Forwards IE Insp Repts 50-010/80-13,50-237/80-14 & 50-249/80-18 on 800707-0801 & Notice of Violation
ML19332B269
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 08/18/1980
From: Heishman R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Reed C
COMMONWEALTH EDISON CO.
Shared Package
ML19332B270 List:
References
NUDOCS 8009260395
Download: ML19332B269 (2)


See also: IR 05000010/1980013

Text

. _ _ _ _ _ _ _ _ _ _ _ _

___

___ ___ ____

TIC

E

gf

'o,,

UNITED STATES

NUCLEAR REGULATORY COMMISSION

g

3 .,.,

g

e e

REGION ill

L

% * . , * d'[

799 ROOSEVELT ROAD

5

Q.

GLEN ELLYN, ILLINOIS 60137

'

AUG 18 G80-

Docket No.50-010

Docket No. 50-237

Docket No. 50-249

Commonwealth Edison Company

ATTN:

Mr. Cordell Reed

Vice President

Post Office Box 767

Chicago, IL

60690

Gentlemen:

This refers to the routine inspection conducted by Messrs. R. L. Spessard,

J. F. Streeter, F. W. Maura, J. L. Barker, T. M. Tongue, R. Walker,

F. Reimann, and R. Schulz of this office on July 7 to August 1, 1980, of

activities at Dresden Nuclear Power Station authorized by NRC Operating

License No. DPR-2, DPR-19, and DPR-25; and to the discussion of our

findings with Mr. B. Shelton and others of your staff at the conclusion

of the inspection.

The enclosed copy of our inspection report identifies areas examined

during the inspection. Within these areas, the inspection consisted of a

selective examination of procedures and representative records, observa-

tions, and interviews with personnel.

During this inspection, certain of your activities appeared to be in

noncompliance with NRC requirements, as described in the enclosed

Appendix A.

This notice is sent to you pursuant to the provisions of Section 2.201 of

the NRC's " Rules of Practice," Part 2, Title 10, Code of Federal Regula-

tions. Section 2.201 requires you to submit to this office within twenty

days of your receipt of this notice a written statement or explanation in

reply, including for each item of noncompliance: (1) corrective action

taken and the results achieved; (2) corrective action to be taken to

avoid further noncompliance; and (3) the date when full compliance will

be achieved.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part

2, Title 10, Code of Federal Regulations, a copy of this letter, the

enclosures, and your response to this letter will be placed in the NRC's

Public Document Room, except as follows.

If the enclosures contain

80092803 5

-

_ _ _ - - - . .

-.

.

..

_.

.

O

Commonwealth Edison Company

-2-

'

AUG 18 $80~

l

information that you or your contractors believe to be proprietary, you

must apply in writing to this office, within twenty days of your receipt

of this letter, to withhold such information from public disclosure'. The

application must include a full statement of the reasons for which the

information is considered proprietary, and should be prepared so that

proprietary information identified in the application is contained in an

enclosure to the application.

We will gladly discuss any questions you have concerning this inspection.

Sincerely,

,

,

'h?iS'

&

pu

. F. Heishman, Chief

Reactor Operationr and

Nuclear Support Branch

Enclosures:

1.

Appendix A, Notice of

Violation

2.

IE Inspection Report No.

50-10/80-13; 50-237/80-14;

and 50-249/80-18

cc w/ encl:

Mr. J. S. Abel, Director of

Nuclear Licensing

,

Mr. D. J. Scott, Station

i