Forwards IE Insp Repts 50-010/77-20,50-237/77-19 & 50-249/77-19 on 770628,29 & 0708 & Notice of Violation
ML19338C972
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 08/03/1977
From: Allan J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Brian Lee
COMMONWEALTH EDISON CO.
Shared Package
ML19338C973 List:
References
NUDOCS 8009120715
Download: ML19338C972 (2)


See also: IR 05000010/1977020

Text

<.

- '

._

_ . _ _ _

._. . -

--

-

- - - '

.l

.

..g .

(CENTRAL FILES

-

..

.

.,.

_

.

tun:Tro STArcs

[g ,,cy,o,

NUCLIEAR REGULATORY COMMISSION

~

! i*

2 d.) g"J)f' )

nccion m

/

m woc.ssvetr ao^o

  • didihb.*j')e

o

cten etvu. n.usois som

s,, m,

p

f.UG 3

1977

-

Docket No. 50-10

Docket No. 50-237-

Docket No. 50-249

Commonwealth Edison Company

ATTN:

Mr. Byron Lee, Jr.

Vice President

P. O. Box 767

Chicago, IL 60690

Centlenen:

This refers to the inspection conducted by Messrs. T. H. Essig

-

.

and L. R. Greger of this office on June 28 and 29 and July 8,

1977, of activities at Dresden Nuclear Power Station, Units

4,

~

2, and 3, authorized by NRC Licenses Nc. DPR-2, No. DPR-19, and

No. DPR-25 and to the discussion of our findings with

Mr. Stephenson and others of your staff at the conclusion of

the inspection.

Ine enclosed copy of our inspection report identifies areas

e.amined during the inspection. Within these areas, the

inspection consisted of a selective examination of procedures

and representative records, observations, and interviews with

personnel.

During this inspection, certain of your activities appeared

to be in noncompliance with NRC requirements, as described

in the enclosed Appendix A.

This notice i- sent to you pursuant to the provisions of

Section 2.2W of the NRC's " Rules of Practice," Part 2, Title

10, Code of Federal Regulations. Section 2.201 requires you

-

to submit to this of fice within twenty days of your, receipt

of this notice a written statement or explanation in reply ,

including for each item of noncompliance: (1) corrective

4

action taken and the results achieved; (2) corre.ctive action

to be taken to avoid further noncompliance; and (3) the date

v'.en full compliance will be achieved.

In accordance with Section 2.790 of the URC's " Rules of

Practice," ." art 2, Titic 10, Code of F.edt.t al Regulations,

{

a

y /

l

Ib

8an2+7nr

e P002 GRIGINAL

.

. .

-.

_.

.-

. ..

_.

.-

.

..

..

.~

'

, .4

-

,_.

'

4

-

.

-

w.

.

. .:J .

-

-

..

.

.

..

,

\\

_

,

Commonwealth Edison

-

2'-

Jgyg 3^ jgff'

. Company

.

.

4

copy of this notice, the enclosed inspection report, and your

response to this notice will be placed in the

'RC's Public

Document Room, except as follows.

If this rep <rt contains

information that you or your contractors beliese to be

proprietary, you must apply in writing to this if fice, within

'

twenty days of'your receipt of this notice, to withhold such

"

information from public disclosure. The application must

include a full statement of the reasons for which the infor-

,

I'

mation is ' considered proprietary, and should be prepared so

j

that proprietary information identified in the application

is contained in an enclosure to the application.

j

We will gladly discuss any questions you have concerning this

inspection.

Sinc.erely,

-

(/1\\n

1

i

mun}H.

mes M. Allan, Chie f

1

Fuel Facility and

i

Materials Safety Branch

Enclosures:

1.

Appendix A, Notice of

,

4

Violation

2.

IE Inspection Reports

No. 50-010/77-20, No.

50-237/77-19, and

'

No. 50-249/77-19

cc w/ encl:

!

Mr. B. B. Stephenson,

Station Superintendent

Central Files

Reproduction Unit NRC 20b.

.

PDR

I

Local PDR

)

NSIC

TIC

,

Anthony Roisman, Esq.,

Attorney

.

!

i

a

. . - .

.

_

,.

. _ _ ,

- ,

. . . . ,

.

- . - . .

_-

_ _ .

. - -

,

.-

'

(_

-2-

.

.

.

.

.

a)

Auto start and pump acceleration sequence timing- test

with simulated undervoltagt initiation signals,

b)

At conclusion of (a), verify that overspeed limits are

not exceeded by operating with the condensate pump as

the only load and then shedding that load.

4.

Regulatory Position C.2.6:

Demonstrate ability to synchronize with offsite power while

connected to emergency. load, transfer load to offsite

power, isolate diesel generator, and restore to standby

status.

a)

Specific tests to demonstrate this capability will not

be performed because of the possibility of damage to

the emergency load (existing primary feed pump ~and con-

densate pump) during synchronization.

It is also very

unlikely that this system would ever be operated as

described in this regulatory position because of the

short time duration requirements of the emergency

Joad.

Regulatory Position C.2.7:

Demonstrate ability to switch fuel supply systems,

a)

This position is not applicable to this installation.

The design does not include alternate fuel systems.

.

Regulatory Position C.2.8:

,

Demonstrate that capability to supply emergency load is

not impaired during periodic testing.

a)

Review of circuitry shows that a modification to pro-

vide automatic bypass of the Unit / Parallel and

Isochronous/ Droop control switches would be required

to provide this capability.

The probabil.'.ty of an

.

accident coincident with total loss of offsite power

during a one-hour monthly surveillance test is too

small to warrant such a modification.

D.

Surveillance Tests

1.

Manual remote start diesel & bring generator to full load,

monthly

.

-

2.

125 VDC battery inspection, weekly

-

3.

Diesel fluids inspection, monthly

E.

Conditions for Operation of Unit #1

1.

Temrorary DG & TR 13 inoperable - continued operation

permitted for 7 days

2.-

Neither A nor B primary feedpump in standby - same as E-1

3.

Temporary DG inoperable - priority repair

4.

TR 13 inoperable - priority repair

5.

"A" condensate pump not in standby - priority repair

.

._.

.

--