'o

UNITED STATES

NUCLEAR REGULATORY COMMISSION

T@

[

),

g

~r

REGION 111

'

"

,

$

[

799 ROOSEVELT ROAD

%

,d

GLEN ELLYN, ILLINOIS 60137

AUG 14 G80:

Docket No. 50-483

Union Electric Company

ATTN:

Mr. John K. Bryan

Vice President - Nuclear

Post Office Box 149

St. Louis, MO 63166

Gentlemen:

This refers to the inspection conducted by Mr. W. A. Hansen of this office

on July 1-31, 1980, of activities at Callaway, Unit 1, construction site

authorized by NRC Construction Permit No. CPPR-139 and to the discussion

of our findings with Mr. Weber and others of the Callaway staff at the

conclusion of the inspection.

The enclosed copy of our inspection report identifies areas examined

during the inspection. Within these areas, the inspection consisted

of a selective examination of procedures and representative records,

observations, and interviews with personnel.

During this inspection, certain of your activities appeared to be in non-

compliance with NRC requirements, as described in the enclosed Appendix A.

This notice is sent to you pursuant to the provisions of Section 2.201

of the NRC's " Rules of Practice," Part 2, Title 10, Code of Federal

Regulations. Section 2.201 requires you to submit to this office within

thirty days of your receipt of this notice a written statement or expla-

nation in reply, including for each item of noncompliance: (1) corrective

action taken and the results achieved; (2) corrective action to be taken

to avoid further noncompliance; and (3) the date when full compliance will

be achieved.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,

Title 10, Code of Federal Regulations, a copy of this letter, the enclosures,

and your response to this letter will be placed in the NRC's Public Document

Room, except as follows.

If the enclosures contain information that you or

your contractors believe to be proprietary, you must apply in writing to

this office, within twenty days of your receipt of this letter, to withhold

such information from public disclosure. The application must include a full

statement of the reasons for which the information is considered proprietary,

and should be prepared so that proprietary information identified in the

application is contained in an enclosure to the application.

.

801001U3Ho

Q

. - -

.

e

AUG 1 4 G60

2-

Union Electric Company

-

We will gladly discuss any questions you have concerning this

inspection.

Sincerely,

-

t

.

G. Fiorelli, Chief

Reactor Construction and

!

Engineering Support Branch

'

Enclosures:

1.

Appendix A, Notice

of Violation

2.

IE Inspection Report

No. 50-483/80-20

cc w/encls:

Mr. W. H. Weber, Manager

Nuclear Construction

Central Files

Reproduction Unit NRC 20b

PDR

Local PDR

NSIC

TIC

Regions I & IV

Ms. K. Drey

Mr. Ronald Fluegge, Utility

Division, Missouri Public

Service Commission

>

.

.4

,-e..m..%,=.

e e .

wo- -.

ew.-m,*

= = -- * , * +

e

s

  • - - =* *

__

_