

found to be damaged during the first truck load sampling.

UST wrote a nonconformance report, #U3T ICAR #1027-31,

and replaced the thermometer with Nos. 136 and 204 which

were currently calibrated.

.

No items of noncompliance or deviations were identified.

3.

Delivery and Placement

Concrete was pumped to the placement area and deposited via

a.

a flexible hose which adequately confined the concrete, with

a maximum five foot free fall.

b.

Concrete was properly consolidated using internal concrete

vibrators numbers VIB-2, VIB-A1, VIB-3, and VIB-4, which

had been checked during operation to verify the 8000 VPM

frequency required by ACI-301-72, Chapter 8.

These checks

had been properly documented on the Dick Corporation

inspection report checklist as required by their procedure

FQC 10.2 Revision 6.

c.

The inspector reviewed Dick Corporation's documentaticn for

training of the craft in the use of vibrating techniques prior

to the concrete placement.

d.

The inspector observed the curing process of concrete placement

RB2-WST3-639.

No items of noncompliance or deviations were identified.

4.

Observation of Electrical Work Activities

a.

The inspector observed welding or the 4160 volt switchgear

cabinet, tag No. 1R22S006. Upon questioning L.K. Comstock's

-4-

.-

-. _

_.

.

-_

_

_ __

.

.

,

(LKC) QC inspector, it was learned that only four (4) welds

,

per cubicle were going to be welded. Vendor drawings 335198-

E226 thru E233 specify eight (8) plug welds to be made per

cubicle. The inspector could not determine what effect going

to the lesser number of welds would have on the seismic

qualification of these cabinets.

This item is considered

unresolved (440/80-16-01; 441/80-15-01).

b.

During this reporting period, the inspector observed several

cable tray supports (hangers) that were accepted by LKC QC

inspectors and documented.

However, the inspector noted in

the area of the intermediate building that touchup painting

of the galvanized material on the inside of cable trays had

been missed (approximately four trays).

The electrical con-

tractor corrected this problem while the inspector was in the

area. The inspector has no further questions on this matter

'

at this time.

c.

During this reporting period, the inspector observed the

installation of conduit throughout the plant.

During review

of LKC QC inspection records, the inspector could not deter-

mine the following:

conduit cut square, reamed, tapered, or

,

'

champfered to remove all burrs and sharp edges, and threaded

ends painted with "Debanode" or equal. From May, 1980 to

August, 1980 in process inspections were documented on LKC

field inspection reports and form #82. There was no documen-

tation prior to May 1980 that indicated that a QC in process

inspection was performed. The inspector could not determine

at this time what effect, if any, not reaming the cut conduit

would have on cable pulls thru these conduits. The licensee

stated that they would investigate this concern.

This item

is considered unresolved (440/80-16-02; 441/80-15-02).

No items of noncompliance or deviations were identified.

5.

Installation of Safety Related Penetrations

The inspector observed work activities including protection, welding

and liquid penetrant (PT) testing of safety-related penetrations.

The inspector observed the welding of the root pass of penetration

a.

F-102, RHR "A" pump suction, in accordance with Drawing B312-631,

Revision D, and field weld process sheet for FW14.

b.

The inspector observed PT testing of the welded root pass' in

,

accordance with Pullman Power Products (PPP) procedure PT-1XPT-1.

c.

During this reporting period, the inspector reviewed qualification

records for two NDE testing personnel (PPP) qualified to perform

FT examinations and verified that their qualifications were current.

l

l

!

-5-

-

'

. .

_ ___-_ _ -

.

.

,

d.

The inspector reviewed Magnaflux materials and purchase orders

.

  1. 7026-F5602 and 7026-F5862, Spotcheck Cleaner SKC-NF, Batch
  1. 80F055. Certifications were current for the above mentioned

material.

No items of noncompliance or deviations were identified.

6.

Observation of Safety Related Piping Welding Activities Unit 1

The inspector observed the following partially completed and

completed welding activities (PPP):

a.

Low Pressure Core Spray System Weld No. 01 on Isometric

No. 1-E21-6.

b.

Low Pressure Core Spray System Weld No. 03 on Isometric

No. 1-E21-3.

c.

Low Pressure Core Spray System Weld No. 05 on I :. metric

No. 1-E21-3.

d.

Residual Heat Removal System Weld No. 01 on Isometric IE-12-44.

c.

Reactor Core Isolation Cooling System Weld No. 03 on Isometric

No. 1-ESI-5.

It was determined that (1) work was conducted in accordance with the

traveler; (2) proper welding materials were used; (3) welding pro-

cedure requirements were met; (4) the work area was free of weld rod

stubs; and (5) physical appearance was acceptable.

No items of noncompliance or deviations were identified.

7.

Control of Welding Materials

i

The inspector toured the PPP welding material issuing station located

at the control complex building.

It was determined that:

a.

The welding materials are properly identified and segregated.

b.

The temperature of the rod ovens is maintained and thermometers

are currently in calibration.

c.

Records are properly kept,

d.

Issuance and return of welding materials are controlled in

accordance with approved procedures.

No items cf noncompliance or deviations were identified.

-6-

.-

.

.

,

8.

Visual Examination of Welds for Safety Related Piping Unit I

.

a.

Visual Examination

The inspector visually examined the following completed welds:

(1) Low Pressure Core Spray System Weld No. 01 on Isometric

1-E21-7.

(2) Low Pressure Core Spray System Weld No. 04 on Isometric

1-E21-3.

(3) Residual Heat Removal System Weld Nos. 03 and 05 on

l

Isometric 1-E12-35.

(4) Residual Heat Removal System Weld No. 01 on Isometric

1-E12-44.

(5) Reactor Core Isolation Cooling System Weld Nos. 02, 03,

and 09 on Isometric 1-E51-5.

It was determined that (1) the weld surface finish and appearance

'

were acceptable and there was no evidence of wall thinning due to

j

grinding; and (2) are strikes and weld spatter were not evident.

b.

Review of Records

The inspector reviewed weld data sheets for the above welds.

It was determined that (1) the records indicate specified

inspections were completed and (2) records are clear and

legible.

No items of noncompliance or deviations were identified.

9.

Reactor Coolant Pressure Boundary Piping - Observation of Welding

Activities (Unit 1)

a.

The inspector observed welding of the Reactor Recirculation

System Weld No. B33-1-All on traveller No. T1-B33-10, and

Weld No. B33-1-B7 on traveller No. T1-B33-09.

It was deter-

mined that (1) work was conducted in accordance with traveller;

(2) proper welding materials were used; (3) welding procedure

requirements were met; (4) work area was free of weld-rod stubs;

and (5) physical appearance was acceptable.

l

,

b.

The inspector reviewed radiographic film (RT) for the afore-

mentioned welds. Radiography technique was in accordance

with I&SE Procedure GEP-N-0004, Revision O.

Film review was

acceptable.

f

-7-

,

--

._

_

._

.

.

,

,

f,

c.

The inspector toured the I&SE welding material issuing station

!

located at the Intermediate Building.

It was determined that

l

(1) the welding materials are properly identifi-d and segregated;

(2) the temperature of the rod ovens is maintained; (3) calibra-

tions of temperature gauges are current; (4) records are properly

kept, and (5) issuance and return of welding materials are

controlled in accordance with approved procedures.

No items of noncompliance or deviations were identified.

10.

Reactor Containment Dome - Observation of Welding Activities (Unit 1)

a.

The inspector observed welding activities associated with the

containment dome, and determined the following:

(1) Welding of liner plates was in accordance with NNIC

welding instructions 465-NC-W001/N.

(2) Alignment and fit-up was in accordance with drawing

Nos. 249910-2 and 249910-4B.

(3) The root pass and subsequent layers of the weld were

subjected to visual examination (VT) procedure No. VT

701-N-N003, Revision A, and radiographic examination

(RT) procedure No. RT 465-NC-N002, Revision C.

(4) Containment Spray Header brackets were being welded

to the dome. The inspector observed that the welds

were in accordance with drawings 249905 series, except

the drawing indicated a 1/16" maximum fit-up tolerance

which could not be met.

The contractor issued a Manu-

facturing Problem Report (MPR), No. E-350, to revise

brackets to be trim fitted to the dome to 0-3/16"

tolerance with engineering's concurrence; welds for

these welded brackets were VT and Magnetic Particle

(MT) tested to procedure 465-NC-004 (MT), Revision D,

and were found to be acceptable.

b.

The inspector reviewed the weld history records for the

containment welding activities, and noted that MPR-E-350 was

not listed on the records for the containment brackets.

NNIC

corrected the weld history records immediately. The inspector

had no further questions of the contractor at this time.

No items of noncompliance or deviations were identified.

11.

Other Areas Inspected

a.

The inspector accompanied the licArArc audit team to witness

an in process radiography (RT) co: t performed by Construction

Quality Engineering on Pulle A art - Piodui<a.

Results of the

audit are reported in Audia ;eg i e'

ic. 437, dated August 28, 1980.

-8-

_

.

.

,

During this audit, the inspector reviewed the following concerns

o

which were previously reported in IE Report No. 440/80-12 and

441/80-11:

(1) The RT crews failed to survey and monitor the working areas.

During this inspection, the inspector found that the exposure

areas were properly secured, guarded, and monitored. This

item is acceptable.

(2) The RT crews failed to survey the radiographic camera and

Source guide tube upon completion of the RT.

The inspector

witnessed the survey of the camera and source guide tube

during this inspection and found this item to be acceptable.

b.

During this inspection period, the inspector questioned the

licensee regarding the Ruskin Manufacturing fire dampers

deficiency, which was reported to the NRC as a 10 CFR Part 21

item. There was no documentary evidence that the licensee

performed a cursory review to determine if the deficiency was

reportable under 10 CFR 50.55(e). PNPP Project Administration

Procedure 1501, Revision 1, paragraph 1.2.3, states in part

".

. Utilizing the criteria for reporting deficiencies, etc;

.

this is a project requirement." During the inspector's review

of Drawing D962-605, Revision G, (Reactor Building Annulus

Exhaust Gas Treatment System), and Drawing D912-617, Revision D,

(Fuel Handling Area Ventilation System), both systems were found

to be classified as Nuclear Safety-Related by the A/E. The

inspector informed the licensee that this failure to document a

review to determine if the deficiency is reportable is contrary

to 10 CFR 50, Appendix B, Criterion V; PNPP PSAR, Chapter 17,

Section 17.15 and CEI Corporate Project Administration Procedure

1501, Revision 1, dated March 24, 1980. This item of noncompli-

ance is identified in Appendix A (440/80-16-03; 441/80-15-03).

No items of noncompliance or deviations were identified, except as

noted.

Ut .esolved Items

Unresolved items are matters about which more information is required in

order to ascertain whether they are acceptable items, items of noncompliance,

or deviations. Unresolved items disclosed during this reporting period are

discussed in Paragraphs 4.a and 4.c.

Exit Interview

The inspector met with licensee representatives (denoted in Persons Contacted)

on August 8, 15, 22, and 29, 1980. The inspector summarized the scope and

findings of the inspections performed. The licensee acknowledged the findings.

l

Attachment:

Preliminary Inspection Findings

-9-

.g

-

.0FFICE OF INSPECT 10:1 AND ENTCRC

.

6*

.

_ PRELIMINARY INSPECTION FINDINGS

.

1

LICENSEE

2.

$O

REGIONAL OFFICE

__

dJA

l

,

---

f

bll'Y)10 $

.

.

DOCKET NUMBERS

4.

LICENSE NUMBERS

'O- Ho?.sb- w

CPP F 1t/ t d P2 i d T4' U To

5.

DA E OF INSPECTION

/

"

.

I 6.

'

Wi, thin the scope of the inspection, no items of'nonco/'

i

were found.

mpliance or deviation

..

7.

The following matters are preliminary inspection findi

k

i

ngs:

'

(

.

.

'

e

.

.

.

.

.

.

3.

These preliminary inspection findings will be reviewed by NRC S

.

Manage =ent n't

concerning any enforcementthe Region III Office and they will co"Jespond uith

upervision/

action.

.

you

--

/

,

_ [* /M M9

pgg BBB

p/

.OTTICE OF INSPECTION AND E!;TORCE!!!.f..

'-

' . -

.

PREL1HINARY INSPECTION FINDINGS

.

l

11.

LICENSEE

2.

REGIONAL OFFICE

0 l g t.) e k st h 6 0 2 L Y I L

fjj

'

-

()/kllA

11

.

.

.

3.

DOCKET NUMBERS

4.

LICENSE NUMBERS

5 ., DfTEOFINSPE) TION

fo- 49'o ,'To-W/

CPPB-lWfr cPEeA9 TM-M/fo

~

./

~

J

fa

/

-

.

,

,

_

{

6. .Within the scope of the inspection, no items of noncompliance or deviation

were found.

..

7.hfoll wing matters are preliminary insoecti

u

D

& L _Als o f {x

'

'

,

an

&res~asn

s

a-

s ws

JJk & &

,

-

,&&

,ecaeso, a k.e, an s~2

PNPP

P n

ua

a

umf

~

,

s

'

s

a

8

d'$

sa2m an-

-

Jef %.

pillbereviewedbyNRCSupervis

-.

8.

These preliminary inspection findings

Management n't the Region III Office and they will corr s

nd yit you

l

-

concerning any enforcement action.

.Ga asSAC

clear Regul

ry Commission Inspector

- - -

- - - -

O

%2pdCa%& B-&a woi

'

'

0

(ka'- i,b

'

'

/z a, 2L zA/

.

./ut/4

'

.h pp

"

-

\\

b

~ s,caiu bich pci sro.c -e) m<D

c

M cFA' l?uS2/,

ky a

O

x&

6 M

wpz acp

Jes p as /ow d- aysgra s,f4

'

/ocH2fatf9/l'

My .$b dw.

a . i as

Wpn, al4>iCi?.

'

'

~sy-pe-

r~

uf $yw, y.

ggAec

s

.

n a- /s a m ,

-

.-../98v-

pgGR @@$$5

-

.

p3

-

-

...

%

.

24

\\

d A A y a k d 4 2 w e & {;

wesA u

van

a.

e- p ce L a

,L x

/ E.2 2 s o o l /t

?

u>wAun

OAb

s c xa eurk,

'

@)p<aKp caLA

269 ay g haaR kb Lj

t

exe

y

resm /~sagea g .

ss

w

ce)

- sesx b aey-

adab.

' b i

cow 2ueR

'

xauslaR.

..

,

.

O

.

..

4

. OFFICE OF lt:SPECTION A1;D E!;TORCEt:Et;T

,

,

.

PRELIMINARY INSPECTION FINDINGS

.

1.

LICENSEE

-

2.

RECIONAL OFFICE

cleoe k w/ Eb den

gy2 TE

' ~

U/)) /)'} CI llll

'

a

-

L

DOCKET NWiBERS

4.

LICENSE 1mMBERS

5.

D TE OF INSP CTION

@4Vo Giu49/

GMMK;&AeNY 9R-2 2 To

r

./

.

/

j,

<

{

6.

Vithin the scope of the inspection, no items of' noncompliance or deviation

were found.

..

-

7.

The following matters are preliminary inspection findings:

_

'

]DPA}g

w k S N[Nu

n

A

9'

r

3

d o Ju

,

J

.

.

.

.

'

l

8.

These preli=inary inspection findings will be reviewed by NRC Supervision /

Management at

F

the Region III Office and they will c rrespond ith you

concerning any enforcement action.

~

f(( (f? /(ff & Y&

duc1 car R

atory Commission. Inspector

i

~**'

--

OFFICE OF INSPECTION Al.D ENFORCDIENT

.

PRELIMINARY INSPECTION FINDINGS

'

i

.

1.

LICENSEE

2.

REGIONAL OFFICE

-'

Clevehn) Gedra

plu

TE

--

.

ruuavna s 8 co

.

r

3.

DOCKET NUMBERS

4.

LICENSE NUMBERS

5.

DATE OF INSPE TION

%Wo/ A -@l

CPMifr(!cPMi47 74zs=29 2D

"

"

'

/

,

6.

/

Within the scope of the inspection, no items of noncompliance or deviation

were found.

,

..

7.

The following matters are preliminary inspection findings:

'

N

N

.~

T

.

.

.

I

_.

8.

These preliminary inspection findings vill be reviewed by NRC Supervision /

-

Management at the Region III Office and they will co respond u

concerning any enforcement action.

you

/dW AW

h

U

fuelear Regu

tory Commission Inspector

.

y

4

__

-- -