I 3

t v.

l g

Fpridf44 l

Carolins Power & Light Company 3

Company Corresponeence DEC 0 4 $89 SERIAtt NLS-89-315 United States Nuclear Regulatory Commission ATTENTION:

Document Control Desk Washington, DC 20555 l

1 BRUNSWICK STEAM ELECTRIC PLANT, UNIT NO. 2 DOCKET No. 50-324/ LICENSE NO. DPR-62 IE BULLETIN 80-13:

EXAMINATION OF CORE SPRAY SYSTEM SPARGERS I->

Gentlement IE Bulletin 80-13 requires that examinations of the core spray spargers and in-vessel core spray piping be made during each refueling outage. Ihe results-l of these inspections are to be submitted to the NRC within 30 days of comple ting tne examinations.

In accordance with IE Bulletin 80-13, a visual inspection (periodic Test 90.1) of the core opray spargers and in-vessel core spray piping of the Brunswick Steam Electric Plant Unit 2 was completed November 3, 1989.

Carolina Power &

t Light Company (CP&L) has not yet received a final copy of the contractor report evaluating the core spray piping inspections.

Therefore, CP&L will submit the inspection results by Februcry 1,1990.

Please refer any questions regarding this submittal to Mr. Dale B. Bates at L

(919) 546-6154.

Yours very truly,

'~"

q' L. I of in Manage Nuclear Licens*ng Section DBB/bjw (544CRS) cc Mr. S. D. Ebneter Mr. W. H. Ruland i"

.Mr. E. G. Tourigny 8912130495 891204

[

PDR ADOCK 05000324 g

PNV

.-