- port No.:
80-1 Facility:
Crystal River Unit #3 R port Date:
26 September 1980 Occurrence Date:
15 September 1980 Idrntification of Occurrence:
Failure to restore operability to the Meteorological Monitoring Instrumentation channels for more than seven (7) days contrary to Technical Specification 3.3.3.4.
Conditions Prior to Occurrence:
Mode 1 power operation (97%)
Description of Occurrence:
At 0800 the Meteorological Monitoring System power was secured to allow construction workers to relocate the, cables away from a construction project. The construction effort lasted seven (7) days, one (1) hour.
Designation of Apparent Cause:
The cause of this event was the time required to complete the relocation of the cables.
Analysis of Occurrence:
There was no effect upon the general public health or safety.
Corrective Action:
The unique nature of this event precludes the necessity of any further currective action.
Failure Data:
This is the first event of this type and the twelfth report under this specification.