ML19332E397
| ML19332E397 | |
| Person / Time | |
|---|---|
| Site: | Sequoyah |
| Issue date: | 12/04/1989 |
| From: | Liaw B Office of Nuclear Reactor Regulation |
| To: | Kingsley O Tennessee Valley Authority |
| References | |
| NUDOCS 8912070172 | |
| Download: ML19332E397 (7) | |
See also: IR 05000327/1989019
Text
..
.
.-
. . - - ~ -
- . . - - - ._. - -
- -.
_ - .. - - - -
- - . - -
.
,l
'
'
UNITE 3 states
NUCLEAR CECULATCRY COMMISSION
i
.
,
g
WAA888880700d, D. C. 30005
,
,,,,,
December 4, 1989
'
Docket Nos. 50-327
and 50-328
l
i
Mr. Oliver D. Kingsley, Jr.
Senior Vice President Nuclear Power
Tennessee Valley Authority
6N 38A Lookout Place
1101 Market Street
t
'
Chattanooga, Tennessee 37402-2801
i
Dear Mr. Kingsley:
SUBJECT: NRC INSPECTION REPORT NOS. 50-327/89-19 AND E0-328/89-19
'
By letter dated October 2,1989, you responded to our Notice of Violation which
l
'
.
was issued on August 28, 1989,
facility.
concerning activities conducted at your Sequeyeh
We have evaluated your respo,nse to Violation A and found that it mee
-
,
requirements of 10 CFR 2.201. We will examine im
-
to correct Violation A during future inspections.plementation of your actions':
'
.
'
,
After careful consideration of the bases for your denial of Violation 8, we
,
'have concluded, for the reasons presented in the enclosure to this letter that
the violation occurred as stated in the Notice of Violation.
Therefore,In
!
accordance with 10 CFR 2.201(a), please submit to this office within 30 days
'
of the date of this letter a written statement describing steps which have been
taken to correct Violation B and the results achieved, corrective steps which
,
i
will be taken to avoid further violations, and the date when full compliance
will be achieved.
c',
In reaching this conclusion regarding Violation B we are concerned about your
.
entry into Limiting Condition for Operation (LCO),3.0.3.
It could be perceived
that such entry was made to allow Unit 1 to continue operating at 100 percent
power beyond the 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> of Action Statement 2.d of Specification 3.3.1.1 to
complete the thirCattempt to measure the quadrant power tilt ratio. . The staff
.
'
would like to reiterate its view on voluntary entry into LC0 3.0.3.
As stated
in Generic Letter 8/-09. "... entry into LC0 3.0.3 is not intended to be used as
,
an operational convenience ... Its intended purpose is to provide guidance on
the time limits for an ' orderly' shutdown when the individual LC0 or action
statements cannot be complied with."
Action 2.c of Specification 3.3.1.1 allows the operators to reduce the power
range neutron flux high trip to respond to an inoperable power range encore
detector.
We understand that the control room operators did not have a
procedure to perform this action. We would expect that procedures would be
'
in place to allow the operators the full range of options permitted to meet the
,
\\
8912070172 891204
Fl(0
.PDR
ADOCK 05000327
b
'
O
h
,
.
.W
.
,.
!
.
+
,
,
I
Mr. Oliver D. Kingsley, Jr.
-2
December 4,
1989
action statements in the Technical Specifications. The lack of procedures to
carry out Technical Specification actions can unnecessarily challenge the
operators. The staff would like to be informed of your actions with respect
to this issue.
The involvement of TVA management in the decisions for this event show an active
mana9erial role in the operations at Sequoyah,
The responses directed by this letter and its enclosure are not subject to the
-
clearance arocedures of the Office of Management and Budget as required by the
Paperwork leduction Act of 1980, Pub. L. No. 96 511.
We appreciate your cooperation in this matter,
f
Sincerely,
Original signed by
i
'
D.D.Uaw
B. D. Liaw, Director
TVA Projects Division
Office of Nuclear Reactor Regulation
Enclosure:
'
Evaluations and Conclusions
cc w/ enclosure:
See next page
Distribution
Docket tile
NRC PDR
Local PDR
SQN Reading
ADSP Reading
DCrutchfield
BDLiaw
SCBlack
-RCPierson
'
JJWatson
JBBrady
-JRutberg
JDonohew
- SEE PREVIOUS CONCURRENCE
OFC s hRR:'
/PM* :TVA:lP/SQN
TVA:AD/TP*
- A
/P*
- TVA:AD/IP
- T)
- AD! :D
.....:....
.....:............:............:
...:...... 7 ..:...
....:.L
NAME :
( ew:as :LWatson
RPierson
- BWilson
- BDL w
- DC'
id
.....:
.........:............:............:............:............:............:.........
- / /89
- 11/30/89
- g/$l/89
- 11/jp/89
- W/ol /89
- (4/( /89
DATE : g/g/89
0FFICIAL RECORD COPY
Document Name: TVA'S DENIAL
. .
_
_ _ _ . . . . _ . _ . _ . _ _ _ . . . . _ _ . . - . _ . . _ _ _ . _ _ . _ . _ _ -
. , z.g
.
L
.Mr. Oliver D. Kingsley, Jr.
'-3-
December 4, 1989
1
cc w/ enclosures
.
General Counsel
-
Mr. Kenneth M. Jenison
Yennessee Valley Authority
Senior Resident Inspector
400 West Summiit Hill Drive
Sequoyah Nuclear Plant
ET 118 33H
U.S. Nuclear Regulatory Commission
hioxville, Tennessee 37902-
2600 IJou Ferry Road
Soddy )aisy Tennessee 37379
- Mr. F. L. Moreadith-
Vice President.-Nuclear Engineering
Mr. Michael H. Mobley, Director
Tennessee Valley Authority
Division of Radiological Health
400 West Simmit Hill Drive
T.E.R.R.A. Building 6th Floor
WT 12A 12A
150 9th Avenue North
Knoxville, Tennessee 37902
Nashville Tennessee 37219-5404
Dr. Mark 0. Medford
Dr. Henry Myers, Science Advisor
!
Vice President and Nuclear
Committee on Interior
Technical Director
and Insular Affairs
Tennessee Valley Authority
U.S. House of Representatives
.i
6N 38A Lookout Place
Washington, D.C.
20515
Chattanooga, Tennessee 37402-2801
Tennessee Valley Authority
Manager, Nuclear Licensing
Rockville Office
and Regulatory Affairs
11921 Rockville Pike
Tennessee Valley Authority
Suite 402'
- -
SN 1575 Lookout Place
Rockville, Maryland 20852
l
Chattanooga, Tennessee 37402-2801
Mr. Joseph Bynum.
Acting Site Director
Sequoyah Nuclear Plant
Tennessee Valley Authority
P. O. Box 2000
Soddy Daisy, Tennessee 37379
Mr. Mark J. Burzynski
Site Licensing Manager
Sequoyah Nuclear P.lant
P. O. Box 2000
-
Soddy Daisy. Tennessee 37379
l
County Judge
Hamilton County Courthouse
Chattanooga, Tennessee 37402
Regional Administrator, Region II
U.S. Nuclear Regulatory Commission
101 Marietta Street, N.W.
Atlanta, Georgia 30323
'
..
.
-.
- _ .
.
.
.
.
- - . .
_
__ _ _ . _ _ . _ . .
_ _ _ _ _ _ _ _ . _ _ . _ _
_. _ _ _
_
c.:
.
<
.
..
.
.,
l
ENCLOSURE
.
EVALUATIONS AND CONCLUSIONS
i
On August 28, 1989, a Notice of Violation (Notice) was issued for a violation
identified during a routine NRC inspection. TVA responded to the Notice on
October 2, 1989. TVA denies that Violation B is a violation. The NRC's
.
evaluations and conclusions regarding the licensee's arguments are as follows:
j
Restatament of Violation B
Technical Specification 3.0.1 states that upon failure to meet a Limiting
Condition for Operation, the associated Action requirements shall be met.
,
Technical Specification 3.3.1 states that as a minimum, the reactor trip system
instrumentation channels and interlocks of Table 3.3-1 shall be operable with
response times as shown in Table 3.3-2.
Action Statement 2 of TS 3.3.1,
states that with the number of operable channels one less than the total number.
of channels, startup and power operation may proceed provided conditions 24
through 2.d are met.
Action 2.d states that the quadrant power tilt ratio (QPTR), as indicated by-
the remaining three detectors, shall be verified consistent with the normalized
i '
L
symmetric power distribution obtained by using the movable incore detectors in
the four pairs of symmetric thimble locations at least once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> when
thermal power is greater than 75 percent of rated thermal power.
L
On July 22, 1989, the Unit I reactor trip system power range channel N43
l
failed.
The licensee entered Action Statement 2.d.
,
Contrary ~to the above, the licensee failed to reduce power to less than or
equal to 75 percent of rated thermal power to meet Action Statement 2.d when
- an incore flux map to verify the QPTR could not be completed within the 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />
required by Action Statement 2.d.
.
Sunnary of Licensee's Response
The 11consee dentes that its failure to reduce power to less than 75 percent of
rated thermal power constitutes a violation. The licensee believes a condition
existed that was not pmvfded for in the action statements of LCO 3.3.1.1 and
that entry into and compliance with LCO 3.0.3 were correct from both a
L
regulatory compliance and reactor safety standpoint.
The licensee argues that
action statement 2.d does not require reduction to 75 percent power. The
licensee states that the violation implies that LC0 3.0.3 cannot be entered if
a licensee could have previously taku action including mwer reduction to
prevent it (i.e.. TVA should have reduced power before tw expiration of the
2.d action statement to less than 75 percent so that action statement 2.d would
no longer be applicable).
.
--
- , , .
.
-
-
m
..7--w.-e-m
. .
.
m,
. -
-
--
. m------o-
m.
-- --a=w.- -mmsm--
-ss-.-.-
_._.
. _ . .
_ . _ _ _ . _ .____.
. . _ . _ _ _ _ _ _ _ _ _ . _ _ _
,o,
e
t
2
,
,, l u
h&
"
L
.
..
The licenses dese< net eensider that imediate reduction in power was the
,
conservettve er~ reget:wd action to take upon expiration of the initial-12-hour
)
,
action statement nor that unnecessarily introducing a plant transient as a
i
L
result of potential loss of monitoring would have been conservative in
L
consideration of all factors.
'
The licensee believes that the decisions made in this situation were
technically sound with foremost consideration to safe and prudent plant
operation. The licensee additionally believes operations were conducted
conservatively and in full compliance with associated technical specifications.
,
The licensee requests that the subject violation be withdrawn.
NRC Evaluation
L
The licensee has denied violation 327,328/89-19-07 on the basis that Limiting
'
E
Condition for Operation (LC0) 3.0.3 was appro
l
statement 2d of Technical Specification (TS) priately entered when action
3.3.1.1 was not met within the
!
specified time allowance. Upon failurs of a power range monitor, action
!
statement 2d requires that the Quadrant Power Tilt Ratio (QPTR) be verified to-
L
be consistent with an incore detector power distribution at least once ever
hours when themel power is greater than 75 percent of rated themel power.y 12.
E
(-
With 56 minutes remining in the action statement time limit, the licensee had
y
not successfully completed a flux map and the Assistant Shift Operations
L
Supervisor was notified that an additional flux map would be required.
Instead
'
of innediately initiating a reduction to 75 percent power, a decision was made
'
by the Operations Superintendent to invoke the provisions of TS 3.0.3
applicable when LCO action statements are not met.
The denial letter states
that'this. decision was made because initiating a plant transient by reducing
power was not considered the most prudent course of action.
The flux map was
completed approximately 17 hours1.967593e-4 days <br />0.00472 hours <br />2.810847e-5 weeks <br />6.4685e-6 months <br /> after the failure of the power range monitor.
The licensee's denial of the violation does not address the requirement of
TS 3.0.1 to meet action statement requirements when an LC0 is not met.
The-
denial letter states that the violation implies that LC0 3.0.3 cannot be
4
!
entered if a licensee could have previously taken action. including power
reduction, to prevent it. This is not the purpose of the vio!ation.
LCO 3.0.3 may be entered at any time if the purpose is to initiate an orderly
'
shutdown of the un~1t. as discussed below.
The bases of the Sequoyah Technical Specifications, as well as the NRC
posities. contained in Generic Letter 87-09 and Part 9900 of the NRC Inspection
Manual, provide technical guidance pertaining to the use of LC0 3.0.3.
The
technical. specification bases for Section 3.0.3 state that "3.0.3 delineates
the action to be taken for circumstances not directly provided for in the
action statements and whose occurrence would violate the intent of the
specification." Generic Letter 87-09 and the Inspection Manual state that
" entry into LCO 3.0.3 is not intended to be used as an operational convenience
- which pemits redundant. safety systems to be out of service for a limited
period of time.
Its intended purpose is to provide guidance on the time limits
for an ' orderly' shutdown when the individual LC0 or action statements cannot
be complied with." The above guidance makes it clear that LCO 3.0.3 does not
-
--,n
. - - - - . . . . - . - . . . . - - - -
- .
- - - - -
- - . . - -
.
- . - .
- -
.
-
- - - -
- - - . .
.
-
-.,
.
.
-
(.:
'
.-
'
s
(
,
,
relieve the licenseerfrom meeting those requirements of an LCO action
statement which can be met. The incore probes used to obtain the flux map and
verify that the QPTR is within limits essentially act as a redundant core
j
monitoring system for the power range excore detectors.
.
The denial letter states that the licensee considered reducing power within 12
hours to comply with the action statement requirements, but chose instead to
enter TS 3.0.3.
Paragraph 9.c of inspection report 327,328/89-19 stated that
the shift supervisor intended to reduce power to 75 percent prior to the end of
the LC0 3.0.3 action time requirement rather than shut down to mode 3 as required
by the LCO 3.0.3 action statement. The licensee states in the response that_
'
this plan was justified by the provisions of TS 3.0.2, since the LC0
requirements of TS 3.3.1.1 could then be met.
,
,
In effect, the licensee used the requirements of TS 3.0.3 to extend the TS 3.3.1.1 action requirweents until either an acceptable flux map was performed
(allowing exit of LC0 3.0.3 via LCO 3.0.2, which occurred in this case) or the
L
remaining LCO 3.0.3 action time had run sufficientl
power to 75 percent would allow exiting LCO 3.0.3 (y low that reduction ino j
via LC0 3.0.2) prior tea W ,
,
l
having to be in mode 3.
The fact that the licensee planned to reduce poser 103
l
75 percent prior to the expiration of TS 3.0.3 is evidence that the TS 3.3.1.1-
requirements were clear to the licensee and that the requirements could else.
L
have been met-by such a power reduction before LCO 3.0.3 was entered.
'
The Basis of TS 3/4.2.4 states that the quadrant power tilt ratio limit assures
that the radial power distribution satisfies the design values used in the
power capability analysis.
The clear intent of TS 3.3.1.1 and surveillance
requirement 4.2.4.2 is to limit to 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> the period of operation above 75
percent power with an unmonitored quadrant.
However, the licensee operated at
approximately 100 percent power for 17 hours1.967593e-4 days <br />0.00472 hours <br />2.810847e-5 weeks <br />6.4685e-6 months <br /> after the power range instrument
'siled (five hours after the expiration of TS 3.3.1.1) without adequate
monitoring of the quadrant with the failed power range monitor. Although the
licensee's response stated that TVA considered a reduction in power not to be
the conservative or required action, the NRC staff believes that the reasonable
o
and conservative approach would have been to reduce power to 75 percent to
E
meet the action requirements of TS 3.3.1.1, as required by TS 3.0.1, rather
than continuing operation at 100 percent power with an unmonitored quadrant.
(
l
The dental letter states that out-of-limit conditions did not exist and uses
i -
this assumption as additional justification for not initiating a power
reduction within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />, and for not reducing power upon entry into TS 3.0.3.
As the quadrant associated with the failed power range detector was unmonitored
for 17 hours1.967593e-4 days <br />0.00472 hours <br />2.810847e-5 weeks <br />6.4685e-6 months <br />, it is unclear how the lack of out-of-limit conditions on other
parameters assured that a quadrant power tilt did not exist in the unmonitored
-
quadrant.
l
!
i
i
I
-
_ _ . _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . . _ _ - _ _ . _ _ ,
1
1
I.*
_
4
., 7 .-
t l--
'
,
<
NRC Centingler
'
6
.The staff does not agree that the licensee could not comply with the
l
n.
requirements of TS 3.0.1 and 3.3.1.1; does not agree that the licensee's
decision to not reduce power was either conservative or prudent; and does not
'
agree that the licensee used LC0 3.0.3 as intended by the technical
specifications to provide for an orderly shutdown. Therefore the violation
stands.as wr1tten.
,
5
f
.'
-
.
t
m.
J
l
1
.~
1
.
. .- .
. .
-
.
.
. ..