Requests Transfer of Lead Responsibility for Review of Repair Method for Containment Dome Separation from IE to Licensing
ML19329D682
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 04/29/1976
From: Long F
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Seyfrit K
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE)
Shared Package
ML19329D683 List:
References
NUDOCS 8003160303
Download: ML19329D682 (1)


Text

.~

)

UNITED STATES

^'

l'a NUCLEAR REGULATORY COMMISSION yy, 2-3 1 S

REGloN 11

/pj 33a ecAcuract svas:T. u. w. suiic sia 5, - j ATL. ANT A, C Eo RGI A 30303

    • .e*'

April 29, 1976 K. V. Seyfrit, Reactor Technical Assistant Branch, Office of Inspection and Enforcement, Headquarters 7 THRU: Norman C. Moseley, Director, Office of Inspection and Enforcement, f

Region II 4

FLORIDA POWER CORPORATION, CRYSTAL RIVER 3 (DN 50-302), 'ONTAINMENT DOME SEPARATION - REQUEST FOR TRANSFER OF LEAD RESPONSIBILIIY FPC has discovered a separation of the concrete of the containment doce.

(Morning report April 19, 1976)

The utility is currently investigating the extent of damage and evaluating methods for repairing the structure.

Enclosed is a copy of the preliminary notification issued by Region II on April 19, 1976, and the preliminary 50.55e report from FPC, dated April 21, 1976.

It is requested that lead responsibility for review and acceptance of the repair method be transferred to Licensing.

M c_ 4.._ /b L

F. J. Long, Chief Reactor Operations and Nuclear Support Branch

Enclosures:

1.

Preliminary Notification 2.

FPC letter to NRC dated

. April 21, 1976 h

cc:

F. Jap'e, IE:II i

C. E. Murphy, IE:I' I

H. D. Thornburg, IE:HQ

)

1 a

1 I

i

)

1 8003160 JOJ g j

.. _ _ _. y i

- - -