Responds to NRC Re Violations Noted in IE Insp Rept 50-395/80-21.Corrective Actions:Work Hold Placed on QC Work While Procedures Were Amplified & Clarified
ML19338G401
Person / Time
Site: Summer 
Issue date: 10/03/1980
From: Nichols T
SOUTH CAROLINA ELECTRIC & GAS CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
Shared Package
ML19338G402 List:
References
NUDOCS 8010290198
Download: ML19338G401 (2)


Text

..

ffQ 1>

SOUTH CAROLINA ELECTRIC a GAS COMPANY ecst orrice een vs.

y CoiumalA SoutM CAnouuA eszie e

2c rt

v. ;

T. C. Nicuous JR.

_-m

,]

V,u Paumat aseo Geoise tsums umu. o

.io.,

c October 3, 1980

)

co i

- U. S. Nuclear Regulatory Commission Region II

((,

~

1 101 Marietta Street', N.W.

Atlanta, GA 30303 ATTENTION:

Mr. James P. O 'Reilly, Director

Subject:

V.C. Summer Nuclear Station Unit #1 License CPRP-94, Response to NRC Audit Report 50-

-20_

dated 9/4/80 a __0-395/80-21((>

dated 9/11/80 Gentlemen:

a In response to NRC reports 50-395/80-21 and 50-395/80-20, we have reviewed the information therein contained and find no proprietary information. In addition, we have evaluated the circumstances relating to the item of non-i compliance No. 80-20-01 and provide the following results of that evaluation.

80-20-01 Dealt with failure to follow procedure for fit-up of butt welded pipe.

1.

Cause The time frame in which the fit-up of the butt joint identifled in this item of noncompliance was made, was June-July 1979.

It was at that time that the craf t and constructor's ASME Code QC failed to follow procedures and accepted a fit-up that did not meet criteria. SCE&G believes that this occurrence is further manifestation of the constructor's ASME in-spection program breakdown that was reported in various communications to Region II associated with items 79-35-02, 79-24-02, 80-05-06 and 79-36-04.

The breakdown resulted from any of a combination of factors including some specific procedural inadequacies, and some less specific interpre-tation, training, competency, attitude, and supervision inadequacies.

2.

Immediate Corrective Steps Taken Upon discovery, during this NRC visit, that a potential mismatch and/or 4

underwall condition existed for the specific weld joint in question, i

SCE6G took specific steps to ascertain the adequacy.of the joint. The data associated with this joint was added to that taken and being analized for a generic concern on mismatch and fit-up presently assigned NRC unresolved Item 79-35-05.

SCE&G Engineering and their agents are t'

I y

Page 2 g

October 3, 1980 presently determining what the significance is of some mismatch and underwall conditions in Class 3 Butt Welds.

The conclusions of the actions taken with respect to 79-35-05 will apply to the wold joint in question, as well as all other Class 3 Butt Welds with question-

)

able' fit-up of which SCE&G has cognizance. No specific items of action were determined eppropriate with respect to the failure to follow procedure based on 3. to follow.

L 3.

Corrective Steps to Avoid Future Noncompliance l

j Commensurate with many corrective actions taken in December 1979 and January 1980, with respect to the constructor's ASME code inspection f

program breakdown, certain actions were taken with respect to Class 3 Eutt Welds. A work hold was placed on code QC work at that time while 4

procedures were amplified and clarified, and QC organizations were reorganized, and extensive indoctrination and training took place.

The work hold on Class 3 Butt Welds was released January 2,1980 at j

which time it was determined Class 3 Butt Welds could be made within i

procedural guidelines by properly trained personnel.

SCE6G believes the corrective actions implemented in December 1979 and January 1980, with respect to the many concerns in existence as a result of the 4

constructor's QC breakdown, have eliminated the potential for recur-rence of the procedure violation that occurred in June-July 1979.

4 We trust that you will find _ the SCE6G actions to resolve this item both j

appropriate and satisfactory. Please feel free to contact us if further clarification or information relative to this itcm is needed.

Very truly yours, T. C. Nichols, Jr.

TCN:jfr cc:

B. A. Bursey V. C. Summer G. H. Fischer Bill Williams 4

T. C. Nichols i

E. H. Crews i.

H. T. Babb D. A. Nauman O. S. Bradham

?

0. W. Dixon i

J. B. Knotts, Jr.

Ron Clary I&E (Washington)

NPCF/Whitaker File-i 4

.