Interim Deficiency Rept Re Primary Containment Relief Valves Supplied by Gpe Controls.Bechtel Review Showed Calculation Assumptions Re Seismic Analysis Require Further Vendor Justification.Next Rept by 801024
ML19337B345
Person / Time
Site: Hope Creek  PSEG icon.png
Issue date: 08/20/1980
From: Martin T
Public Service Enterprise Group
To: Grier B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
Shared Package
ML19337B344 List:
References
10CFR-050.55E, 10CFR-50.55E, NUDOCS 8010020158
Download: ML19337B345 (1)


Text

o, O

Thomas J. Martin Public Service Electric and Gas Company 80 Park Place Newark, N.J. 07101 201/430-8316 Vics Pres; dent Engineering ard Construction August 20, 1980 Mr. Boyce H.

Grier, Director U.

S.

Nuclear Regulatory Commission Office of Inspection and Enforcement Region 1 631 Park Avenue King of Prussia, Pennsylvania 19406

Dear Mr. Grier:

PRIMARY CONTAINMENT RELIEF VALVES 10CFR50.55(e), POTENTIAL SIGNIFICANT DEFICIENCY NO. 1 UNIT HOPE CREEK GENERATING STATION On March 26, 1980 a verbal report was made to Region 1, Office of Inspection and Enforcement representative, Mr.

A.

Cerne advising of a potential significant item regarding the primary containment relief valves supplied by GPE Controls.

Supplemental information was submitted in writing to Region 1, Office of Inspection and Enforcement on April 25, 1980, May 23, 1980 and June 25, 1980 with the indication that the analysis of the potential problem was continuing.

The following is an interim report concerning the potential design deficiency in the primary containment relief valves, GPE Controls Model LD240-447.

Bechtel Power Corraration, PSE&G's Architect Engineer,has completed a review of additional design analysis submitted by GPE Controls.

The current submittal of the vendor documentation to Dechtel has resolved a majority of their concerns.

Results of the review, how-ever, revealed calculation assumptions in the area of seismic analysis which require further justification by the vendor.

The expected completion date of actions, including additional design analysis by GPE Controls and evaluation of design analysis by Bechtel Power Corporation is expected to be completed by October 24, 1980.

PSELG will respond to you at that time.